This study identified 10 most important causes of delay from a list of 28 different causes and 6 different effects of delay. Ten most important causes were: (1) contractor’s improper planning, (2) contractor’s poor site management, (3) inadequate contractor experience, (4) inadequate client’s finance and payments for completed work, (5) problems with subcontractors, (6) shortage in material, (7) labor supply, (8) equipment availability and failure, (9) lack of communication between parties, and (10) mistakes during the construction stage. Six main effects of delay were: (1) time overrun, (2) cost overrun, (3) disputes, (4) arbitration, (5) litigation, and (6) total abandonment.
Trang 1Causes and effects of delays in Malaysian construction industry
Graduate School of Management, Universiti Putra Malaysia, 43400 UPM, Serdang Selangor, Malaysia Received 21 April 2006; received in revised form 27 June 2006; accepted 21 November 2006
Abstract
The problem of delays in the construction industry is a global phenomenon and the construction industry in Malaysia is no exception The main purpose of this study is to identify the delay factors and their impact (effect) on project completion Earlier studies either con-sidered the causes or the effects of project delays, separately This study takes an integrated approach and attempts to analyze the impact
of specific causes on specific effects A questionnaire survey was conducted to solicit the causes and effects of delay from clients, consul-tants, and contractors About 150 respondents participated in the survey This study identified 10 most important causes of delay from a list of 28 different causes and 6 different effects of delay Ten most important causes were: (1) contractor’s improper planning, (2) con-tractor’s poor site management, (3) inadequate contractor experience, (4) inadequate client’s finance and payments for completed work, (5) problems with subcontractors, (6) shortage in material, (7) labor supply, (8) equipment availability and failure, (9) lack of commu-nication between parties, and (10) mistakes during the construction stage Six main effects of delay were: (1) time overrun, (2) cost over-run, (3) disputes, (4) arbitration, (5) litigation, and (6) total abandonment This study has also established an empirical relationship between each cause and effect
Ó 2006 Elsevier Ltd and IPMA All rights reserved
Keywords: Delay causes; Delay effects; Construction industry; Malaysia; Correlational analysis
1 Introduction
The problem of delays in the construction industry is a
global phenomenon In Saudi Arabia, Assaf and Al-Hejji
[6]found that only 30% of construction projects were
com-pleted within the scheduled completion dates and that the
average time overrun was between 10% and 30% In
Nige-ria, Ajanlekoko [2] observed that the performance of the
construction industry in terms of time was poor Odeyinka
and Yusif[16]have shown that seven out of ten projects
sur-veyed in Nigeria suffered delays in their execution
Ogunl-ana and Promkuntong [17] conducted a study on
construction delays in Thailand Al-Momani [5] carried
out a quantitative analysis on construction delays in
Jor-dan Frimpong et al [10] conducted a survey to identify
and evaluate the relative importance of the significant
fac-tors contributing to delay and cost overruns in Ghana groundwater construction projects Chan and Kumarasw-amy[8]studied delays in Hong Kong construction industry They emphasized that timely delivery of projects within budget and to the level of quality standard specified by the client is an index of successful project delivery Failure
to achieve targeted time, budgeted cost and specified quality result in various unexpected negative effects on the projects Normally, when the projects are delayed, they are either extended or accelerated and therefore, incur additional cost The normal practices usually allow a percentage of the pro-ject cost as a contingency allowance in the contract price and this allowance is usually based on judgment [3] Although the contract parties agreed upon the extra time and cost associated with delay, in many cases there were problems between the owner and contractor as to whether the contractor was entitled to claim the extra cost Such sit-uations, usually involved questioning the facts, causal fac-tors and contract interpretation [4] Therefore, delays in
0263-7863/$30.00 Ó 2006 Elsevier Ltd and IPMA All rights reserved.
doi:10.1016/j.ijproman.2006.11.007
*
Corresponding author Tel.: +60 389467698; fax: +60 389434019.
