Opportunity costs are relevant costs.. In the situation of Pointdextre Ltd, if it goes ahead with the new business that is the decision then it will lose forgo the contribution from some
Trang 1Answers
Trang 3Part 1 Examination – Paper 1.2
Section A
10 B
11 A
12 B
13 C
14 D
15 A
16 C
17 D
18 A
19 A
20 C
21 D
22 D
23 D
24 D
25 B
2 C 1,700 units – Breakeven level units (1,200) = 500 units
3 C Contribution per unit = 22 ÷ 0·55 ×0·45 = £18
Breakeven point = 198,000 ÷ 18 = 11,000
4 C Variable cost per unit = [(170,000 – 5,000) – 140,000)] ÷ (22,000 –17,000) = £5
Total fixed cost above 18,000 units = 170,000 – (22,000 ×5) = £60,000
Total cost of 20,000 units = (20,000 ×5) + 60,000 = £160,000
7 C Weighted average after 13th = [(200 ×9,300 ÷ 300) + (600 ×33)] ÷ (200 + 600) = £32·50
Closing stock valuation = 300 ×32·50 = £9,750
8 C EOQ = [(2 ×160 ×9,000) ÷ (0·08 ×40)]0·5= 949
10 B
17
Trang 411 A Absorption rate = 247,500 ÷ 30,000 = £8·25
Absorbed cost = 28,000 ×8·25 = £231,000
12 B Marginal costing profit = 36,000 – (2,000 ×63,000 ÷ 14,000) = £27,000
13 C Process F: expected output = 0·92 ×65,000 = 59,800
∴abnormal loss Process G: expected output = 0·95 ×37,500 = 35,625
∴abnormal gain
Actual hours at standard rate (27,000 ×8·50) 229,500
Standard hours of production at standard rate 253,980
––––––––
∴Labour efficiency variance is 24,480 Favourable
––––––––
Actual sales at standard price (4,650 ×6) 27,900
–––––––
–––––––
Adverse sales volume contribution variance:
16 C
17 D
18 A
19 A Coefficient of determination = r2= 0·6 ×0·6 = 0·36 = 36%
20 C
21 D 4,000 ×[(20,000 ÷ 2,500) ×1·025] = £32,800
22 D Production (units):
J: (6,000 – 100 + 300) = 6,200
K: (4,000 – 400 + 200) = 3,800
––––––
10,000 ––––––
Joint costs apportioned to J: (6,200 ÷ 10,000) ×110,000 = £68,200
23 D Material required to meet maximum demand:
6,000 ×(13 ÷ 4) + 8,000 ×(19 ÷ 4) = 57,500 litres
∴Material is a limiting factor
Labour required to meet maximum demand:
6,000 ×(35 ÷ 7) + 8,000 ×(28 ÷ 7) = 62,000 hours
∴
Trang 524 D Profits maximised when: marginal revenue (MR) = marginal cost (MC)
MR = 50 – 0·05Q
MC = 15
P = 50 – (0·025 ×700) = £32·50
25 B When P = 20 then 20 = 50 – 0·025Q
£ Total revenue (P ×Q) = 1,200 ×20 = 24,000
Less total costs 2,000 + (15 ×1,200) = 20,000
––––––
––––––
Section B
1 (a) Using the high-low method:
Working (W1)
Full capacity = 102,000 ÷ 0·85 = 120,000
(i) Variable cost per unit = 81,000 ÷ 18,000 = £4·50
(ii) Total fixed costs = 700,000 – (120,000 ×4·50) = £160,000
(iii) Selling price per unit = variable cost per unit ÷ (1·00 – 0·40)
= 4·50 ÷ 0·6 = £7·50
(iv) Contribution per unit = (7·50 – 4·50) = £3·00
Less variable cost (4·50)
–––––
–––––
£ Contribution from 15,000 units (15,000 ×1·50) 22,500
Less opportunity cost (15,000 ÷ 6) ×£3·00 (7,500)
–––––––
Net increase in contribution (and profit) 15,000
–––––––
(c) An opportunity cost is the cost of the best alternative forgone in a situation of choice Opportunity costs are relevant costs
In the situation of Pointdextre Ltd, if it goes ahead with the new business (that is the decision) then it will lose (forgo) the contribution from some existing sales This lost contribution is an opportunity cost relevant to the decision
Workings:
W1 Cost per litre (365,000 + 256,000) ÷ (50,000 ×0·92) = £13·50
Output value = 47,000 ×13·50 = £634,500
W2 Abnormal gain = 47,000 – (50,000 ×0·92) = 1,000
Valuation (1,000 ×13·50) = £13,500
19
Trang 6(b) Workings:
EL
Started and finished within the month (50,000 – 5,000) 45,000
–––––––
49,000 –––––––
∴Cost per EL = 392,000 ÷ 49,000 = £8
(i) Output = 80,000 + (45,000 ×13·50) + (48,000 ×8·00) = £1,071,500
(ii) Closing WIP = (2,000 ×13·50) + (1,000 ×8·00) = £35,000
