Supply Chain Mangagement (SCM) - Implementation Methodology & Best presented by Rachel Hsieh
Trang 1Jul 14, 2006
Presented by Rachel Hsieh
Rachel_hsieh2000@yahoo.com.tw
Supply Chain Management (SCM)
Implementation Methodology & Best
Trang 2• The Introduction of SCM Systems
• The Practice of Multi-sites Production Planning
• SCM Planning Cycle
• SCM Planning Policies
• The Points for Attention When SCM Projects Are Implemented
Trang 3The Introduction of SCM Systems
Trang 4SCM Workflow
Order &
Production Planning
Allocation Planning
Forecasting Netting Master
Planning
Demand Forecasting &
Collaboration
Order Entry
Order Promising
Demand Fulfillment
New Orders,
Forecast Supply Allocation
Central Planning
Supply Plan
Frozen Plan
Supply Plan/
Allocations Latest Available to Promise
Schedule Ship Date
Netted Forecast
Local Planning Order Quoting
Trang 5Introduction to Planning
Systems
• Manufacturing environments vary greatly.
• A planning methodology that works in one environment may fail in another.
• Inadequate analysis often results in
inefficient planning.
• We will discuss various approaches to
planning.
Trang 6Characteristics of Some
Approaches
• Material Requirements Planning
• Manufacturing Resource Planning
– (MRP II) / Order Launch Schemes
• Constraint Based Management
– Theory of Constraints
– Synchronous Flow Management
Trang 7Purchase Req.
Open Order
Trang 82006 Trainers` Training
Manufacturing Resource Planning
(MRP II) Order Launch
• Builds on data of “little MRP”
• Adds business strategy
integration
• Adds rough cut capacity check
• Adds resource capacity check
• Adds shop floor feedback
• Iterative process
Master Planning
Rough Cut Capacity
MRP
Capacity Requirements Planning
Shop Floor Control
Business Planning
Production Planning
Trang 9Manufacturing Resource Planning (MRP II) Order Launch Limitations
• Batch processing
• Uses planned lead times
• Sequentially decomposes solution with long
planning cycles
– Capacity constraints are accommodated iteratively with material planning as a separate step.
– Requirements such as setups are improperly treated.
• Work is pushed through the shop, not pulled
• Local optimization
Trang 102006 Trainers` Training
MRP II Limitations for Planning
Master Planning
Rough Cut Capacity
MRP
Capacity Requirements Planning
Shop Floor Control
Business Planning
Production Planning
for material and capacity
constraints
• Plan doesn’t incorporate
material shortages
• Schedule doesn’t account for
material and capacity
Trang 11Procurement Plan Execution
Work Order Execution
Shipping MDS Relief
CRP RCCP
Trang 12Theory Of Constraints
• Postulated by Dr Eliyahu Goldratt in
1970’s
• Described in the novel “The Goal”
• TOC is an different approach to the
continuous improvement process
• TOC has application to all industries
where there is a flow of information and/or materials.
Trang 13TOC Fundamental Concepts
• Optimization of sub-system components does not equal optimization of the total system
• Standard accounting practices diverts attention away from the real problems
• A new set of operational performance
measurements is required
• The goal of any company is to make money
• A constraint is anything that limits you from
achieving the goal or desired result
Trang 14TOC Improvement Process
• Step 1 IDENTIFY the system’s constraints
• Step 2 EXPLOIT the system constraint (I.e
squeeze the most possible from the limits of the current process)
• Step 3 SUBORDINATE everything else to Step
2 (I.e try to synchronize flow, or do anything
else
• Step 4 ELEVATE the system constraint
• Step 5 If the constraint is BROKEN, go back to
step 1
Trang 15Advanced Planning Systems (APS)
Trang 16Why Is MRP Not Enough?
• Demand Cannot Be Sorted by Our Prefer Sequence The Demands Can Only Be Planned by Their
Requirement Time
• Some MRP Systems Don’t Consider about Order Status
• Lacking Simulation Functions
• Not Considering about Capacity and Transfer Batch for Every Workstation
Trang 17The Advantagea of APS
̇ Account for material and capacity
̇ Reduce planning cycle time
̇ Get more SCM information
̇ Strength SCM process
̇ Reduce inventory
Trang 18Adexa’s Unified Environment
ERP Users
U D S
Unified Data Server
Local Unified Data Server
ERP Users
ERP Users
Demand Planning ( DP DP) Global Strategic Planning Planning ( (GSP GSP )
Strategic Planner
Factory Planning Engine
Supply Chain Planner
Decision Analysis User
GRAServer
Web Access
ATP Users
Marketing Planner
Web Access
SC Agents (purchasing, etc.)