E-mail address: murali@econ.upm.edu.my (M Sambasivan).
www.elsevier.com/locate/ijproman International Journal of Project Management 25 (2007) 517–526
PROJECT MANAGEMENT
Trang 2construction projects give rise to dissatisfaction to all the
parties involved and the main role of the project manager
is to make sure that the projects are completed within the
budgeted time and cost The construction sector in
Malay-sia, a fast developing country in South-East Asia has not
escaped the problem of delays In 2005, about 17.3% (of
417 government contract projects in Malaysia) were
consid-ered sick (more than 3 months of delay or abandoned)
The Construction Sector is one of the important sectors
that contribute to Malaysia’s economic growth The sector
accounted for nearly 3.3% of GDP in the year 2005 and
employed about 600,000 workers including 109,000 foreign
workers (MALBEX[12]) The huge volume and complexity
of projects in Malaysia’s construction sector pose a great
challenge and provide a wealth of opportunities to various
companies in the construction industry The construction
sector in Malaysia can be divided into four broad
catego-ries: office, retail, residential and infrastructure This sector
suffered a temporary crisis between 1997 and 2000 (ASEAN
crisis) and now it has started to improve However, the
delays in the projects continue to occur The main purpose
of this study is to identify the delay factors and their impact
(effect) on project completion Earlier studies either
consid-ered the causes or the effects of project delays, separately
This study takes an integrated approach and attempts to
analyze the impact of specific causes on specific effects
Some causes and effects of delays in construction projects
can be country-specific The logical question at this point
is: Why is it necessary to link the causes and effects of delays
and how can the link help the practitioners to prevent or
remedy future delays? In this research, we identified major
causes of delay and categorized them as client-related,
con-tractor-related, consultant-related, material-related,
labor-related, contract-related, contract relationship-related,
and external factors We have also identified major effects
of delay as: time overrun, cost overrun, dispute, arbitration,
litigation, and total abandonment Identification of causes
and effects alone does not help the project managers to take
appropriate remedial or preventive steps The project
man-agers need to understand, for example, what causes or
fac-tors result in time overrun or cost overrun Once these
factors become clear, the managers can take proactive steps
to avoid such situations For example, if it is known that
time overruns are predominantly caused by client-related
factors, the project manager can: (1) make sure that
pay-ments for the completed work are paid on time, (2) reduce
owner interference, (3) speed up the decision-making
pro-cess, and (4) avoid unrealistic contract duration and
requirements Therefore, the link between causes and effects
of delays need to be established
This paper is organized as follows Section2 deals with
the previous studies on causes and effects of delays in
pro-jects Section3 explains the methodology of research
Sec-tion 4 discusses the analysis the data using statistical
procedures Section 5 discusses the results Section 6
pre-sents the strategies for reducing delays in construction
pro-jects and Section7presents the conclusions
2 Previous studies Many researchers have studied the causes and few researchers have studied the effects of project delays in the construction industry We have broken the studies into two parts: (1) Studies on causes of delay and (2) Studies on effects of delay
2.1 Studies on causes of delay Mansfield [14] identified 16 major factors that caused delays and cost overruns in Nigeria A questionnaire sur-vey was carried out with contractors, consultants and client organizations in Nigeria They presented that the causes of delay and cost overruns in Nigerian construction projects were attributed to finance and payment arrangements, poor contract management, shortages in materials, inaccu-rate estimation, and overall price fluctuations
Assaf et al [7] identified 56 main causes of delay in Saudi large building construction projects and their relative importance Based on the contractors surveyed the most important delay factors were: preparation and approval
of shop drawings, delays in contractor’s progress, payment
by owners and design changes From the view of the archi-tects and engineers the cash problems during construction, the relationship between subcontractors and the slow deci-sion making process of the owner were the main causes of delay However, the owners agreed that the design errors, labor shortages and inadequate labor skills were important delay factors
Ogunlana and Promkuntong[17]conducted a study on construction delays in Thailand They found that the prob-lems faced by the construction industry in developing econ-omies like Thailand could be: (a) shortages or inadequacies
in industry infrastructure (mainly supply of resources); (b) caused by clients and consultants and (c) caused by con-tractor’s incompetence/inadequacies They recommended that there should be concerted effort by economy managers and construction industry associations to provide the nec-essary infrastructure for efficient project management Chan and Kumaraswamy [8] conducted a survey to determine and evaluate the relative importance of the sig-nificant factors causing delays in Hong Kong construction projects They analyzed and ranked main reasons for delays and classified them into two groups: (a) the role of the parties in the local construction industry (i.e whether client, consultants or contractors) and (b) the type of pro-jects Results indicated that five major causes of delays were: poor site management and supervision, unforeseen ground conditions, low speed of decision making involving all project teams, client initiated variations and necessary variations of works
Odeyinka and Yusif [16] have addressed the causes of delays in building projects in Nigeria They classified the causes of delay as project participants and extraneous factors Client-related delays included variation in orders, slow decision-making and cash flow problems
