Rigid Pavements for Roads, Streets, Walks and Open Storage Areas - Mobilization Construction Criteria and standards presented herein apply to construction considered crucial to a mobilization effort . These requirements may be altered when necessary to satisfy special conditions on the basis of good engineering practice consistent with the nature of the construction . Design and construction of mobilization facilities must be completed within 180 days from the date notice to proceed is given with the projected life expectancy of five years . Hence, rapid construction of a facility should be reflected in its design. Time-consuming methods and procedures, normally preferred over quicker methods for better quality, should be de-emphasized . Lesser grade materials should be substituted for higher grade materials when the lesser grade materials would provide satisfactory service and when use of higher grade materials would extend construction time . Work items not immediately necessary for the adequate functioning of the facility should be deferred until such time as they can be completed without delaying the mobilization
Trang 1ENGINEER MANUAL EM 1110-3-132
April 1984
ENGINEERING AND DESIGN
RIGID PAVEMENTS FOR ROADS, STREETS,
WALKS AND OPEN STORAGE AREAS MOBILIZATION CONSTRUCTION
DEPARTMENT OF THE ARMY CORPS OF ENGINEERS OFFICE OF THE CHIEF OF ENGINEERS
SOFTbank E-Book Center Tehran, Phone: 66403879,66493070 For Educational Use
Trang 2DEPARTMENT OF THE ARMY EM 1110-3-132
U S Army Corps of Engineers
1 Purpose This manual provides guidance for the design of rigid pavements
for roads, streets, walks and open storage areas at U S Army mobilization
installations
2 Applicability This manual is applicable to all field operating
activities having mobilization construction responsibilities
3 Discussion Criteria and standards presented herein apply to construction
considered crucial to a mobilization effort These requirements may be
altered when necessary to satisfy special conditions on the basis of good
engineering practice consistent with the nature of the construction Design
and construction of mobilization facilities must be completed within 180 days
from the date notice to proceed is given with the projected life expectancy of
five years Hence, rapid construction of a facility should be reflected in
its design Time-consuming methods and procedures, normally preferred over
quicker methods for better quality, should be de-emphasized Lesser grade
materials should be substituted for higher grade materials when the lesser
grade materials would provide satisfactory service and when use of higher
grade materials would extend construction time Work items not immediately
necessary for the adequate functioning of the facility should be deferred
until such time as they can be completed without delaying the mobilization
effort
FOR THE COMMANDER :
PAUL F ANAUGColon9&1 Corps of EngineersChief of Staff
Trang 3Engineer Manual
DEPARTMENT OF THE ARMY EM 1110-3-132
U S Army Corps of EngineersWashington, D C 20314
Engineering and DesignRIGID PAVEMENTS FOR ROADS, STREETS, WALKS
AND OPEN STORAGE AREASMobilization Construction
Paragraph PageCHAPTER 1 GENERAL
Purpose and scope 1-1 1-1Basis of pavement design 1-2 1-1Frost conditions 1-3 1-1Soil stabilization 1-4 1-2Concrete quality 1-5 1-2Walks 1-6 1-2CHAPTER 2 SUBGRADE
Preliminary investigations 2-1 2-1Soil classification
and tests 2-2 2-2Compaction 2-3 2-2Treatment of unsuitable
materials 2-4 2-2Determination of modulus of
subgrade reaction 2-5 2-3CHAPTER 3 BASE COURSES
General requirements 3-1 3-1Compaction 3-2 3-1Materials 3-3 3-1CHAPTER 4 VEHICULAR TRAFFIC
Effect on pavement design 4-1 4-1Traffic evaluation 4-2 4-1
Trang 4EM 1110-3-132
9 Apr 84
Paragraph PageCHAPTER 6 REINFORCED RIGID PAVEMENTS
Application 6-1 6-1Design procedure , 6-2 6-1Limitations 6-3 6=2Reinforcing steel 6-4 6-4Design details 6-5 6-4CHAPTER 7 PAVEMENT JOINTS
Joint types and usages 7-1 7-1Joint design 7-2 7-3Joint spacing 7-3 7-5Joint sealing 7-4 7-6CHAPTER 8 OPEN STORAGE AREAS
Parking areas 8-1 8-1Motors pools or motor
storage areas 8-2 8-1Open storage of supplies
and materials '8-3 8-2CHAPTER 9 OVERLAY PAVEMENTS
General 9-1 9-1Definitions and symbols for
overlay pavement design 9-2 9-1Preparation of existing
pavement 9-3 9-2Rigid overlay of rigid base
