BRANTAS RIVER BASIN DEVELOPMENT PROJECT The Brantas Project ……… 2 2.1 The Brantas Project and its Development Performance ……… 2 2.2 Institutions Developed during the Course of the Branta
Trang 1JBICI Research Paper No 36-2
July 2008
ISSN 1347-5703
JBIC Institute Japan Bank for International Cooperation
Aid Effectiveness to Infrastructure:
A Comparative Study of East Asia and
Sub-Saharan Africa Case Studies of East Asia
Trang 2JBICI Research Paper No 36-2
July 2008
JBIC Institute Japan Bank for International Cooperation
Aid Effectiveness to Infrastructure:
A Comparative Study of East Asia and
Sub-Saharan Africa Case Studies of East Asia
Trang 3JBICI Research Paper No 36-2
Japan Bank for International Cooperation (JBIC)
Published in July 2008
© 2008 Japan Bank for International Cooperation
All rights reserved.
This Research Paper is based on the findings and discussions of the JBIC The views expressed in this paper are those of the authors and do not necessarily represent the official position of the JBIC
No part of this Research Paper may be reproduced in any form without the express permission of the publisher For further information please contact the Planning and Coordination Division of our Institute.
Trang 4Prof Koji Fujimoto
Takushoku University
Aid Effectiveness to Infrastructure:
A Comparative Study of East Asia and
Sub-Saharan Africa Indonesia Case Study
Trang 6Table of CONTENTS
1 INTRODUCTION ……… 1
2 BRANTAS RIVER BASIN DEVELOPMENT PROJECT (The Brantas Project) ……… 2
2.1 The Brantas Project and its Development Performance ……… 2
2.2 Institutions Developed during the Course of the Brantas Project by Stakeholders ……… 17
2.3 Institutional Development and Development Performance of the Brantas Project ……… 38
3 A COMPARATIVE VIEW ON THE BRANTAS RIVER BASIN DEVELOPMENT PROJECT AND THE CITARUM RIVER BASIN DEVELOPMENT PROJECT ……… 47
3.1 Development Area ……… 47
3.2 Development Principle ……… 47
3.3 Development History ……… 48
3.4 Coordination between Planning and Project Implementation ……… 49
3.5 Project Management Unit ……… 49
3.6 Projects (Master Plans/Studies and Physical Projects) Implemented and External Assistance ……… 51
3.7 Performance (Output and Outcome) ……… 52
3.8 Institutions Created and Developed ……… 52
4 JAKARTA WATER SUPPLY SYSTEM DEVELOPMENT PROJECT (The JWSSD Project) ……… 56
4.1 The JWSSD Project and its Development Performance ……… 56
4.2 Institutions Developed during the Course of the JWSSD Project by Stakeholders ……… 68
4.3 Institutional Development and Development Performance of the JWSSD Project ……… 86
5 CONCLUSION ……… 93
5.1 Stakeholders and Institutions Created/Developed ……… 93
5.2 Performances within the Project Cycle and Spillover Performance outside the Project Cycle ……… 94
5.3 Contributions of Institutions to Performances ……… 94
Trang 71 References for the Brantas Project and the Citarum Project ……… 97
2 References for the JWSSD Project ……… 98
INTERVIEWEES
1 List of Interviewees on the Brantas Project and the Citarum Project ………… 99
2 List of Interviewees on the JWSSD Project ……… 100
Trang 8List of Figures
Figure 2.1: Organization of Brantas River Basin Development Executing Office … 31 Figure 2.2: Linkages between Institutions and Development Performances
of the Brantas Project ……… 46
Figure 4.1: Organization of the Jakarta Project Office -PMU- ……… 79
Figure 4.2: Organization of Pulogadong Project Site Office (Sub-PMU) ……… 79
Figure 4.3: Organization of Buaran Project Site Office (Sub-PMU) ……… 79
Figure 4.4: Organization of PJSIP Project Site Office (Sub-PMU) ……… 80
Figure 4.5: Organization of Ministry of Public Works ……… 81
Figure 4.6: Linkages between Institutions and Development Performances of JWSSD Project ……… 92
Trang 9List of Tables
Table 2.1: Master Plans and Projects Implemented ……… 6
Table 2.2: Dam and Hydropower Projects ……… 7
Table 2.3: Barrage Projects ……… 7
Table 2.4: Irrigation Projects ……… 8
Table 2.5: River Improvement Projects ……… 9
Table 2.6: Debris Control/ Sabo Projects ……… 9
Table 2.7: Installed Capacity of Electricity in Java and in Brantas Basin ……… 10
Table 2.8: Agricultural Land Use and Irrigation ……… 12
Table 2.9: Rice Yields in Brantas Basin ……… 12
Table 2.10: Number of Brantas Office Staff……… 15
Table 2.11: Number of Staff Distributed to Each Organization ……… 16
Table 2.12: Average Annual Income per Farming Household……… 16
Table 2.13: Aid Commitments to Indonesia by Major Donors on CGI Basis ……… 19