Also connection to existing order entry front end
PP
Factory Planning Engine
Factory Planners
Factory Planning Engine
UDS = Adexa Unified Data Server
Trang 19Active Data Warehouse
(Using Common Data Model)
DP
Customers, Products, Forecasts, Orders, Shipment, Backlog Info
FNE
Customers, Products, Confirmed Orders
Forecast
MP
Supply Chain Data WIP, fixed wafer start plan, Order Backlog
Netted Forecast
DF
ATP/CTP
Customer Allocation, Order Status
FP FP
FP FP
Work Orders Exceptional Work Orders
Sales Order
Info
DB
Order Inquiry
Order Promise
Trang 20The Practice of Multi-Sites
Production Planning
Trang 21SCM Planning Cycle
Trang 22tion Pla
n
MO Sch edu le
MO Sch edu
le
E-Procurement
Planning Server Procure Req.
Trang 242006 Trainers` Training
Rhythm Planning Cycle
Modify Plan
Spec Files
Rhythm Memory- Resident Data
Generate Plan
Modify Plan
4
5
6 7
DOWNLOAD DATA
Download data from
execution system to ASCII
files on periodic basis
1
SERVER STARTUP
Pull data from ASCII files to memory-resident using spec file mapping Generate material-constrained, infinite capacity plan(ICP)
2
3
RUN CLIENT
Generate client/user-specific screen using ad files
5
Trang 252006 Trainers` Training
Summary—Typical Rhythm
Planning Cycle
Save Plan
Detailed Scheduling
Auto Capacity
Capacity Planning
Material Planning
Data Cleanup
Approval Process 1
9 Save Plan to Simulation Database
Management Approval Save Plan to Production Close Loop
10 11 12 13
Trang 262 FP Plan
- Infinite Capacity, Finite Material Plan
- Finite Capacity Balance
-Confirm Schedule Ship date
-Confirm Promise Date
1 Data Download
3 Data Feedback
DECISION POIN TS
Planning Cycle
4 MC
- Check material issues
Trang 27SCM Planning Policies
Trang 28The Method to Plan a Master Schedule
• Determine profile buckets according to Master Planning buckets
• Determine how forecast is distributed into profile buckets considering
– demand profile within forecast bucket or
– Preferences in Master Planning due to
material/capacity availability or other constraints
• Determine from which distribution bucket’s
forecast to net promised order quantity
• Sort all demands by demand priority
• Estimate capacity
Trang 29Forecast Policy 1 - Single Request
Profiling
1000
On the First Day of the Bucket
Trang 30Forecast Policy 2 - WEEKLY
DP
MP
250 F.Req
250 F.Req
250 F.Req
250 F.Req
Profiling
1000 Forecast
10/2005
Trang 31120 F.Req 10/01/05
120 F.Req 10/11/05
40 F.Req 10/28/05
Profiling
1000 Forecast
10/2005
Trang 321000 Forecast
10/2005
Trang 33Oct 2005
1000 Forecast
Sep 2005
166 233 233 233 231 225 225 225 229
Trang 34Forecast Netting Policy
1-PROPORTIONAL
9/10 Order for 800
• Total forecast 1000 in Sep Forecast Bucket
• Netted Forecast in Weekly buckets
• 1000 – 800 = 4 * 50
Trang 35Forecast Netting Policy 2 - NEAREST
9/10 Order for 800
• Total forecast 1000 in Sep Forecast Bucket
• Netted Forecast in Weekly buckets
• Nets 250 in week 2 only
Trang 36Forecast Netting Policy
3-BACKWARD_AND_FORWARD
9/10 Order for 800
• Total forecast 1000 in Sep Forecast Bucket
• Netted Forecast in Weekly buckets
• Nets 800 in the following sequence
• 250 from week2, 250 from week1, 250 from week3, 50 from week4
Trang 37Inventory Assignment
Prioritize Demand Orders
Sort prioritized Demand Orders
Sort parts from end-item
to raw materials
Calculate demands
Allocate supplies
Trang 38Sort Demands by Demand Priority (1)
Demand Order Due Date Quantity Priority
ORDER_1 09/14 250 100
ORDER_2 09/14 50 100
ORDER_3 09/13 150 100
Forecast_1 09/14 100 0
Trang 39Sort Demands by Demand Priority (2)
Demand Order Due Date Quantity Priority
ORDER_3 09/13 150 100
ORDER_2 09/14 50 100
ORDER_1 09/14 250 100
Forecast_1 09/14 100 0
Trang 40Inventory Preprocessing
• Sort routings for each part by date-effectivity
• Calculate demand_sort_priority for each
demand order based on due date, quantity, and priority
• Sort demand orders using the
demand_sort_priority.
