Abstract : Due to stormwater runoff along Pohang Bay at typhoon Rusa and Maemi in 2002 and 2003, P steel Company requires a counter measure for all future typhoons. P steel Company will have the challenge of both determining the benefits of their existing treatment facility and deciding what additional practices they will need to achieve the goal. In order to reduce the nonpoint source pollution during rainfalls, P steel Company is considering the installation of stormwater pits and the construction of a stormwater treatment plant. This study analyzed the reduction effect of nonpoint source pollution achieved through such measures using the Storm Water Management Model (SWMM). As a result, we found that the installation of stormwater pits (storage capacity 60mm/day) and stormwater treatment plant have reduced the pollution load (SS) by 38 to 87% compared to the existing state, and the concentration of SS in outflow also satisfied 20mg/L or lower
Trang 1OPTIMIZING STORM DETENTION AND TREATMENT FACILITY TO CONTROL NONPOINT SOURCE POLLUTION IN STEEL COMPANY
1 Korea Environment Institute, 613-2 Bulgwang-Dong, Eunpyeng-Gu, Seoul, Korea
2 Han-River Basin Environmental Office, 231 Manwol-Dong, Hanam-City, Kyunggi-Do, Korea
3 Department of Environmental Engineering, University of Seoul, 90 Cheonnong-Dong, Dongdaemun-Gu, Seoul, Korea
Abstract : Due to stormwater runoff along Pohang Bay at typhoon Rusa and Maemi in 2002 and 2003, P steel Company requires a counter measure for all future typhoons P steel Company will have the challenge of both determining the benefits of their existing treatment facility and deciding what additional practices they will need to achieve the goal In order to reduce the nonpoint source pollution during rainfalls, P steel Company is considering the installation of stormwater pits and the construction of a stormwater treatment plant This study analyzed the reduction effect of nonpoint source pollution achieved through such measures using the Storm Water Management Model (SWMM) As a result, we found that the installation of stormwater pits (storage capacity 60mm/day) and stormwater treatment plant have reduced the pollution load (SS) by 38 to 87% compared to the existing state, and the concentration of SS in outflow also satisfied 20mg/L or lower
Key words : Nonpoint-source pollution, SWMM, Swormwater
INTRODUCTION
Impacts caused by storm water discharges from primary metals facilities will vary A number of factors will influence to what extent the activities at a particular facility will affect water quality These include: geographic location, hydrogeology, the amounts and types of materials stored outside, the types of processes taking place outside, the size of the operation, as well as the characteristics of a particular storm event Although operations at primary metals facilities may vary considerably, the elements with potential impact on storm water discharges are fairly uniform and consistent Facilities may include considerable areas of raw and waste material storage such as coal, coke, metal, ores, sand, scale, scrap, and slag Processes generally involve furnaces for heating and melting metals or for producing coke, any of which may result in significant particulate emissions Due to the nature of their operations some facilities will have large areas of exposed soil and heavy vehicle traffic which can lead to erosion Especially in such a large factory as P steel Company, due
to its wide impervious area, a sudden increase of stormwater runoff may occur during rainfall, and nonpoint source pollutants may flow into public waters, causing water pollution problems at typhoon