Trang 3Contrac-tor-related delays identified were: financial difficulties,
material management problems, planning and scheduling
problems, inadequate site inspection, equipment
manage-ment problems and shortage of manpower Extraneous
causes of delay identified were: inclement weather, acts of
nature, labor disputes and strikes
Al-Momani [5] carried out a quantitative analysis on
construction delays in Jordan The result of his study
indi-cated that the main causes of delay in construction of
pub-lic projects were related to designers, user changes,
weather, site conditions, late deliveries, economic
condi-tions and increase in quantity Similarly, Odeh and
Battai-neh [15]also conducted a survey aimed at identifying the
most important causes of delays in construction projects
with traditional type of contracts from the viewpoint of
construction contractors and consultants Results of the
survey indicated that contractors and consultants agreed
that owner interference, inadequate contractor experience,
financing and payments, labor productivity, slow decision
making, improper planning, and subcontractors were
among the top ten most important factors
Frimpong et al.,[10]conducted a survey to identify and
evaluate the relative importance of significant factors
con-tributing to delay and cost overruns in Ghana groundwater
construction projects A questionnaire with 26 factors was
carefully designed from preliminary investigations
con-ducted in groundwater drilling projects between 1970 and
1999 in Ghana The questionnaire was directed towards
three groups in both public and private organizations:
owners of the groundwater projects, consulting offices,
and contractors working in the groundwater works The
questionnaire was distributed to a random sample of 55
owners, 40 contractors and 30 consultants The result of
the study revealed the main causes of delay and cost
over-runs in construction of groundwater projects: monthly
payment difficulties from agencies; poor contractor
man-agement; material procurement; poor technical
perfor-mance; and escalation of material prices
Assaf and Al-Hejji[6]conducted a survey on time
per-formance of large construction projects in Saudi Arabia
The survey had 73 different causes of delay He studied
the importance of various causes from the viewpoint of
contractors, consultants, and owners The most common
cause of delay identified by all the parties was ‘‘change
order’’ He also found that about 70% of the projects
expe-rienced time overruns
2.2 Studies on effects of delay
Aibinu and Jagboro[1]studied and evaluated the effects
of construction delays on project delivery in Nigerian
struction industry They found that the six effects of
con-struction delay were: time overrun, cost overrun, dispute,
arbitration and litigation and total abandonment The
questionnaires were sent to three groups of construction
practitioners: quantity surveyors, architects and engineers,
and contractors
Manavazhia and Adhikarib [13]conducted a survey to investigate material and equipment procurement delays in highway projects in Nepal Delay in the delivery of materi-als and equipment to construction sites is often a contribu-tory cause to cost overruns in construction projects in developing countries An assessment of the causes of the delays and the magnitude of their impact on project costs were also made The survey method was used in conducting this research involving 22 highway projects The main causes of material and equipment procurement delays were found to be (in rank order) organizational weaknesses, sup-pliers’ defaults, governmental regulations and transporta-tion delays However, the actual impact of these delays
on project costs was found to be on average, only about 0.5% of the total budgeted cost of the projects Among materials, delays in the supply of aggregates and equipment were found to occur most frequently
Chan and Kumaraswamy[9]explored strategies of com-pressing construction durations of various types of build-ing projects on the basis of the lessons learned from Hong Kong based surveys and other research findings The literature from different countries on the factors affect-ing construction durations, reasons for project delays and existing statistical models for duration forecasts were reviewed A regression-based model developed from Hong Kong public housing construction project data was used for predicting the durations of the primary work packages
in the building process and the overall completion period And finally, a survey was conducted by the researchers to explore the construction time performance of projects in three building sub-sectors (i.e public housing, public non-residential and private sector) Based on the factors identified as significant from the above research, specific technological and managerial strategies for reducing con-struction periods in particular building sub-sectors were formulated in order to improve the construction time per-formance of Hong Kong building projects
Terry Williams [19] studied the standard methods cur-rently available for assessing extension of time delays on major projects, and issues around such assessment He used network causal mapping and system dynamics approach to study the impact of delays on a project
Based on the above studies, it can be inferred that the earlier studies concentrated on either the causes or the effects However, some studies have alluded to the probable link between the causes and effects of delays without a sys-tematic analysis Manavizha and Adhikarib[13]linked the material-related causes to the probable cost overruns in construction projects in Nepal Assaf and Al-Hejji[6]linked the contractor-related and labor-related causes to the prob-able time overruns in construction projects in Saudi Arabia Odeh and Battaineh[15]linked the contract-linked causes
to the probable disputes occurring in construction projects
in Jordan Chan and Kumaraswamy[8]linked the consul-tant-related and client-related causes to the probable time overruns in construction projects in Hong Kong Mansfield
et al.[14]and Frimpong et al.[10]linked the client-related,
Trang 4consultant-related, and material-related factors to the
prob-able cost and time overruns In this research, we take an