pavements 9-4 9°-3Reinforced rigid overlay of
rigid base pavements 9-5 9-4Rigid overlays of flexible
base and composite basepavements 9-6 9-4Nonrigid overlay of rigid
base pavements 9-7 9-5Overlays in frost regions 9-8 9-6
Trang 51-2 Basis of pavement design
CHAPTER 1GENERAL
EM 1110-3-132
9 Apr 84
1-1 Purpose and scope This manual provides criteria for the design
of rigid pavements for roads, streets, walks, and open storage areas at
U S Army mobilization installations for the loadings and conditionsset forth herein
a Design factor The prime factor influencing the structuraldesign of a pavement is the load-carrying capacity required For rigidpavements, the slab thickness necessary to provide the desired
load-carrying capacity is a function of five principal variables : (a)vehicle wheel load or axle load, (b) configuration of the vehiclewheels or tracks, (c) volume of traffic during the design life of thepavement, (d) modulus of rupture (flexural strength) of the concrete,and (e) modulus of subgrade reaction
b Pavement stresses The rigid pavement design procedurepresented herein is based on the critical tensile stresses producedwithin the slab by the vehicle loading Maximum tensile stresses inthe pavement occur when the vehicle wheels are tangent to a free orunsupported edge of the pavement Stresses for the condition of thevehicle wheels tangent to a longitudinal or transverse joint are lesssevere due to the use of load-transfer devices in these joints totransfer a portion of the load to the adjacent slab Other stresseswhich, due to their cyclic nature, will at times be additive to thevehicle load stresses include : (a) restraint stresses resulting fromthermal expansion and contraction of the pavement and (b) warpingstresses resulting from moisture and temperature gradients within thepavement
c Vehicle loadings The criteria presented in this manual areapplicable to rigid pavement design requirements for all Army vehicles For determining pavement design requirements, all vehicles have beendivided into three general classifications : (a) pneumatic-tiredvehicles, (b) track-laying vehicles, and (c) forklift trucks (includingboth solid and pneumatic tires) By relating each vehicle, based onthe wheel configuration and loading, to an equivalent number of
Trang 6EM 1110- 3-132
9 Apr 84
on pavements or pavement bases, the design procedures outlined in EM
1110-3-138 should be followed
1-4 Soil stabilization In some instances, unsuitable or adverse
soils may be improved economically by stabilization with such materials
as cement, fly ash, lime, or certain chemical additives whereby the
characteristics of the composite material become suitable for subgrade
purposes When this is the case, the design procedures outlined in EM
1110-3-137 should be followed
1-5 Concrete quality The criteria contained in EM 1110-3-135 are
applicable to the design of rigid pavements for facilities covered by
this manual Particular attention must be given to providing a
nonslippery surface Concrete flexural strength will be determined in
accordance with ASTM C 78
1-6 Walks Portland cement walks may be provided where pedestrian
traffic justifies this type of construction Normally, the design
thickness for walks will be 4 inches Where it is necessary and
desirable to continue the walk across driveways, private entrances,
etc , provided for vehicle crossings, the thickness of the walk should
be increased to provide sufficient strength to support the vehicular
loads to which such portions of the walks will be subjected Concrete
walks should be grooved transversely into rectangular areas at 3- to
5-foot intervals to create planes of weakness for control of
contraction cracking The depth of such grooves should be a minimum of
one-fourth the thickness of the slab Expansion joints consisting of
approved preformed bituminous filler or wood, approximately 1/2-inch
thick, should be installed to surround or to separate all structures or
features which project through or against the sidewalk slab Expansion
joints of a similar type should be installed at regularly spaced
intervals transversely across the sidewalk slab The spacing for such
joints should be not less than 30 feet nor more than 50 feet
Trang 7CHAPTER 2SUBGRADE
Erg 1110-3-132
9 Apr 84