Table 3.1: Comparison between Brantas River Basin Development Project and Citarum River Basin Development Project ……… 54
Table 3.2: Summary of External Assistance to the Citarum River Basin Development ……… 55
Table 4.1: Japanese ODA Assistance and Development of Jakarta Water Supply System……… 59
Table 4.2: Summary of Japanese Assistance to JWSSD ……… 61
Table 4.3: Performances in Project Implementation ……… 62
Table 4.4: Planned Costs and Actual Costs ……… 65
Table 4.5: Changes in Project Scope ……… 66
Table 4.6: Financial Internal Rate of Return (FIRR) ……… 67
Table 4.7: Water Treatment Plant ……… 67
Table 4.8: Served Population and Service Ratio ……… 67
Table 5.1: Stakeholders and Institutions Identified ……… 96
Trang 10Acronyms and Abbreviations
AAP Annual Action ProgramADB Asian Development BankCFE Compagnie Francaise d’EnterpriseCGI Consultative Group for IndonesiaCOB Coyne et Bellier ConsultantDWS Directorate of Water SupplyEIRR Economic Internal Rate of ReturnETC East Tarum Canal
FIRR Financial Internal Rate of ReturnGOJ Government of Japan
IDA International Development AssociationIGGI Inter-Governmental Group on IndonesiaIRR Internal Rate of Return
JBIC Japan Bank for International CooperationJICA Japan International Cooperation AgencyJWSS Jakarta Water Supply System
JWSSD Jakarta Water Supply System DevelopmentMDBs Multilateral Development Banks
M/Ps or M/P Master Plans
NK Nippon Koei Co., Ltd
NTC North Tarum CanalODA Official Development AssistanceOECF Overseas Economic Cooperation FundOJT On-the-Job-Training
OMM Operation, maintenance and managementOTCA Overseas Technical Cooperation AgencyPCR Project completion report
PJSIP PAM JAYA System Improvement ProjectPJT Perum Jasa Tirta Public CorporationPLN National Power Company
PMU Project Management UnitSAPROF Special Assistance for Project Formationthe Brantas Project the Brantas River Basin Development Projectthe Citarum Project the Citarum River Basin Development Projectthe JWSSD Project the Jakarta Water Supply System Development ProjectTOR Terms-of-Reference
Trang 11TSL Two Step Loan
WTC West Tarum Canal
WTP Water Treatment Plant
Trang 121 INTRODUCTION
In accordance with the research framework and TOR spelled out in the Framework Paper of this study “Aid Effectiveness to Infrastructure: A Comparative Study of East Asia and Sub-Saharan Africa” (Jerve and Nissanke, 2008), the Indonesian case selected two projects; the Brantas River Basin Development Project (the Brantas Project) and the Jakarta Water Supply System Development Project (the JWSSD Project) In addition, the Citarum River Basin Development Project (the Citarum Project), which is quite similar to the Brantas Project in its natural, climatic and physical conditions, is chosen as a reference project for a brief comparative study against the Brantas Project One of the distinct characteristics common to the Brantas Project and the JWSSD Project is that each Project is composed of multiple individual projects Throughout this paper, therefore, both Projects are analyzed in an aggregate manner, not on an individual project basis
The analytical framework applied to the Brantas Project and the JWSSD Project
is the same It consists of three steps First, a big picture of project development à-vis Japanese assistance is reviewed together with its development performances at each stage of the project cycle (pre-implementation stage, implementation stage and post-implementation stage) Second, major stakeholders involved are specified from the donor side, Japan, and the recipient side, Indonesia Then, a variety of institutions created and developed by all the stakeholders during the course of Project’s realization are identified In doing so, backgrounds and reasons why those institutions are formed are also investigated Third, relationships between project performances perceived
vis-in the first step and vis-institutions identified vis-in the second step are analyzed vis-in such a way as to identify cause-and-effect linkages between them as well as qualitative and quantitative contributions of the institutions related to the performances
In addition, in an attempt to assess the effectiveness of Japanese ODA, the assisted Brantas Project and the Euro/World Bank-assisted Citarum Project are comparatively analyzed, within the analytical framework of the Brantas Project/the JWSSD Project, with institutional development in mind
