This Test Plan for the Management Information System for Information Center supports the following objectives: - Identify the scope, environment, features to be tested and not to be tes

Trang 1

Management Information System for Information Center

Master Test Plan

Version: 1.3

Revision History

SinhVienZone.Com

Trang 2

Table of Contents

1 Introduction 3

1.1 Purpose 3

1.3 Intended Audience 3

1.4 Document Terminology and Acronyms 3

1.5 References 3

2 Evaluation Mission and Test Motivation 3

2.1 Background 3

2.2 Evaluation Mission 3

2.2 Test Motivators 4

3 Target Test Items 4

5 Test Approach 5

5.1 Function Testing 5

5.2 User Interface Testing 5

6 Entry and Exit Criteria 5

6.1 Test Plan Entry Criteria 5

6.2 Test Plan Exit Criteria 5

7 Deliverables 5

8 Testing Workflow 6

9 Environmental Needs 6

9.1 Base System Hardware 6

9.2 Base Software Elements in the Test Environment 6

9.3 Productivity and Support Tools 6

9.4 Test Environment Configurations 7

10 Responsibilities, Staffing, and Training Needs 7

10.1 People and Roles 7

10.2 Staffing and Training Needs 8

12 Risks, Dependencies, Assumptions, and Constraints 9

12.1 Risks 9

12.1.1 Schedule 9

12.1.2 Management 9

12.1.3 Personnel 9

12.1.4 Requirements 9

12.2 Dependencies 9

12.2.1 Personnel Dependencies 9

12.2.2 Software Dependencies 9

12.2.3 Test Data & Database 9

13 Management Process and Procedures 9

13.1 Reviews 9

13.2 Bug Review meetings 9

13.3 Defect Reporting 10

14 Documentation 10

15 Approvals 10

SinhVienZone.Com

Trang 3

Master Test Plan

1 Introduction

1.1 Purpose

The purpose of the Iteration Test Plan is to gather all of the information necessary to plan and control the test effort for a given iteration It describes the approach to testing the software, and is the top-level plan generated and used by managers to direct the test effort

This Test Plan for the Management Information System for Information Center supports the following

objectives:

- Identify the scope, environment, features to be tested and not to be tested, risk and contingency, resources

- List the recommended test requirements

- Recommend and describe the testing approach to be employed

- Include traceability from requirements of the Test Case

- List the deliverable elements of the test project

1.2 Scope

This document provides test requirements, test strategies for:

- Plan Test

- Design Test Case

- Execute Test

- Report Test

In five Use cases:

- Student management

- Long-term education management

- Short-term education management

- Desire management

- Statistics report

1.3 Intended Audience

This test plan is useful for the Q&A team group to keep on track the process of test Simultaneously, it is also useful for the customer to give the appreciation for the product

1.4 Document Terminology and Acronyms

MISIC: Management Information System for Information Center

1.5 References

1 Assignment specification for software testing subject (internal use)

2 MISIC theses for bachelor of engineering; Ho Chi Minh City University of Technology

2 Evaluation Mission and Test Motivation

2.1 Background

This software aims at the purpose that design and implement a system called the system of information management center, which provides two main functions: support the management, organization, operation of the actions of center about human resource and education; and remote services for students It is implemented

on J2EE, DBMS by MS SQL server The Operating system can be one of: Windows XP( package 2,3); windows Vista, windows 7 And it has a strict integration with antivirus in implement environment

2.2 Evaluation Mission

- find as many bugs as possible

- find important problems, assess perceived quality risks

- advise about perceived project risks

SinhVienZone.Com

Trang 4

- certify to a standard

- verify a specification (requirements, design or claims)

- advise about product quality, satisfy stakeholders

- advise about testing

- fulfill process mandates

2.2 Test Motivators

Q&A team members will be motivated by some key factors

- Quality risks

- Technical risks

- Five use cases those must be tested

- Functional requirements

- Non-functional requirements

- Design elements

- Suspected failures or faults

3 Target Test Items

The listing below identifies those test items; software, hardware, and supporting product elements that have been identified as targets for testing This list represents what items will be tested