2=1 Preliminary investigations The subgrade provides a foundationfor supporting the pavement and base course As a result, much of therequired pavement thickness and the performance obtained from thepavement during its design life will depend on the strength anduniformity of the subgrade It is desirable a thorough investigation
of the subgrade be made so that the design and construction will insureuniformity of support for the pavement slab and realization of themaximum strength potential for the particular subgrade soil type
a Site investigations Insofar as time will allow, investigations
of subgrade conditions at the site of proposed construction should be
performed to determine the engineering characteristics of the subgradesoils, and the extent of any peculiarities of the proposed site whichmight affect pavement behavior Such investigations should determine
the general suitability of the subgrade soils based on : (a)
classification of the soil, (b) moisture-density relation, (c) degree
to which the soil can be compacted, (d) expansion characteristics, (e)
susceptibility to pumping, and (f) susceptibility to detrimental frost
action In order to give consideration to factors that may affect the
performance of the pavement, a review of the service history of
existing pavements on similar subgrades in the locality of the proposed
site should be made The engineer is cautioned that such factors as
ground water, surface infiltration, soil capillarity, topography,
rainfall, and drainage conditions also may affect the future support
rendered by the subgrade
b Soil conditions A general picture of the subgrade conditions
to assist in determining the representative soils should be developed
Field reconnaissance should be made to study landforms and soil
conditions in ditches and cuts Full use also should be made of
existing agricultural soil maps and geological maps in ascertaining
subgrade conditions Advice from contractors actively involved in the
subject area should be solicited
(1) Additional subsurface explorations should be made in thoseareas where the initial investigation indicates unusual or potentially
troublesome subgrade conditions Subsurface explorations should be
Trang 8EM 1110-3-132
9 Apr 84
2-2 Soil classification and tests All soils should be classified in
accordance with the Unified Soil Classification System as given in
MIL-STD-619
2-3 Compaction Compaction improves the stability of the subgrade
soils and provides a more uniform foundation for the pavement slab or
base course The CE-55 soil compaction test is used to determine the
compaction characteristics of the subgrade soils and is given in
MIL-STD-621 This is abbreviated as a percent of maximum density
Density measurements could also be made by the following procedure :
- Materials representing the soils at the project site are taken to
a laboratory where moisture-density relationships are ascertained(ASTM D 1557) From these relationships, the material's maximumdensity, occurring at optimal water content, is determined These relationships establish the bases to which fieldmeasurements are compared
- Field in-place density tests are made at critical locations atthe construction site These tests can be the sand-cone test(ASTM D 1556), the balloon test (ASTM D 2167), or the nucleartest (ASTM D 2922) In-place density test values are thendivided by the maximum obtainable and multiplied by 100 to obtainthe percent maximum density
a Cut sections With the exception of those areas in which thesoil exhibits expansive characteristics or those areas composed of
cohesionless sand or sandy gravel subgrades, the entire subgrade area
should be scarified, moistened, if necessary, to approximately optimum
moisture content, and compacted to a minimum of 90 percent of maximum
density If the densities of the natural subgrade materials are equal
to or greater than 90 percent of the above-mentioned maximum value, no
rolling is necessary other than that required to provide a smooth
surface In the case of cohesionless sands or sandy gravels, these
materials should be compacted to a minimum of 95 percent of maximum
density For all subgrade soil types, it is required that the subgrade
under the pavement slab or base course be compacted to a depth of 6
inches
b Fill sections With the exception of fills composed of soilsexhibiting expansive characteristics or those composed of cohesionless