Japan-In this paper, assuming that all the stakeholders make their best efforts to carry out their roles and responsibilities in the most effective and efficient way or to reduce transaction costs in the North’s terminology and, to this end, develop a variety of institutions, the author defines “institutions” in the broadest sense and, therefore, includes systems, measures, methods, policies, rules/regulations, procedures, modalities, organizations and so forth, anything that can contribute to project performances
Trang 132 BRANTAS RIVER BASIN DEVELOPMENT PROJECT
(The Brantas Project)
2.1 The Brantas Project and its Development Performance
Japan has assisted in the development of the Brantas River Basin for 40 years The
Brantas Project is said to be the flag symbol of the successful cooperation between
Japan and Indonesia on water resources development We, in this sub-section, review
the entire picture of the Brantas Project, as well as continuous and massive Japanese
development assistance together with its performances
(1) Prelude to Brantas River Basin Development
Development of the Brantas river basin began during the Dutch colonial days in the
1840s During the period of World War II and independence, between 1941 and 1947
in particular, the condition and performance of the facilities deteriorated badly due to
the shortage of funds for maintenance In the late 1950s, the government of Indonesia
established a national development policy to develop irrigation and hydropower with
priority to increase food production and to accelerate industrialization The Brantas
river basin was selected as one of the strategic basins for this policy
A Japanese consulting company, Nippon Koei Co., Ltd (NK) was established in
1946 by Mr Yutaka KUBOTA Mr Kubota, in his attempt to foster his consulting
company to be regarded as an international development consultant, visited
Indonesia, Thailand, Burma, India and Pakistan in September 1953 A few years
later, Mr Kubota revisited Indonesia having the Asahan River Hydropower
Development Project in mind and recommended its implementation to the Secretariat
of the President Office The Indonesian authorities then, instead of the Asahan
project, requested Mr Kubota to undertake a pre-investment study on the Brantas
river basin development NK under the guidance of Mr Kubota quickly responded
to this request and prepared a study report on the Brantas river basin development
under Indonesian Government’s contract number: 16/MISPRI-33/59 This report was
initiated by a reconnaissance report completed in October 1959, followed by an interim
report in August 1960 A preliminary report was released in September 1960 which
was finalized as the Comprehensive Report on the Kali Brantas Overall Project in
April 1961, the first Master Plan for the Brantas River Basin Development
In 1961, the Brantas Project was formerly launched under the initial title of “State
Electricity Company, Brantas Hydropower Development Project” as stipulated by the
decree of the Minister for Public Works and Power Generation, number: 16/2/11 dated
Trang 14June 6, 1961 The late Prof Ir Suryono was appointed as the first project manager
NK was awarded contract (No MISPRI/178/62) to undertake the engineering services for the Karangkates dam and power station which was the first priority infrastructure project within the first master plan
(2) Socio-Economic Conditions of the Brantas Basin during the Early Days of Its Development
The Brantas River Basin covering a catchment area of 12,000 km2, blessed with favorable natural conditions such as water resources and a tropical climate, had been developed as the granary of Java for many years Besides, making the most use of its favorable conditions various industries had been developed around Surabaya city This was attributable not only to the above available resources but also to the favorable transportation conditions, such as the fairly developed railway, a highway linked with Middle Java and the second largest sea port located in the center of inter-insular trade among Java, Kalimantan, Sulawesi and other islands
The major industry in the basin was agriculture in which about 70% of the population was engaged Total farmland occupied 730,000ha or about 60% of the basin area Mountain slopes mostly occupied the remaining areas where the lands were not
so suitable for irrigation farming due to the topography and soils as well as limited availability of water