P steel Company is one of the largest steel makers in the world with total area size of 891ha, and steel production capacity of 12 million tons The researched area was iron and steel making area, a part of P steel Company with the area size of 461.82ha(P steel Company, 2003) To review the water treatment system of P steel Company; the wastewater generated from the industrial processes
is primarily treated in each individual treatment facility, which is then finally treated in the wastewater treatment plant before it is discharged The site has the separated sewer system, and most of the stormwater runoff, especially the initial stormwater runoff flows into and treated in the wastewater treatment plant, so nonpoint source pollution are being efficiently controlled However, whenever a typhoon brings heavy rainfalls, the stormwater runoff from the iron ores and coal yard would exceed the capacity of the treatment plant, discharging most of it to Hyeongsan River This
Trang 2situation must be improved
Accordingly, on behalf of management of nonpoint source pollution for P steel Company, this study tries to derive effective alternatives to the installation of detention and treatment facilities, and find the optimum management practices for nonpoint source pollution control by analyzing the pollution reduction effects of the alternatives using the Storm Water Management Model(SWMM)
CONSTRUCTION OF MODEL FOR CATCHMENT USING SWMM
Scheme of SWMM
The United States Environmental Protection Agencies (USEPA's) Storm Water Management Model
is a comprehensive computer model for analysis of quantity and quality problems associated with urban runoff Both single-event and continuous simulation can be performed on catchments having storm sewers, or combined sewers and natural drainage, for prediction of flows, stages and pollutant concentrations Extran Block solves complete dynamic flow routing equations (St Venant equations) for accurate simulation of backwater, looped connections, surcharging, and pressure flow(Huber and Dickinson, 1988)
Construction of model
Distribution of sub-catchments and channel network of the study area is shown in Fig 1 The study area was divided into 16 drainage zones based on the treatment area divisions by channel networks and surface slopes For sub-catchments, informations such as catchment area , slope, roughness, impervious percentage, and land use were input For Conduit, informations such as conduit length, diameter, slope, shape, roughness werw input For the parameters related to depression storage and infiltration, the values in the references were applied, and then calibrated to exhibit the runoff characteristics of catchment during the calibration of the model For the information related to water flow and quality, the actual measured values were applied for average water flow and quality and temporal variation For the pollutants buildup and washoff parameters, after the values in the literature were applied, they were corrected during the model calibration process
Fig 1 Division of sub-catchment and channel network in the study area
Trang 3The model was calibrated for the water flow and quality during dry weather and wet weather Fig.2 shows the comparisons between actual measured values and the simulated values for flow volume and water quality, and we can find that the overall trends of both flow volume and water quality are well simulated
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
1: 3: 5: 7: 9:
Time
Es tima te d
O b s e rve d
(a) Flow simulation at treatment plant(dry weather)
0 40 80 120 160 200 240
1: 6:
3: 8:
Time
Es tima te d
P re d ic te d
(b) SS simulation at treatment plant(dry weather)
0.0
0.1
0.1
0.2
0.2
0.3
0.3
1: 6:
2: 7:
Time
0 5 10 15
20 P
Pre cipita tio n
Estim a ted
Ob serve d
(c) Flow simulation at yard area(wet weather)
0 100 200 300 400 500
1: 6:
2: 7:
Time
0 4 8 12 16
20 P
(d) SS simulation at yard area(wet weather)
Fig 2 Calibration of Model
MANAGEMENT PRACTICES OF NOMPOINT SOURCE POLLUTION