sands or sandy gravels, all fills should be compacted to a minimum of
90 percent of maximum density In the case of fills composed of
cohesionless sands or sandy gravels, the entire depth of the fill
should be compacted to a minimum of 95 percent of maximum density
2-4 Treatment of unsuitable materials Materials unsuitable for
pavement subgrades are :
- organic soils - top soil, loam, peat, bog, etc
Trang 9- excessively shrinking or expanding soils upon drying or moistureabsorption
- excessively wet soils such as quicksand or mud
- soils which show a marked decrease in stability when scarified,worked, or rolled
Such soils should be removed and replaced, or covered with soils whichare suitable The depth to which such adverse soils should be removed
or covered depends on the soil type, drainage conditions, and depth offreezing temperature penetration and should be determined by the
engineer on the basis of judgment and previous experience, with dueconsideration of the traffic to be served and the time elementinvolved
2-5 Determination of modulus of subgrade reaction For the design ofrigid pavements, the modulus of subgrade reaction, k, is used for
design purposes It usually is determined by the field plate-bearingtest However, when time will not allow for this testing, the subgrademodulus value can be determined from figure 2-1
EM 1110-3-132
9 Apr 84
Trang 10EM 1110-3-132
9 Apr 84
CALIFORNIA BEARING RATIO - CBR
PCA Soil Primer (EB007 068), With Permission of the Portland Cement
Association, Skokie, IL
FIGURE 2-l APPROXIMATE INTERRELATIONSHIPS OF SOIL
CLASSIFICATION AND BEARING VALUES
2 3 4 5 6 T 8 9 10 15 20 25 30 40 50 60 TO 80 90 1
r~~~~~ir~r~rrrrr~rmr
IyIUNIFIE - "
~ri"~.t-arri
=.rr~~"IrrrrAASHTO CLASSIFICATION
v ad.
r~
-MFEDERAL AVIATION
Trang 11CHAPTER 3BASE COURSES3-1 General requirements Base courses may be required under
rigid pavements for the purpose of : (a) providing additional
structural strength, (b) providing a more uniform bearing surface
for the pavement, (c) replacing soft, highly compressible or
expansive soils, (d) providing protection for the subgrade against
detrimental frost action, (e) providing drainage, and (f)
providing a suitable surface for the operation of construction
equipment during adverse weather conditions Base courses, where
required, will be a minimum of 4 inches in thickness over all
subgrades The designer is cautioned against the use of fine-grained
material for leveling courses or choking open-graded base courses since
this may create a pumping condition Positive drainage should be
provided for all base courses to insure against water being trapped
directly beneath the pavement and saturation of these layers, thus
inviting the pumping condition that the base course is intended to
prevent The use of base course for subsurface drainage is discussed
further in EM 1110-3-136
3-2 Compaction Where base courses are used, the base-course
material should be compacted with the same procedures as
recommended for subgrades in paragraph 2-3 High densities are
desirable to reduce future consolidation to a minimum
3-3 Materials If conditions indicate that a base course is
desirable, an investigation should be made to determine the
source, quantity, and characteristics of the available materials
The base course may consist of natural materials, processed
materials, or stabilized materials The material selected should
be the one that best accomplishes the intended purpose of the base
course In general, the base-course material should be a
well-graded, high-stability material In this connection, all
base courses to be placed beneath concrete pavements for Army
roads and streets should conform to the following requirements :
Percent passing No 10 sieve : Not more than 85Percent passing No 200 sieve : Not more than 15
EM 1110- 3-132
g Apr 84
Trang 12CHAPTER 4
4-1 Effect on pavement design In order to determine the pavement
thickness required for an adequate design, it is necessary that the
designer obtain traffic data which will include : (a) the types of
vehicles to be served (passenger cars, light trucks, heavy trucks,
tanks, etc ), (b) the distribution of the vehicles by type, (c) vehicle
loadings, including the maximum single-axle and tandem-axle loadings
for pneumatic-tired vehicles and the gross weight of the heaviest