The major agricultural products in the basin were rice, sugar cane, cassava, soybean and maize The total production of milled rice in 1971 was about 600,000 tons, accounting for about 5% of the national production The basin produced about 230,000 tons of sugar annually occupying about 30% of the total production in Indonesia
The population in the basin was about 10 million in 1971 which constituted 13% of the population of Java or 8% of the country’s total The population density in the basin was as high as 850 persons per km2 Population versus land area naturally limited the average holding size of farmland as little as 0.5 ha per farming family There existed substantial surplus labor force in the rural area which would be available for various industries when they were developed later on Such unemployment or underemployment, therefore, could only be mitigated by intensification of crop farming for years to come Thus, special attention had to be paid to the increase of crop yield to raise the living standard and to stabilize the farm economy Crop diversification would have to be studied to improve the diet of the people in the area from depending on starchy foods to protein and vegetable fat foods
Out of 730,000 ha of farmlands in the basin, the paddy area occupied 321,000 ha
Trang 15The irrigation areas which depended on the Brantas main stream were 77,000 ha The
existing intakes for these irrigation areas mostly faced the river directly However, the
river water of the Brantas was not always effectively utilized for these areas due to
the unfavorable condition of intake structures, deterioration of the existing irrigation
facilities and insufficient maintenance and management The river water used
for municipal and pollution control was also limited However, water demand was
gradually increasing along with the progress of industrialization of Surabaya Thus,
much more effective utilization of the water resources was to be planned under a well
balanced distribution of the available river discharge
Against this socio-economic background, efforts to develop the Brantas River Basin
started in the late 1950s under the assistance of the Japanese Official Development
Assistance (ODA) program
(3) Brantas River Basin Development and Japanese Assistance
Since the late 1950s, development of the Brantas river basin has been achieved
using a holistic approach, with well planned, sustainable and environmentally sound
management, based on the philosophy of “One River, One Plan and One Management”
The development projects have been constructed steadily based on four Master Plans
(M/Ps or M/P) which were formulated in 1961, 1973, 1985/86 and 1998 on a 10 year
review basis Each M/P contained several to a dozen feasibility studies The first M/
P (Comprehensive Report on the Kali Brantas Overall Project, 1961) was prepared by
NK with the financial support of the Japanese war reparation fund The second M/P
(Report on the Brantas River Basin Development Plan, 1973) was also formulated by
NK with a T/A grant sponsored by OTCA (present JICA) The third (Final Report for
the Study of Widas Flood Control and Drainage Project Part I & Part II Study, 1985
(I) and 1986 (II)) and the fourth M/P (Operation, Maintenance and Rehabilitation of
Brantas River Basin Development, 1998) were prepared by NK with a T/A grant by
JICA Almost all the projects proposed in the M/Ps were implemented with Japanese
financial loan assistance by OECF (present name is JBIC and hereinafter referred to
as such) In Table 2.1, the four Master Plans, and major development projects proposed
in the M/Ps and implemented over 40 years are sorted out
Throughout the development of the Brantas River Basin, the principle of “One
River, One Plan and One Management” has been well kept The Brantas River has
been the only target There were four M/Ps, but the relationship between them has
been so closely interrelated and synchronized as if they were one long-term plan
Further at an early stage of the Brantas development (1965), the Brantas River
Basin Development Executing Office was firmly established as an independent
Project Management Unit This Unit supervised and implemented the projects in a
Trang 16unified manner This development principle must have been supported partly by NK who had been for over 40 years the sole expatriate consultant for the entire Brantas development.