integrated approach and attempt to link the causes and
the effects of delays in Malaysian construction industry
through a systematic analysis
3 Methodology
A questionnaire was developed to assess the perceptions
of clients, consultants, and contractors on the relative
importance of causes and effects of delay in Malaysian
con-struction industry The questionnaire was divided into
three parts The first part requested background
informa-tion about the respondents
The second part of the questionnaire focused on causes
of construction delay The respondents were asked to
indi-cate their response indi-category on 28 well-recognized
con-struction delay factors identified by Odeh and Battaineh
[15] These causes were categorized into the following eight
major groups:
1 Client related factors: finance and payments of
com-pleted work, owner interference, slow decision making
and unrealistic contract duration imposed by owners
2 Contractor related factors: delays caused by
subcontrac-tor, site management, improper construction methods,
improper planning and errors during construction, and
inadequate contractor experience
3 Consultant related factors: contract management,
prep-aration and approval of drawings, quality assurance and
waiting time for approval of test and inspection
4 Material related factors: quality of material and
short-age in material
5 Labor and equipment related factors: labor supply,
labor productivity and equipment availability and
failure
6 Contract related factors: change orders and mistakes or
discrepancies in contract document
7 Contract relationship related factors: major disputes
and negotiations, inappropriate overall organizational
structure linking to the project and lack of
communica-tion between the parties
8 External factors: weather condition, regulatory changes,
problem with neighbors and unforeseen site condition
The respondents were asked to highlight their
recom-mendations to improve the performance of Malaysian
con-struction industry through an open-ended question at the
end of second part of the questionnaire
Third part of the questionnaire focused on the effects of
construction delay in Malaysian construction industry The
six effects of construction delay identified were: time
over-run, cost overover-run, dispute, arbitration, litigation, and total
abandonment [1] Similar to the second part of the
ques-tionnaire, the respondents were asked to highlight their
rec-ommendation to minimize the effects of construction delays
through an open-ended question A five-point Likert scale
ranging from 1 (not important) to 5 (extremely important) was adopted to capture the importance of causes and effects of delays
Before distributing the questionnaire, a small pilot study was conducted using 10 consultants, 10 clients, and 10 con-tractors The basic purpose of the pilot study was to verify the completeness of the questionnaire in capturing the fac-tors relevant for Malaysia All the respondents agreed that the questionnaire was sufficient to capture the causes and effects of delays Therefore, we did not make any modifica-tion to the causes of delay identified by Odeh and Battai-neh [15] and effects of delay identified by Aibinu and Jagboro[1]
The sampling method used in this study was conve-nience and snowball sampling This sampling comes under the class of non-probability sampling techniques As the name implies, sample elements are identified by conve-nience (friends) and through referral networks This method of sampling is preferred when it is difficult to get response from sample elements selected at random [18]
We distributed the questionnaires through our friends working in Public Works Department of Malaysia, devel-opers, consultants and construction firms Our friends in turn distributed to their friends This sampling method enabled us to obtain a large number of completed question-naires quickly and economically Two hundred sets of questionnaires were distributed to the potential respon-dents at all levels in the organizations within the construc-tion industry One hundred sets were distributed to clients (50 sets to Public Works Department of Malaysia and 50 sets to private developers), 50 sets to consultants and 50 sets to the contractors Of the 200 questionnaires, 150 sets (75%) were returned and there were 67 sets (67%) from cli-ents, 48 sets (96%) from consultants and 35 sets (70%) from contractors
3.1 Calculation of relative importance of factors Kometa et al [11] used the relative importance index method to determine the relative importance of the various causes and effects of delays The same method was adopted
in this study within various groups (i.e clients, consultants
or contractors) The five-point scale ranged from 1 (not important) to 5 (extremely important) was adopted and transformed to relative importance indices (RII) for each factor as follows:
RII¼
PW
where W is the weighting given to each factor by the respondents (ranging from 1 to 5), A is the highest weight (i.e 5 in this case), and N is the total number of respon-dents The RII value had a range from 0 to 1 (0 not inclu-sive), higher the value of RII, more important was the cause or effect of delays
The RII was used to rank (R) the different causes These rankings made it possible to cross-compare the relative
Trang 5importance of the factors as perceived by the three groups
of respondents (i.e clients, consultants and contractors)
Each individual cause’s RII perceived by all respondents
were used to assess the general and overall rankings in
order to give an overall picture of the causes of
construc-tion delays in Malaysian construcconstruc-tion industry The same
procedure was adopted for ranking the effects The indices
(RII) were then used to determine the rank of each item
(effect) These rankings made it possible to cross compare
the relative importance of the items as perceived by the
three groups of respondents The weighted average for each
item for the three groups of respondents was determined
and ranks (R) were assigned to each item representing the
perception of the three groups
4 Analysis of data
The demographic characteristics of the respondents are
given inTable 1
4.1 Causes of delay
The primary data collected from the second part of the
questionnaire was analyzed from the perspective of clients,