As a method of nonpoint source pollution control during rainfall, P steel Company plans to install a stormwater pit for prevention of rapid runoff and removal of pollutants, and also construct a stormwater treatment plant This study tries to derive the optimum management practices for nonpoint source pollution by analyzing the pollution load reduction effect between different alternatives using the Storm Water Management Model
Proper storage capacity for stormwater pit
A stormwater pit temporarily keeps stormwater runoff during a rainfall to prevent rapid outflow of stormwater, and the storage water in the pit is transferred to the treatment plant after the rain stops The proper storage capacity of the stormwater pit was determined from analyses of the rainfall data
of Pohang-city and pollution reduction effects for different storage capacities using SWMM
First, after an analysis of the Phonag's rainfall data during the recent 43 years (1961 to 2003), we
Trang 4found that 4,168days(97.6%) of the total 4,271 wet days had less than 60mm of rainfall, and 27 days(0.6%)had over 100mm
Next, to analyze the pollution load reduction effects by the installation of the stormwater pit, we set
up alternatives according to the storage capacity of stormwater pit, and simulate the runoff characteristics of each alternative using the SWMM
(a) Case 1 : The storage capacity of the stormwater pit : 60mm/day
(b) Case 2 : The storage capacity of the stormwater pit : 100mm/day
The rainfalls applied for model simulation are shown in Fig 3
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
0: 2: 4: 6: 8: 10:
Time
(a) 30mm/event(2003.4.23)
0.0 2.0 4.0 6.0 8.0 10.0 12.0
0: 2: 4: 6: 8: 10:
Time
(b) 60mm/event(2003.7.13)
0.0
4.0
8.0
12.0
16.0
20.0
9: 5: 1: 21:
9: 5: 1: 21:
Time
(c) Typhoon Rusa(394.5mm/event, 2002.8 6∼8.17)
0 5 10 15 20 25
0: 6: 12:
0: 6: 12:
0: 6: 12:
Time
(d) Typhoon Maemi(175.0mm/event, 2003 9.11∼9.13)
Fig 3 Hyetograph of simulated rainfalls
Fig 4 shows the runoff characteristics for each alternative at the final discharge in the wastewater treatment plant If we look at the runoff characteristics for a rainfall of 30mm/event(Fig 4 (a), (b), (c)), the existing state exceeded 100mg/L of SS, when inflow exceeded the treatment capacity However, Alternatives 1 & 2 showed a good water quality of less than 30mg/L over the whole period During heavy rainfalls of over 60mm/event, the concentration in outflow was considerably reduced by the installation of the stormwater pit However, once the capacity of the stormwater pit and the treatment plant are exceeded, the concentration in outflow rapidly increased
Trang 50 0
0 5
1 0
1 5
2 0
2 5
3 0
0: 2: 4: 6: 8:
Tim e
0 50 100 150 200 250
COD
(a) Present(30mm/event)
0 0
0 5
1 0
1 5
2 0
2 5
3 0
0: 2: 4: 6: 8: 10:00 12:00 14:00 16:00 18:00 20:00 22:00
Tim e
0 50 100 150 200 250
(b) Case1(30mm/event)
0 0
0 5
1 0
1 5
2 0
2 5
3 0
0: 2: 4: 6: 8:
Tim e
0 50 100 150 200 250
(c) Case2(30mm/event)
0
2
4
6
8
10
0: 2: 4: 6: 8:
Tim e
0 50 100 150 200 250
(d) Present(60mm/event)
0 2 4 6 8 10
0: 2: 4: 6: 8:
Tim e
0 50 100 150 200 250
(e) Case1(60mm/event)
0 2 4 6 8 10
0: 2: 4: 6: 8:
Tim e
0 50 100 150 200 250
(f) Case2(60mm/event)
0
4
8
12
16
0: 1: 2: 3: 4: 5: 6: 7: 8: 9:
Tim e
0 100 200 300 400
(g) Present(typhoon Rusa)
0 4 8 12 16
0: 1: 2: 3: 4: 5: 6: 7: 8: 9:
Tim e
0 100 200 300 400
(h) Case1(typhoon Rusa)
0 4 8 12 16
0: 1: 2: 3: 4: 5: 6: 7: 8: 9: 10:00
Tim e
0 100 200 300 400
(i) Case2(typhoon Rusa)
0
4
8
12
16
20
0: 6: 12:00 18:00 0: 6: 12:00 18:00 0: 6: 12:00 18:00
Tim e
0 50 100 150 200 250
(j) Present(typhoon Maemi)
0 4 8 12 16 20
0: 6: 12:00 18:00 0: 6: 12:00 18:00 0: 6: 12:00 18:00
Tim e
0 50 100 150 200 250
(k) Case1(typhoon Maemi)
0 4 8 12 16 20
0: 6: 12:00 18:00 0: 6: 12:00 18:00 0: 6: 12:00 18:00
Tim e
0 50 100 150 200 250