It is quite interesting to see that some of the projects recommended in a particular M/P were implemented in the following M/P period Tulungagung Diversion Improvement Project and Waruturi Irrigation Project are a case in point They were planned in the M/P II and implemented during the period of the M/P III And it turned out that both projects were Asian Development Bank (ADB) loan-assisted The Japanese ODA loaning institution, JBIC, almost solely provided the financial loan assistance However, the World Bank (IBRD) and ADB as well as Austrian government supported, on an ad hoc basis, some of the projects proposed in the M/Ps
As of 1996, total investment in the Project (except for urban-related development projects) amounted to \216.9 billion including local funds Of this, the foreign currency component amount was \103.7 billion, of which Japan’s loans and grants (including the reparations provided during the early phase of the development) account for approximately 73% Further, it is estimated that a sum almost equal to the above investment to the Brantas Project was invested in the urban related development projects of Surabaya The investments up to 1996 on the Brantas Project are less than US$250 per resident at the 1996 current price basis on a population average
of 25 years In a way, it can be said that an investment as little as US$250 laid the foundation for acceleration of the economic activities of the entire basin
Trang 17Table 2.1: Master Plans and Projects Implemented
(4) Development Performance of Japanese Assistance over 40 Years
(i) Physical Structures Implemented
Almost three dozen physical structures were constructed over 40 years and they are
sorted out and grouped by their characteristics in the 5 tables below
Generally speaking, all those projects were implemented fairly successfully
as planned and considerably satisfied their performance indicators in terms of
conventional evaluation
(a) Dam-cum-Hydropower Projects
Nine multi-purpose dams were constructed, out of which 7 dams were supported
by Japan in one form or another Of the remaining two, one, Sengguruh Dam, was
financially supported by ADB and Austria, and the other, Tulungagung Hydropower,
by Austria Austrian Government supported the latter project in response to
Indonesian Government’s aid request due to the fact that an Austrian contractor
supplied Austrian-made mechanical and electrical equipment to Sengguruh Dam
project, and the Brantas Office as well as the Indonesian Government wanted to
quickly acquire Austrian technologies which were then new to them (Table 2.2 below)
Trang 18Table 2.2: Dam and Hydropower Projects
(b) Barrage ProjectsFor over 40 years 6 barrages, as shown in Table 2.3, were constructed along the Brantas River These barrages were mostly constructed for irrigation purposes, but a couple of them had different purposes such as flood control (New Lengkong Barrage) and water supply (New Lengkong Barrage and Tiudan Headworks) Of these 6 projects, only one, the Mrican Barrage project was financed by ADB This barrage covers the entire Widas river area and ADB as well as IBRD supported the irrigation development in and around the down stream area of the Mrican Barrage Specifically, the Kediri-Nganjuk Groundwater Irrigation project and Warujayeng-Tri Tunggorono Irrigation project was respectively supported by IBRD and ADB (Table 2.4 below)
Table 2.3: Barrage Projects
(c) Irrigation ProjectsEight projects listed in Table 2.4 are characterized as irrigation projects and were constructed successfully over the years The very first project of the Brantas Project was South Tulungagung Drainage project or South Tulungagung Irrigation project (so called, the Neyama Diversion Tunnel project), which was implemented between 1959
Trang 19and 1961 This project was funded by the Japanese war reparation fund
In those days, every year the 3,000 ha marsh area in the Ngrowo river middle
reaches expanded up to 28,000 ha during the rainy season For many years, the
Government of Indonesia tried to construct an open channel to discharge the
rainy season flood water into the Indian Ocean without succeeding NK proposed
to the Indonesian Government a plan to drain these floodwaters directly into the
Indian Ocean by constructing a tunnel (7.2 m in dia ×1,000 m in length) NK and
the Japanese construction company (Kajima Corporation) successfully completed
the project in less than three years as promised to the Government of Indonesia
Indonesian Government high officials were greatly impressed with the level of
Japanese technology used on as well as efficiency and economy of the Japanese
consultant and the contractor that worked for the Neyama Diversion Tunnel project
One of the reasons that NK has been appointed as the main consultant throughout
the Brantas Project must have been due to this early demonstration of success The
Neyama Tunnel project brought about great effects such as the expansion of the rice
growing area by over 25,000 ha and even a reduction of the 3,000 ha marsh by half, an
increase of farming products worth US$2 million per annum which is approximately