consultants and contractors Each individual cause’s RII
perceived by all respondents was computed for overall
analysis
The relative importance index, RII, was computed for
each cause to identify the most significant causes The
causes were ranked based on RII values From the ranking
assigned to each cause of delays, we were able to identify
the most important factors or causes of delays in
Malay-sian construction industry
Based on the ranking, the five most important causes of
construction delays as perceived by clients were: (1)
con-tractor’s improper planning (RII = 0.821); (2) concon-tractor’s
site management (RII = 0.779); (3) inadequate contractor
experience (RII = 0.770); (4) labor supply problems (RII
= 0.770) and (5) subcontractor problems (RII = 0.758)
The five most important causes of construction delays as
perceived by consultants were: (1) contractor’s improper
planning (RII = 0.842); (2) contractor’s site management
(RII = 0.821); (3) shortage in material (RII = 0.804); (4)
inadequate contractor experience (RII = 0.770), and (5)
inadequate client’s finance and payments of completed
work (RII = 0.792) The five most important causes of
struction delays as perceived by contractor were: (1)
con-tractor’s poor site management (RII = 0.869); (2)
inadequate client’s finance and payments of completed
work (RII = 0.823); (3) subcontractors (RII = 0.789); (4)
inadequate contractor experience (RII = 0.783), and (5)
equipment availability and failures (RII = 0.777) From
the above list, it is interesting to compare the causes as
per-ceived by clients and contractors Most of the disputes that
arise in the construction industry in Malaysia are between
clients and contractors, most often, one party blaming the
other Three of the causes perceived common between
clients and contractors are: contractor’s site management, inadequate contractor experience, and subcontractors The clients blame contractor’s improper planning and labor supply as other important causes of delay The con-tractors’ inability to plan can be attributed to contractor’s inexperience A significant portion of the labor force in the construction industry is from neighboring countries like Indonesia It is quite difficult to prevent the movement of these laborers from one construction company to another causing disruption of work The contractors blame client’s inability to pay for the completed work and equipment availability and failures as other important causes of delay These causes can be attributed to the client’s financial posi-tion and contractor’s improper planning In government related projects, payments to the contractors take relatively longer time It is the responsibility of the contractors to fac-tor in this time during the planning process Table 2gives
Table 1 Demographic characteristics of respondents Demographic characteristic Frequency Percent Age
Sex
Education
Type of organization Clients (government or developer) 67 44.7
Occupational level
Number of years working experience
Fields of specializations
Largest project involved based on contract sum
Trang 6the ranking of causes based on response of all respondents
(clients, contractors and consultants).Table 3summarizes
RII and ranking of the categories of causes of delay as
per-ceived by all respondents
In order to test the degree of agreement between the
three groups of respondents as to the causes of delays, a
correlation analysis using Spearmen’s rank correlation
coefficient was done [6] Table 4 gives the results of the
analysis High correlation indicates that there is a high
degree of agreement between the respondents
4.2 Effects of delay
The primary data collected from the third part of the
questionnaire was analyzed from the perspective of
cli-ents, consultants and contractors The calculation of RII
and ranking were done as explained in the previous
section
Based on the ranking, the important effects of construc-tion delays as perceived by clients were: time overrun (RII = 0.821), cost overrun (RII = 0.782), dispute (RII = 0.687), arbitration (RII = 0.621), litigation (RII = 0.591), and total abandonment (RII = 0.585) The important effects of construction delays as perceived by contractors and consultants were exactly the same as those
of clients and therefore, a separate analysis using Spear-men’s Rank correlation was not done to test the agreement between the three groups of respondents.Table 5gives the ranking of effects based on response of all respondents (cli-ents, contractors and consultants)
The next step in the analysis was to identify the empiri-cal relationships between the causes and the effects Empir-ical relationships are based on observations and propositions that are based on sense experience and are derived from methods of inductive logic, including mathe-matics and statistics[18] In short, empirical relationships
Table 2
Ranking of causes (based on overall)
Client related causes
Unrealistic contract duration and requirements imposed 5.3 10.7 42.0 32.0 10.0 0.661 24 Contractor related causes
Consultant related causes
Waiting time for approval of tests and inspection 1.3 14.0 44.0 30.0 10.7 0.669 23 Material related causes
Labor and equipment category causes
Contract related causes
Contract relationships related causes
Inappropriate overall organizational structure linking to the project 0.0 14.7 48.0 29.3 8.0 0.661 25
External causes
Trang 7attempt to describe, explain, and make predictions through
observation In this research, we attempt to establish
rela-tionship between causes and effects through observable
data Since the data we have collected through survey is
based on Likert-scale, it can be considered as interval data
Correlation analysis is a powerful method to study the rela-tionship between variables that have interval data [18] Therefore, a correlation analysis was done to study the empirical relationships between the categories of causes and effects.Table 6gives the results of the analysis
Table 3
RII and ranking of categories of causes of delay
Table 4
Spearman’s rank correlation coefficients of the ranking of clients, consultants and contractors for causes of delay (28 causes)
a Correlation is significant at the 0.01 level of significance – if significance probability is lesser than the level of significance, correlation is significant.