(l) Case2(typhoon Memi)
Fig 4 Result of simulation for each alternative (treatment outflow)
To analyze the nonpoint source pollution reduction effects of each alternative during rainfall, we compared the total pollution load for each alternative The total pollution load was determined by the following formula, where the outflow volume per unit time is multiplied by the concentration of pollutants
▪ Total pollution load(kg/event) = ∑ C i ⅹQ i
Trang 6-10,000
20,000
30,000
40,000
P re s e n t 3,211 3,942 31,303 9,744
Ca s e 1 1,888 3,201 15,120 6,258
Ca s e 2 1,651 2,855 14,685 5,887
30mm
/e ve n t
60mm /e ve n t
Ty p h o o n
R u s a
Ty p h o o n
Ma e mi
-20,000 40,000 60,000 80,000 100,000
P re s e n t 6,322 7,511 82,837 26,814
Ca s e 1 1,027 6,967 60,319 20,909
Ca s e 2 830 6,366 58,332 19,474
30mm /e ve n t
60mm /e ve n t
Ty p h o o n
R u s a
Ty p h o o n
Ma e mi
Fig 5 Total pollution load for each alternative
As shown in Fig 5, the differences of pollution load reduction effects are not great between alternatives When you review the average pollutants reduction effects compared to the existing state, COD was reduced by 37% for alternative 1 and 42% for alternative 2, and SS was reduced by 35% for alternative 1, and 40% for alternative 2
Therefore, considering the fact that about 97.6% of yearly rainfall events are 60mm or lower, and the pollutants reduction effects of alternative 1 and 2 are not very different, our recommendation for the proper storage capacity of the stormwater pit is about 60mm/day
Installation of wastewater treatment facility and stormwater treatment facility
P steel Company has the separated sewer system, and most of the stormwater runoff, especially the initial stormwater runoff flows into and treated in the wastewater treatment plant, but during heavy rainfall, polluted stormwater runoff from the iron ores and coal yards exceeds the capacity of the treatment plant, and directly discharged to the receiving water without proper treatments, deteriorating water pollution
Accordingly, this study reviewed the case that the wastewater is treated in a newly-installed wastewater treatment facility while the stormwater runoff is treated in the existing wastewater treatment plant retrofitted(Alternative 3) To quantify the pollution reduction effects of Alternative3,
we simulated the runoff characteristics of alternative 3 in comparison with Alternative 1
Table 1 Comparison of each alternative
Treatment of
Wastewater treatment plant (Q=50,000 mNewly-installed wastewater 3/day)
Treatment of
Stormwater runoff
Retrofit of existing wastewater treatment plant(Q=200,000 m3/day)
Existing wastewater treatment plant (Q=80,000 m3 /day)
Fig 6 shows the outflow characteristics of each alternative at the final discharge in the treatment plant Alternative 3 showed 20mg/L or lower SS concentration during 30mm/event and 60mm/event conditions as well as the rainfall from typhoon Maemi However, Alternative 1 exceeded 100mg/L of SS concentration for rainfalls of 60mm/event or more As the Typhoon Rusa brought a big rainfall of 394.5mm/event, both alternatives showed more than 100mg/L of SS concentration
Trang 70.5
1.0
1.5
2.0
2.5
0: 2: 4: 6: 8:
Time
0 10 20 30 40 50
COD
(a) Case1(30mm/event)
0.0 0.5 1.0 1.5 2.0 2.5
0: 2: 4: 6: 8: 10:00 12:00 14:00 16:00 18:00 20:00 22:00
Time
0 10 20 30 40 50
(b) Case3(30mm/event)
0
2
4
6
8
10
0: 2: 4: 6: 8: 10:00 12:00 14:00 16:00 18:00 20:00 22:00
Time
0 30 60 90 120 150
(c) Case1(60mm/event)
0 2 4 6 8 10
0: 2: 4: 6: 8:
Time
0 30 60 90 120 150
(d) Case3(60mm/event)
0
4
8
12
16
6: 0:
6: 0:
6: 0:
Time
0 100 200 300 400
(e) Case1(typhoon Rusa)
0 4 8 12 16
6: 0:
6: 0:
6: 0:
Time
0 100 200 300 400
(f) Case3(typhoon Rusa)
0
4
8
12
16
20
0: 6:
0: 6:
0: 6:
Time
0 30 60 90 120 150
(g) Case1(typhoon Maemi)
0 4 8 12 16 20
0: 6:
0: 6:
0: 6:
Time