track-laying vehicle expected, and (d) the average daily volume (ADV)
of traffic which, in turn, determines the total volume of traffic
anticipated during the design life of the pavement
4-2 Traffic evaluation
VEHICULAR TRAFFIC
a Pneumatic-tired vehicles To aid in evaluating vehiculartraffic for the purpose of pavement design, pneumatic-tired vehicles
have been divided into three groups, as follows :
- Group 1 Passenger cars, panel trucks, and pickup trucks
- Group 2 Two-axle trucks
- Group 3 Three-, four-, and five-axle trucks
EM 1110-3-132
9 Apr 84
Pneumatic-tired vehicular traffic has been classified into four general
categories based on the distribution of vehicles from each of the three
groups listed above These traffic categories are defined as follows :
Category I - Traffic composed primarily of passenger cars,panel and pickup trucks (Group 1 vehicles), and containing notmore than 1 percent two-axle trucks (Group 2 vehicles)
Category II - Traffic composed primarily of passenger cars,panel and pickup trucks (Group 1 vehicles), but containing asmuch as 10 percent two-axle trucks (Group 2 vehicles) Notrucks having three or more axles (Group 3 vehicles) arepermitted in this category
Category III - Traffic containing as much as 15 percenttrucks, but with not more than 1 percent of the total trafficcomposed of trucks having three or more axles (Group 3
vehicles) Category IV - Traffic containing as much as 25 percenttrucks, but with not more than 10 percent of the total trafficcomposed of trucks having three or more axles (Group 3
vehicles)
Trang 13EM 1110-3-132
9 Apr 84
b Track-laying vehicles and forklift trucks Track-layingvehicles having gross weights not exceeding 15,000 pounds and
forklift trucks having gross weights not exceeding 6,000- pounds
may be treated as two-axle trucks (Group 2 vehicles) and
substituted for trucks of this type in the traffic categories
defined above on a one-for-one basis Track-laying vehicles
having gross weights exceeding 15,000 pounds but not exceeding
40,000 pounds and forklift trucks having gross weights exceeding
6,000 pounds but not exceeding 10,000 pounds may be treated as
Group 3 vehicles and substituted for trucks having three or more
axles in the appropriate traffic categories on a one-for-one
basis Traffic composed of track-laying vehicles exceeding 40,000
pounds and forklift trucks exceeding 10,000-pound gross weight has
been divided: into the following three categories
Maximum Vehicle Gross Weight, BoundsCategory Track laying vehicles Forklift truck
Trang 14CHAPTER 5NONREINFORCED RIGID PAVEMENTS
EM 1110-3-132
9 Apr 84
5-1 Application In general, all rigid pavements for roads, streets,and open storage areas at Army installations will be nonreinforcedexcept for those conditions listed under paragraph 6-1, or unlessotherwise required
requirements Values for the design index to be used during amobilization situation are presented in table 5-1 Thus to arrive atthe applicable design index, the designer needs only to determine thevolume of traffic and the appropriate traffic category based on thedistribution of traffic by vehicle type Once the design index hasbeen determined from table 5-1, the required thickness of nonreinforcedpavement is then obtained from the design chart presented in figure5-1 This design chart is a graphical representation of the
interrelation of flexural strength, modulus of subgrade reaction,pavement thickness, and coverages of the basic 18,000-pound single-axleloading The design chart is entered using the 28-day flexural
strength of the concrete determined in accordance with paragraph 1-5
A horizontal projection is then made to the right to the design valuefor the modulus of subgrade reaction, k A vertical projection is thenmade to the appropriate design-index line A second horizontal
projection to the right is then made to intersect the scale of pavementthickness When the thickness from the design curve indicates a
fractional value, it will be rounded upward to the nearest full inchthickness All nonreinforced rigid pavements will be uniform incross-sectional thickness The minimum thickness of concrete for anyArmy road or street will be 6 inches