(c) The disposal costs would be debited to the process account Alternatively, they could be shown as a negative value on the credit side of the account
3 Let X = the number of units of product X
and Y = the number of units of product Y
Contribution per unit:
£ per unit £ per unit
Less variable cost (45) (13)
Objective function:
Total contribution = 15X + 12Y
Constraints:
Material (£5 per kg) 3X + Y ≤ 4,200
Labour (£6 per hour) 4X + 0·5Y ≤ 3,000
Using a graphical approach, the constraints (solid lines) and the objective function (dotted line) can be shown as follows:
Note: the objective function line has been shown on the above graph for a total contribution of £9,000 (assumed) Thus 15X + 12Y = 9,000
Therefore when X = 0, Y = (9,000 ÷ 12) = 750
and when Y = 0, X = (9,000 ÷ 15) = 600
The ‘feasible region’ is the area OABC shown on the graph If the objective function line is moved away from the origin (at the same gradient) the last point it reaches in the feasible region is point A which must therefore be the optimal point
B A
C 0
750
600
4,200
6,000
Y
units
X units Material
Labour
Trang 7An alternative approach would be to calculate the total contributions at points A, B and C shown on the graph and select the point giving the highest total contribution, as follows:
Point A
Total contribution from 4,200 units of Y is (4,200 ×£12) = £50,400
Point B
To find the units at this point, solve the following equations simultaneously:
4X + 0·5Y = 3,000 … (2)
Substituting into (2) 4X + 0·5(4,200 – 3X) = 3,000
Substituting into (1) (3 ×360) + Y = 4,200
Total contribution from 360 units of X and 3,120 units of Y is (360 ×£15) + (3,120 ×£12) = £42,840
Point C
Total contribution from 750 units of X is (750 ×£15) = £11,250
Point A gives the highest contribution (£50,400 from producing 4,200 units of Y and no units of X) and is therefore the optimal solution (as before)
Standard cost of actual production [12,500 ×(11 + 24 + 18)] 662,500
––––––––
Workings:
5,200 A Standard cost of actual production 137,500
W2
8,700 F Standard cost of actual production 300,000
W3
5,800 A Standard cost of actual production 225,000
Expenditure variance:
14,800 A
Volume variance:
9,000 F Standard cost of actual production 225,000
(c) The total direct materials and labour variances would be the same under absorption and marginal costing The total fixed overhead variance under marginal costing would be different and would be the same as the expenditure variance under absorption costing (£14,800 A) There is no volume variance under marginal costing as fixed production costs are treated
as period costs and not treated as product costs
21
Trang 85 (a) Absorption rates:
Cost centre T: (780,000 ÷ 16,250) = £48 per machine hour
Cost centre W: (173,400 ÷ 14,450) = £12 per direct labour hour
Direct labour:
––––
45 Production overheads:
Cost centre T: (35 ÷ 60) ×48 28
Cost centre W: (21 ÷ 6) ×12 42
––––
115 ––––
(c) Products do not pass through service cost centres so the costs of such centres cannot be absorbed directly into products Products only pass through production cost centres Therefore in order to calculate a total production cost per unit, service cost centre costs have to be reapportioned to production cost centres for absorption
The method of reapportionment that fully recognises any work that service cost centres do for each is called the reciprocal method There are two techniques for applying the reciprocal method – a repeated distribution approach or the use of simultaneous equations
Trang 9Part 1 Examination – Paper 1.2
Marks
Section A
–––
Section B
–––
6
–––
4
–––
2
–––
12
–––
–––
5
–––
5
–––
12
–––
–––
5
–––
4
–––
9
–––
23
Trang 10–––
4
–––
2
–––
3
–––
9
–––
–––
2
–––
3
–––
3
–––
8
–––