0 30 60 90 120 150
(h) Case3(typhoon Maemi)
Fig 6 Result of simulation for each alternative(treatment outflow)
Fig 7 shows the nonpoint source pollution reduction effects of each alternative The average
Trang 8pollution reduction effects of Alternative 3 was 27% for COD and 40% for SS In particular, its pollution reduction effects for heavy rainfalls such as 60mm/event and typhoon Maemi were high,
so we can conclude that with Alternative 3, we can secure relatively stable water quality in heavy rainfalls as well
-5,000
10,000
15,000
20,000
Ca s e 1 1,888 3,201 15,120 6,258
Ca s e 3 1,360 2,139 13,040 4,250
30mm
/e ve n t
60mm /e ve n t
Ty p h o o n
R u s a
Ty p h o o n
Ma e mi
-20,000 40,000 60,000 80,000
Ca s e 1 1,027 6,967 60,319 20,909
Ca s e 3 818 1,525 51,320 11,172
30mm /e ve n t
60mm /e ve n t
Ty p h o o n
R u s a
Ty p h o o n
Ma e mi
Fig 7 Total pollution load for each alternative
CONCLUSION
P steel Company has the separated sewer system, and most of the stormwater runoff, especially the initial stormwater runoff flows into and treated in the wastewater treatment plant, resulting in relatively good management of nonpoint source pollution During heavy rainfalls, however, polluted stormwater runoff from the iron ores and coal yards exceeds the capacity of the treatment plant, and directly discharged to Hyeongsan River This may be attributed to natural disasters such
as typhoons, but P steel Company, as a world-class company, tries to achieve perfect environmental management through optimum nonpoint source pollution control by complementing their existing treatment system
As a means to reduce the nonpoint source pollution during rainfall, we have derived the installation
of stormwater pits and stormwater treatment plant We analyzed the pollution load reduction effects
of these alternatives using SWMM
▪ By the installation of stormwater pits, pollution load(SS) could be reduced by up to 35% compared to the existing facility with Alternative 1 (storage capacity: 60mm/day), and 40% with Alternative 2 (storage capacity: 100mm/day) Further, in case of rainfalls of 30mm/event or lower, good water quality of 30mg/L or lower was estimated
▪ In addition to the stormwater pit installation, through a separate treatment of wastewater and stormwater runoff, we could reduce the pollution load(SS) by about 66% compared to the existing situation, and for most simulated rainfalls except typhoon Rusa, good water quality of 20mg/L or lower was estimated
REFERENCE
County of Sacramento(2002), Best management practices for industrial storm water pollution control, Sacramento, USA
Federal register, Final NPDES Storm Water Multi-Sector General Permit for Industrial Activities; Notice(1995), EPA, USA
Trang 9Huber, W.C and R.E Dickinson (1988) Storm Water Management Model, Version 4, User's Manual EPA/600/3-88/001a (NTIS PB88-236641/AS), U.S EPA
Ji-Yong Choi, Chang-Min Shin (2002) Management of Nonpoint Pollution by Reducing Storm Runoff, Report RE-03, Korea Environment Institute, Seoul, Korea
Joint Task Force of the Water Environment Federation and American Society of Civil Engineers
(1998) Urban runoff quality management, Alexandria, USA
Ministry of Environment (2003) The Stormwater Design Manual by the Stormwater Manager Resource Center, Ministry of Environment, Seoul, Korea
P steel Company engineering & construction Co., Ltd (2003) A master plan of drainage system improvement at iron & steel making area in P steel Company, P steel Company engineering &
construction Co., Seoul, Korea
You-Sun Kang (2003) A Study on Model Applied in the Integrated Water Management in a Small Water System Master's thesis, Department of Environmental Engineering, Ewha Womans
University
Wisconsin Department of Natural Resources(1994) Industrial storm water pollution prevention planning, Wisconsin, USA.