b Track-laying vehicles Provision is made herein whereby thedesigner may determine pavement design requirements for track-layingvehicles in combination with traffic by pneumatic-tired vehicles, orfor traffic by track-laying vehicles only In most cases of trafficcombining pneumatic-tired vehicles with track-laying vehicles havinggross weights in excess of 40,000 pounds, the determination of theappropriate traffic category will be governed by the track-laying
Trang 15EM 1110-3-132
9 Azcc84
U S Army Corps of Engineers
V (60-kip track-lay' vehiclea,
l5-kip forklift trucks) :
Table 5-I Rigid Pavement DesigA
Rigid Pamement DesignClassification
Trang 16zWH
NJQXW
Q co
N
800T90780770760750740T30720710700690680
0
670660650640630620610600590580570560550
U S Army Corps of Engineers
EM 1110-3-132
9 Apr 84
NOTE : Minimum allowable thickness of nonreinforced
rigid pavement is 6 inches
FIGURE 5-1 DESIGN CURVES FOR CONCRETE PAVEMENTS, ROADS,
STREETS, AND OPEN STORAGE AREAS
mt
vc N W z
YV
S
HWW
Q
Trang 17EM 1110-3-132
9 Apr 84
vehicle component of the traffic In table 5-1, the traffic for
Categories V, VI, and VII has been divided further into various levels
of frequency If the track-laying vehicle traffic is composed of
vehicles from more than a single traffic category, it will be necessary
for the designer to determine the anticipated frequency of traffic in
each category in order to determine the appropriate design index For
example, 40 vehicles per day of Category VI traffic requires a greater
pavement design index than does one vehicle per day of Category VII
traffic Thus, the designer cannot rely on maximum gross weight alone
to determine rigid pavement design requirements for track-laying
vehicles Once the design index has been determined from table 5-1,
the required thickness of nonreinforced rigid pavement is obtained from
figure 5-1 as described previously
c Design examples Appendix A contains several examples ofnonreinforced rigid pavement design involving various traffic volumes
and types of vehicles
5-3 Design procedures for stabilized foundations
a Soil stabilization or modification Soils that have beentreated with additives such as cement, lime, fly ash, or bitumen are
considered to be either stabilized or modified A stabilized soil is
one that shows improvement in load-carrying capability and durability
characteristics A modified soil is one that shows improvement in its
construction characteristics but which does not show an increase in the
strength of the soil sufficiently to qualify as a stabilized soil The
principal benefits of soil modification or stabilization include :
reduction of rigid pavement thickness requirements when applicable, a
stable all-weather construction platform, reduction of swell potential,
reduction of the susceptibility to pumping, and reduction of the
susceptibility to strength loss due to moisture
b Requirements The design of the stabilized or modified layerswill be in accordance with EM 1110-3-137 To qualify as a stabilized
layer, the stabilized material must meet the unconfined compressive
strength and durability requirements in EM 1110-3-137 ; otherwise, the
layer is considered to be modified
c Thickness design pavement on a modified The thickness requirements for a rigid
soil foundation will be designed as if the layer
Trang 18based on k value of unbound material, inches
Ef = flexural modulus of elasticity
hs = thickness of stabilized layer, inches5-4 Design details Typical details for the design and construction
of nonreinforced, rigid pavements for Army roads and streets are shown
on Standard Mobilization Drawing No XEC-007
EM 1110-3-132
9 Apr 84
ho = ~/hd - (0 0063-3 Ef h s )where
ho = thickness of rigid pavement overlay required over thestabilized layer, inches
hd = thickness of rigid pavement from design chart (fig 5-1)
Trang 19CHAPTER 6REINFORCED RIGID PAVEMENTS
(1) Odd-shaped slabs Odd-shapedusing a minimum of 0 06 percent of steel
other over the entire area of the slab
considered to be one in which the
dimension by more than 25 percent
neither square nor rectangular
EM 1110-3-132
9 Apr 84
6-1 Application Under certain conditions, concrete pavement slabs
may be reinforced with welded wire fabric or deformed bar mats arranged
in a square or rectangular grid The advantages in using steel
reinforcement include : (a) a reduction in the required slab thickness