• Sort parts from downstream to upstream for a part sequence
Trang 41• Sort the Parts to obtain a part sequence:
– If part B follows part A in the part sequence,
then in no BOM can part B be downstream to part A
Trang 42Inventory Preprocessing
• Iterate through demand orders and post
demands on part buffers
• Iterate through supplies (PO’s, Unassigned
inventory, etc.) and post supplies at part buffers
Trang 442006 Trainers` Training
Inventory Preprocessing
Part Buffer A
Demand 1
Demand 2
Demand 3
Part Buffer B
Mfg 1
Mfg 2
Part Buffer C
Part Buffer D
First: Determine demands on highest level part
Second: Manufacturing orders for A appear as demand for B
Third: Demands for Bcreate demand for C and D
Fourth: Demands for C and D require PO’s to satisfy
Trang 45Depth-first Problem Fixing
• Sort the demand orders using the demand sort priority
• Starting from the highest priority demand order, fix problems
– using alternate parts
– alternate routings for short orders
– changing decisions to make, procure, use
surplus etc
Trang 46CAO - Concept
Step -1 Run Infinite Capacity Plan
a Will identify Material and Capacity
problems
b Fix Material problems
Step - 2 Run Finite Capacity Plan - CAO
a Will attempt to fix Capacity problems
Trang 47CAO - Resource Criticality
Trang 48CAO - Resource Criticality
Step - 2 (Contd.) Once resource identified it will
start with the earliest overloaded bucket
1 Which tasks among in the bucket to
consider for moving ?
Time
Trang 49CAO - Resource Criticality
CAO Priority: All tasks in a bucket are assigned
Trang 50CAO - Resource Criticality
CAO Priority=LPST - start_time
LPST
1
start_time
Trang 51CAO - Resource Criticality
Pull-Offload-Push - First Pass
1 2
Trang 52CAO - Resource Criticality
Pull-Offload-Push
2 3
3 The resource overload in bucket 4 solved
So go to next overloaded bucket ie., 5
1
Trang 53CAO - Resource Criticality
Pull-Offload-Push - First Pass
2 3 1
Trang 54CAO - Resource Criticality
Pull-Offload-Push - First Pass
2 3 1
4 End of bucket reached Repeat procedure from start of the bucket
Trang 55CAO - Resource Criticality
Pull-Offload-Push - Second Pass
2 3 1
Trang 56CAO - Resource Criticality
Pull-Offload-Push - Second Pass
2
3 1
Trang 57CAO - Resource Criticality
Pull-Offload-Push - Third Pass
̶ Cannot pull any tasks due to MATERIAL
CONSTRAINT
̶ OFFLOAD if alternate exists
̶ Push - Higher CAO Priority pushed first
2
3 1
Trang 58• SCM System plan the starting time according
to order delivery date, the current
capacity and material
• The work orders can be consolidated
• All planning result can be input into ERP System
Trang 59Procurement Policy (1)
• It’s allowed to consolidate the
procurement orders of the same
material in a period.
• The failure rate and shrinkage rate should be considered about
Trang 60Procurement Policy (2)
procurements is today, the planned orders can
be input into ERP System
reports
ERP System, we need to use alerts to notice the key persons.
Trang 61What Information can Suppliers get from
– Shipping date, shipping location, the total output quantity of the PO
– The information about material receiving
– The information about material returning
– The information about late orders
– The time to create an invoice and invoice number
– Payment Time, Amount of Money , Account, Payment Term
Trang 62The Points for Attention When SCM
Projects Are Implemented
Trang 63Acceptance Test
25%
Deploy, Monitor &
Transition
10%
Develop Solution
35%
Business Release Activities
Measure Value Delivered
Assess Delivered Value
Project QA Review
End User Acceptance
Technical Model Review
Sign Contract
Solution QA Review
Project Kick-off
Average 6 months
Trang 64SCM Project Management
Risk Management Scope Control Management of client expectation
Quality Management Management of Project Team
Proposal Presentation
Project Startup
Project Execution
Project Completion
Trang 65Identify Project Risk
Average risk projects
Low risk projects
Technology Risk
Implementation Risk
Economic Risk
Organization Risk
Expected IS benefits difficult to achieve
Expected IS benefits likely to achieve
Expected IS benefits almost certain
to achieve
Major realignment
of organizationa
l resources
Minor realignment
of organizationa
l resources
Compatible with existing organizationa
l structure
Regulatory Risk
Expected Major government policy change
Expected Minor government policy change
Compatible with existing
government policy
Trang 66Key Success Factors
• Business Focused Implementation Strategy
– Establish current baseline and target business value to be derived
– Establish a clear relationship between requirements and business value
• Client Commitment
– Strong feeling of project ownership (Its OUR project )
– Executive Management support
• Supply project with required resources
• Enable changes in business policies, procedures, and measurements
• Remove road blocks and broker rapid resolutions of issues
– User driven with strong support from IT Function
– Continuity / Stability of project team
• Delivering Early and Often
– Maintain a Sense of urgency -make decisions, take actions, and move on – Project momentum accelerates with production use
– Rapid realization of a ROI speaks loudly and clearly to the project’s success
Trang 67Thank You!