- Build a test project which include Plan Test, Design Test Cases, Execute Test, Report Test

- Realize a test plan, realize all components in test plan completely, in addition

o Define features to be tested and features not to be test in tested plan clearly

o Define functions those to be tested and not to be tested ( just test only five use cases)

- Just only write the necessary test cases for five use cases

- Inspect by the way relying on written test cases, record bugs in bug tracking system

- Give the report

4 Features to Be Tested

4.1 Student management

- Search information

- Update data

- Insert data

- Delete data

- GUI to report in test report file

4.2 Long-term education management

- Search information

- Update data

- Insert data

- Delete data

- GUI to report in test report file

4.3 Short-term education management

- Search information

- Update data

- GUI to report in test report file

4.4 Desire management

- Search information

SinhVienZone.Com

Trang 5

- Update data

- GUI to report in test report file

4.5 Statistics report

- Search information

- Update data

- GUI to report in test report file

5 Test Approach

The test strategy consists of a series of different tests that will fully exercise the visualizing application The primary purpose of these tests is to uncover the systems limitations and measure its full capabilities In this project,

we just only concentrate on test in two aspects: functioning test and user interface test The test personnel will follow CSTE standard

5.1 Function Testing

We measure the quality of the functional (business) components of the system by function testing Tests verify that the system behaves correctly from the user / business perspective and functions according to the requirements, models, storyboards, or any other design paradigm used to specify the application The function test must determine if each component or business event: performs in accordance to the specifications, responds correctly to all conditions that may be presented by incoming events / data, moves data correctly from one business event to the next (including data stores), and that business events are initiated in the order required to meet the business objectives of the system We will apply the white-box and also black-box approach with the collaborate with the use equivalence class, boundary values, decisions table, cause-effect diagram, so on;

5.2 User Interface Testing

To ensure graphical user interface meets its written specifications We create GUI tests by use IPP technique; first, the systems UI are analyzed to determine what operations are possible These operations become the operators used in the planning problem Next an initial system state is determined Next a goal state is determined that the tester feels would allow exercising of the system Lastly the planning system is used to determine a path from the initial state to the goal state

6 Entry and Exit Criteria

6.1 Test Plan Entry Criteria

- Business needs are confirmed

- Business Requirement document prepared by Analyst

- Estimation of IT infrastructure

- Acquisition of resources

- Project kick off meeting is done and sign off is given

6.2 Test Plan Exit Criteria

- All the testing has been performed as defined

- 100% test coverage is met

- All the bugs raised are resolved, retested and closed

- Product goes live with optimal quality and standards

- meeting customer requirements and satisfaction

7 Deliverables

Deliverable Responsibility Completion Date

Develop Test cases Testers 05/06/10

Test Case Review Test Lead, Testers 06/06/10

Execute manual Test Lead, Testers 08/06/10

Complete Defect Reports Test Lead, Testers On-going

SinhVienZone.Com

Trang 6

8 Testing Workflow

- Verify the result from implementation by testing each build

- Plan the tests in each iteration

- Design and implement tests by creating

- Perform the tests and systematically handle the test results

- Test model artifacts

 Test cases

 Test procedures

 Test components

 Test subsystem packages for complex test models’

- Other artifacts

 Test Plan

 Defects

 Test Evaluation

9 Environmental Needs

9.1 Base System Hardware

System resources that need for the test effort presented in this Test Plan are:

- Database server

- CPUs core 2dual 2.0; Ram 2GB

9.2 Base Software Elements in the Test Environment

The following base software elements are required in the test environment for this Test Plan

Software

9.3 Productivity and Support Tools

The following tools will be employed to support the test process for this Test Plan

Test Management

Defect Tracking

ASQ Tool for functional testing

ASQ Tool for performance testing

Test Coverage Monitor or Profiler

Project Management

SinhVienZone.Com

Trang 7

DBMS tools

9.4 Test Environment Configurations

The following Test Environment Configurations needs to be provided and supported for this project