usually is permissible ; (b) wider spacing between the transversecontraction joints may be used ; (c) the width of crack opening is
controlled, with the result that load transmission is maintained at a
high level at these points and objectionable material is prevented from
infiltrating the cracks ; and (d) differential settlement due to
nonuniform support and/or frost heave is reduced materially Guidance
relative to the use of reinforced pavement is discussed in the
following subparagraphs
a Subgrade conditions Reinforcement may be used to controlcracking in rigid pavements founded on subgrades where differential
vertical movement is a definite potential (for example, foundations
with definite or borderline frost susceptibility that cannot feasibly
be made to conform to conventional frost design requirements as given
in EM 1110-3-138)
b Nonreinforced pavements In otherwise nonreinforced rigidpavements, steel reinforcement should be used for the following
conditions :
slabs should be reinforced
in directions normal to each
An odd-shaped slab islonger dimension exceeds the shorter
or a slab which essentially is
(2) Mismatched joints A partial reinforcement of slab isrequired where the joint patterns of abutting pavements or adjacent
paving lanes do not match, and when the pavements are not positively
separated by an expansion or slip-type joint The pavement slab
directly opposite the mismatched joint should be reinforced with a
Trang 20EM 1110-3-132
9 Apr 84
principle of allowing a reduction in the required thickness of
nonreinforced rigid pavement due to the presence of the steel
reinforcing Essentially, the design method consists of determining
the percentage of steel required, the thickness of the reinforced rigid
pavement, and the maximum allowable length of the slabs A graphic
solution for the design of reinforced rigid pavements is presented in
figure 6-1 Since the thickness of a reinforced rigid pavement is a
function of the percentage of steel reinforcing, the designer may : (a)
determine the required percentage of steel for a predetermined
thickness of pavement, or (b) determine the required thickness of
pavement for a predetermined percentage of steel In either case, it
is necessary first to determine the required thickness of nonreinforced
rigid pavement in accordance with the method outlined previously in
paragraph 5-2 for nonreinforced pavements The exact thickness (to the
nearest 0 1 inch) of nonreinforced pavement, hd, is used to enter the
nomograph in figure 6-1 A straight line is then drawn from the value
of hd to the value selected for either the thickness of reinforced
rigid pavement, hr , or the percentage of reinforcing steel, S It
should be noted that the percentage or reinforcing steel, S, indicated
by figure 6-1, is the percentage to be used in the longitudinal
direction only For normal designs, the percentage of nonreinforcing
steel used in the transverse direction will be one-half of that to be
used in the longitudinal direction Examples of reinforced rigid
pavement design are given in appendix A Once the pavement thickness
and percentage of reinforcing steel have been determined, the maximum
allowable slab length, L, is obtained from the intersection of the
straight line and the scale of L A provision also is made in figure
6-1 for adjusting L on the basis of the yield strength, fs , of the
reinforcing steel Difficulties may be encountered in sealing joints
between very long slabs because of large volumetric changes caused by
temperature changes
b Thickness design on stabilized base or subgrade To determinethe thickness requirements for reinforced concrete pavement on a
stabilized foundation, it is first necessary to determine the thickness
of nonreinforced concrete pavement required for the design conditions
This thickness of nonreinforced concrete pavement is determined
according to procedures set forth in paragraph 5-3 Figure 6-1 is then
entered with the exact thickness of nonreinforced concrete pavement and
the thickness of reinforced pavement and the percent steel determined
as discussed in paragraph 6-2 a above
6-3 Limitations The design criteria for reinforced rigid pavement
for Army roads and streets are subject to the following limitations :
a No reduction in the required thickness of nonreinforced rigidpavement should be allowed for percentages of steel less than 0 06
percent