Table 5
Ranking of effects (based on overall)
Table 6
Correlation between the categories of causes and effects of delays
Client Contractor Consultant Material Labor Contract related Contract relationship External
Highlighted coefficients are significant at 0.05 significance level.
Trang 85 Discussion of results
This section discusses the results obtained in the earlier
section First, we discuss the results obtained by analyzing
the causes of delays Second, we discuss the results
obtained by analyzing the effects of the delays Third, we
link each of the effect with the causes of delay
The ten most important causes of delays (based on all
respondents) as shown in theTable 2were: (1) contractor’s
improper planning (RII = 0.815), (2) contractor’s poor site
management (RII = 0.813), (3) inadequate contractor
experience (RII = 0.783), (4) inadequate client’s finance
and payments for completed work (RII = 0.792), (5)
prob-lems with subcontractors (RII = 0.771), (6) shortage in
material (RII = 0.771), (7) labor supply (RII = 0.757), (8)
equipment availability and failure (RII = 0.755), (9) lack
of communication between parties (RII = 0.755), and
(10) mistakes during the construction stage (RII = 0.753)
5.1 Contractor’s improper planning
Local contractors often fail to come out with a practical
and workable ‘‘work program’’ at the initial planning
stage This failure is interrelated with lack of systematic site
management and inadequate contractor’s experience
towards the projects The consultant only checks and
reviews the work program submitted by the contractors
based on experience and intuitive judgment Improper
planning at the initial stages of a project manifests
through-out the project and causes delays at various stages Only a
project that is well planned can be well executed
5.2 Contractor’s poor site management
Contractor’s poor site management is one of the most
significant causes in causing the construction delays The
results of this research indicate that local contractors face
deficiency in site planning, implementation and controls
A poor site management results in delays in responding
to the issues that arise at the site and causes negative
impact on the overall work progress
5.3 Inadequate contractor experience
Odeh and Battaineh[15]indicated that inadequate
con-tractor experience was an important factor and this could
be linked to the contract awarding procedure where most
projects were awarded to the lowest bidder A contractor
with inadequate experience cannot plan and manage the
projects properly and this can lead to disastrous
consequences
5.4 Client’s finance and payments for completed work
Construction works involve huge amounts of money
and most of the contractors find it very difficult to bear
the heavy daily construction expenses when the payments
are delayed Work progress can be delayed due to the late payments from the clients because there is inadequate cash flow to support construction expenses especially for those contractors who are not financially sound
5.5 Problems with subcontractors Typically in huge projects, there are many subcontrac-tors working under main contracsubcontrac-tors If the subcontractor
is capable, the project can be completed on time as planned The project can be delayed if the subcontractor under performs because of inadequate experience or capa-bility High degree of subcontracting in Malaysia leads to high risk of delays and this leads to inefficiencies in the Malaysian construction industry
5.6 Shortage in material Shortages in basic materials like sand, cement, stones, bricks, and iron can cause major delays in projects Since Malaysia is a country that is developing very fast, often times demand exceeds the supply and this causes prices
to increase The contractors postpone the purchase activi-ties until the prices decrease Manavazhia and Adhikarib
[13] investigated material and equipment procurement delays in highway projects in Nepal and found these delays
to cause cost overrun
5.7 Labor supply The quality and quantity of labor supply can have major impact on the projects About 20% of the workers in the Malaysian construction industry are foreign workers, mainly from Indonesia and Vietnam (MALBEX [12]) A few of them are illegal workers and their work quality is relatively low when compared to local laborers The low quality and productivity of the foreign workers have impact on the project progress and efficiency The illegal workers are frequently caught by the Malaysian immigrant officials and deported and this causes shortage of labor pool in the construction industry
5.8 Equipment availability and failure Many of the contractors do not own equipments that are required for the construction work They rent the equipments when required During the season when there are many construction projects, the equipments are in short supply and are poorly maintained This leads to failure of the equipments causing the progress to be hampered 5.9 Lack of communication between parties