Configuration Average user configuration

Minimal configuration supported

Visually and mobility challenged

International Double Byte OS

Network installation (not client)

10 Responsibilities, Staffing, and Training Needs

10.1 People and Roles

This table shows the staffing assumptions for the test effort

Human Resources

Recommended

(number of full-time roles allocated)

Specific Responsibilities or Comments

Responsibilities include:

 planning and logistics

 agree mission

 identify motivators

 acquire appropriate resources

 present management reporting

 advocate the interests of test

 evaluate effectiveness of test effort

conducted

Responsibilities include:

 identify test ideas

 define test details

 determine test results

 document change requests

 evaluate product quality SinhVienZone.Com

Trang 8

Test Designer Defines the technical approach to the

implementation of the test effort

Responsibilities include:

 define test approach

 define test automation architecture

 verify test techniques

 define testability elements

 structure test implementation

Responsibilities include:

 implement tests and test suites

 execute test suites

 log results

 analyze and recover from test failures

 document incidents

managed and maintained

Responsibilities include:

 administer test management system

 install and support access to, and recovery

of, test environment configurations and test labs

Database Administrator,

Database Manager

Ensures test data (database) environment and assets are managed and maintained

Responsibilities include:

 support the administration of test data and test beds (database)

and associations of the test classes

Responsibilities include:

 defines the test classes required to support testability requirements as defined by the test team

test packages

Responsibilities include:

 creates the test components required to support testability requirements as defined by the designer

10.2 Staffing and Training Needs

SinhVienZone.Com

Trang 9

Test designs assume a thorough and complete knowledge of the operation of both systems under test as well as knowledge of the primary service tools and their appropriate operation

Testing was performed under the operating of team-leader Ha Thai Vu; all Members of Q&A team group are:

- Ha Thai Vu

- Trinh Van Quang

- Dang Tuan Anh

- Nguyen Truong Toan

12 Risks, Dependencies, Assumptions, and Constraints

12.1 Risks

12.1.1 Schedule

The schedule for each phase is very aggressive and could affect testing A slip in the schedule in one of the other phases could result in a subsequent slip in the test phase Close project management is crucial to meeting the forecasted completion date

12.1.2 Management

Management support is required so when the project falls behind, the test schedule does not get squeezed to make up for the delay Management can reduce the risk of delays by supporting the test team throughout the testing phase and assigning people to this project with the required skills set

12.1.3 Personnel

Due to the aggressive schedule, it is very important to have experienced testers on this project Unexpected turnovers can impact the schedule If attrition does happen, all efforts must be made to replace the experienced individual

12.1.4 Requirements

The test plan and test schedule are based on the current Requirements Document Any changes to the requirements could affect the test schedule

12.2 Dependencies

12.2.1 Personnel Dependencies

The test team requires experience testers to develop, perform and validate tests

12.2.2 Software Dependencies

The source code must be unit tested and provided within the scheduled time outlined in the Project Schedule

12.2.3 Test Data & Database

Test data & database should also be made available to the testers for use during testing

13 Management Process and Procedures

13.1 Reviews

The project team will perform reviews for each Phase (i.e Requirements Review, Design Review, Code Review, Test Plan Review, Test Case Review and Final Test Summary Review) A meeting notice, with related documents, will be emailed to each participant

13.2 Bug Review meetings

Regular weekly meeting will be held to discuss reported defects The development department will provide status/updates on all defects reported and the test department will provide addition defect information if needed All member of the project team will participate

SinhVienZone.Com

Trang 10

13.3 Defect Reporting

When defects are found, the testers will complete a defect report on the defect tracking system The defect tracking systems is accessible by testers, developers & all members of the project team When a defect has been fixed or more information is needed, the developer will change the status of the defect to indicate the current state Once a defect is verified as FIXED by the testers, the testers will close the defect report

14 Documentation

The following documentation will be available at the end of the test phase:

Test Plan

Test Cases

Test Case review

Defect reports

Final Test Summary Report

15 Approvals