Since there are many parties involved in a project (client, consultant, contractor, sub-contractors), the communica-tion between the parties is very crucial for the success of the project Proper communication channels between the
Trang 9various parties must be established during the planning
stage Any problem with communication can lead to severe
misunderstanding and therefore, delays in the execution of
the project
5.10 Mistakes during the construction stage
The mistakes during the construction stage can be due
to accidents, inadequate planning, or miscommunication
between the parties Whatever the reason, the mistakes
can have impact on the progress of the project
While analyzing the effects of delays, all respondents
were unanimous in ranking the effects The time and cost
overruns were ranked highly by the respondents Any delay
in a project can lead to cost and time overruns and these
two are linked Whenever there are delays, there are
dis-putes as to who should bear the responsibility and the cost
These disputes often lead to an arbitration process by third
parties and failure in this process leads to litigation where
the disputes are settled by the court In extreme cases, some
projects might be totally abandoned About 17% of the
projects in Malaysia are abandoned (MALBEX[12])
In the following paragraphs, we analyze the impact of
causes on each effect of delay Correlation analysis results
given in Table 6 establish the link between them From
the table, we can identify the causes for each of the effects
of delay
5.11 Time overrun
Client-related and contractor-related factors have
impact on the time overrun Out of the ten most important
causes of delay discussed earlier, six causes belong to
client-related and contractor-client-related factors Factors such as
inadequate planning by the contractors, improper site
management by the contractors, inadequate project
han-dling experience of contractors, and delay in the payments
for the work completed directly affect the completion of the
project and cause time overrun
5.12 Cost overrun
Contract-related factors such as change orders (changes
in the deliverables and requirements) and mistakes and
dis-crepancies in the contract document result in cost overrun
Mistakes and discrepancies in the contract document can
be in scope, deliverables, resources available and allocated,
payment terms, achievement of various milestones, and the
project duration In most of the instances, time overrun
leads to cost overrun Correlation analysis between cost
and time overruns indicated a strong linkage (correlation
coefficient = 0.487, significant at 0.01 level of significance)
5.13 Disputes
Client-related, contract-related, contract
relationship-related, and external factors have impact on the disputes
that arise during the course of the project Factors such
as delay in the payments for completed work, frequent owner interference, changing requirements, lack of com-munication between the various parties, problems with neighbors, and unforeseen site conditions give rise to dis-putes between the various parties The disdis-putes, if not resolved amicably, can lead to arbitration or litigation 5.14 Arbitration
Client-related and contract relationship-related factors escalate disputes to be settled by arbitration process A competent third-party can settle the disputes amicably without going to the court
5.15 Litigation Client-related, labor-related, contract-related, contract relationship-related, and external factors escalate disputes
to be settled by the litigation process The parties involved
in the projects use litigation as a last resort to settle disputes
5.16 Total abandonment Client-related, consultant-related, labor-related, con-tract-related, and external factors contribute to the total abandonment of the projects In Malaysia, many projects were temporarily abandoned during the financial crisis between 1997 and 2000 Promoters of various projects backed out because of poor cash flow and economic condi-tions Many of these projects have now become so prohib-itive that they have been abandoned permanently (MALBEX[12])
Based on the discussions above, the next step is to pro-vide suggestions to clients, contractors, and consultants to reduce delays These suggestions, we hope, will alleviate the problems faced by the construction industry in Malaysia
6 Prescriptions to reduce delays
We divide the prescriptions to adopted into three groups: (1) prescriptions for the clients, (2) prescriptions for the consultants, and (3) prescriptions for the contractors
6.1 Prescriptions for the clients (1) While selecting the contractors, clients have to make sure that the contractors are not selected based only on the lowest bid The selected contractor must have sufficient experience, technical capability, financial capability, and sufficient manpower to execute the project, (2) clients should not interfere frequently during the execution and keep making major changes to the requirements This can cause inordinate delays in the project, (3) clients should have the finances in time to pay the contractors after
Trang 10com-pletion of a work Therefore, clients should work closely
with the financing bodies and institutions to release the
payment on schedule, and (4) clients must make quick
deci-sions to solve any problem that arise during the execution
6.2 Prescriptions for the consultants
(1) While drawing the contract between the client and
contractor, the consultant must include items such as
dura-tion of contract, mechanism to solve disputes, mechanism
to assess the causes of delay, if there are any and risk
man-agement plans, (2) consultants should prepare and approve
drawings on time, and (3) consultants should monitor the
work closely by making inspections at appropriate times
6.3 Prescriptions for the contractors
(1) Contractors should not take up the job in which they
do not have sufficient expertise, (2) contractors should have
able site-managers for the smooth execution of work, (3)
contractors must plan their work properly and provide
the entire schedule to the clients, and (4) contractors must
make sure they have a sound financial backing
7 Conclusions
We investigated the causes and effects of delays facing in
the Malaysian construction industry A questionnaire was
designed and distributed among the three major groups
of participants (clients, consultants and contractors) We
identified main causes of delay and ten most important
causes were: (1) contractor’s improper planning, (2)
con-tractor’s poor site management, (3) inadequate contractor
experience, (4) inadequate client’s finance and payments
for completed work, (5) problems with subcontractors,
(6) shortage in material, (7) labor supply, (8) equipment
availability and failure, (9) lack of communication between
parties, and (10) mistakes during the construction stage
We identified main effects of delay and they were: (1) time
overrun, (2) cost overrun, (3) disputes, (4) arbitration, (5)
litigation, and (6) total abandonment As an important
contribution, we also studied the empirical relationships
between the causes and effects of delays We isolated the
causes of delay for each of the six effects We believe that
the results of this study can be of immense help to the
prac-titioners (clients, contractors and consultants) and
acade-micians The practitioners can better understand the
dynamics of project management and make efforts to
reduce the incidences of delays The academicians can con-duct similar studies in other parts of world and identify causes and effects of delays As mentioned earlier, some causes and effects may be unique to certain countries References
[1] Aibinu AA, Jagboro GO The effects of construction delays on project delivery in Nigerian construction industry Int J Project Manage 2002;20:593–9.
[2] Ajanlekoko JO Controlling cost in the construction industry Lagos
QS Digest, Lagos 1987;1(1):8–12.
[3] Akinsola AO Neural network model for predicting building projects’ contingency In: Conference: proceedings of association of research-ers in construction management, ARCOM 96, Sheffield Hallam University, England, 11–13 September 1996 p 507–16.
[4] Alkass S, Mazerolle M, Harris F Construction delay analysis techniques Construction Manage Econ 1996;14(5):375–94.
[5] Al-Momani A Construction delay: a quantitative analysis Int J Project Manage 2000;20:51–9.
[6] Assaf SA, Al-Hejji S Causes of delay in large construction projects Int J Project Manage 2006;24(4):349–57.
[7] Assaf SA, Alkhalil M, Al-Hazmi M Causes of delay in large building construction projects J Manage Eng, ASCE 1995;11(2):45–50 [8] Chan DWM, Kumaraswamy MM A comparative study of causes of time overruns in Hong Kong construction projects Int J Project Manage 1997;15(1):55–63.
[9] Chan DWM, Kumaraswamy MM Compressing construction dura-tions: lessons learned from Hong Kong building projects Int J Project Manage 2002;20:23–35.
[10] Frimpong Y, Oluwoye J, Crawford L Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study Int J Project Manage 2003;21:321–6.
[11] Kometa ST, Olomolaiye PO, Harris FC Attributes of UK construc-tion clients influencing project consultants’ performance Construc-tion Manage Econ 1994;12:433–43.
[12] MALBEX, 2005 Market watch – construction industry, Kuala Lumpur Exhibition Center Report p 1–8.
[13] Manavazhia MR, Adhikarib DK Material and equipment procure-ment delays in highway projects in Nepal Int J Project Manage 2002;20:627–32.
[14] Mansfield NR Causes of delay and cost overruns in Nigerian construction projects Int J Project Manage 1994;12(4):254–60 [15] Odeh AM, Battaineh HT Causes of construction delay: traditional contracts Int J Project Manage 2002;20:67–73.
[16] Odeyinka HA, Yusif A The causes and effects of construction delays
on completion cost of housing project in Nigeria J Financial Manage Property Construction 1997;2(3):31–44.
[17] Ogunlana SO, Promkuntong K Construction delays in a fast growing economy: comparing Thailand with other economies Int J Project Manage 1996;14(1):37–45.
[18] Sekaran Uma Research methods for business: a skill building approach 3rd ed New York: John Wiley; 2000.
[19] Terry Williams Assessing extension of time delays on major projects Int J Project Manage 2003;21:19–26.