equivalent to the construction cost of the Neyama Tunnel project Further, unlike the
pre-tunnel days, malaria has been nearly eradicated in the area, a salient factor not
to be understated Out of the 8 irrigation projects, only three projects were financed
by Japanese assistance As touched briefly in “Barrage Projects” above, ADB played
a substantial role in constructing irrigation facilities under the Brantas Project Out
of the remaining 5 projects, 4 projects by ADB and one by IBRD were financed, yet
NK was the consultant for all 8 projects So far as the irrigation sector projects are
concerned, Japanese assistance did not play a major role The Brantas Project was too
grand for Japan to support totally by itself
Table 2.4: Irrigation Projects
Trang 20(d) River Improvement ProjectsRiver improvement is the backbone of Brantas water resources development, and therefore all 7 projects tabled below were carried out continuously over 30 years in sequence one after another JBIC handled 6 projects along the Brantas main stream over the middle reach, and the lower reach (Porong River and Surabaya River) which runs through the City of Surabaya ADB financed a branch river project, the Widas River Improvement project to support the JBIC-financed Widas Irrigation project (Table 2.5 below)
Table 2.5: River Improvement Projects
(e) Debris Control/Sabo ProjectsTwo major debris control/Sabo projects are listed in Table 2.6 One is the ever-lasting debris control project, financed by the Government of Indonesia, which started in 1960 and is still under implementation This project is meant for eruptive debris control JBIC assisted the other project, Mt Kelud Emergency Debris Control Project, which was to rehabilitate the crater lake diversion tunnel It was completed in 1997
Table 2.6: Debris Control/ Sabo Projects
(ii) Development Benefits(a) Electric Power
Electrification is indispensable to promote the living standard of people through enhanced economic and social activities The electrification rate of the Brantas Basin villages was below 10% in the 1960s
In order to integrate hydroelectric generation as one of the purposes of the Brantas
Trang 21Project, two fundamental principles of planning were employed: 1) hydroelectric
generation is to be introduced where possible, as part of multipurpose development,
along with water resources development, and 2) mini-hydroelectric development is to
be included where economically feasible
The power generation capacity in the basin in 1961 was 31.7 MW for hydroelectric
and 21.6 MW for thermal power (53.3 MW in total) Hydroelectric power was
developed as part of the Brantas Project and as of 1993 it reached 268 MW (Table 2.7),
an 8-fold increase Progress of industrial development in particular further boosted
the demand for electricity in the basin and thermal power generation was drastically
increased As of 1993, the installed capacity of thermal power generation reached
1,350 MW (Table 2.7) Thus, the installed capacity of power generation increased from
52 MW in 1960 to 1,618 MW in 1993
Thanks to the development of electric power generation, the electrification of
the Brantas River villages improved from less than 10% in 1960s to 85% in 1993
Although the effects of the electrification are difficult to measure, there is no doubt
that such progress enhanced substantially the living standard of the Brantas people
Table 2.7: Installed Capacity of Electricity in Java and in Brantas Basin
(b) Flood Control
Flood control was a serious concern not for only the classic Mataram Kingdom (8th
and 10th century AD) but right through to the Dutch colonist as well Rudimentary
dikes and flood retaining structures were constructed as early as the 9th century
The Dutch also constructed various gates and flood diversion channels in the late
19th century However, around 1958, when the Brantas Project was initiated, a huge
amount of debris produced by the eruption of Mt Kelud accumulated on the beds of
the Brantas main stream and its tributaries This sediment deposition decreased the
river discharge capacity especially for carrying floodwaters This incurred flooding
almost every year, which caused human calamities, crop damage and loss of assets
Trang 22In order to prevent the basin from flooding, three measures were introduced in the development planning First, multipurpose dams are to be constructed in the upper reaches to control floods Second, floodwaters of the upper Brantas and its tributaries are to be partly discharged into the Indian Ocean Third, natural retarding basins in the middle reaches of the main Brantas are to be converted to artificial basin for more efficient reduction of the flood runoff in the lower reaches
Most of the measures were successfully carried out in the form of specific projects and, as a result, the Brantas River Basin succeeded in reducing flood damages considerably, as it is evidenced in an article written in Kompas (Indonesian Newspaper), dated February 17, 1993, “Why is it that in the year 1993 there were floods in many places, even in the Citarum River Basin with 3 big reservoirs, but in the Brantas River Basin no floods occurred?”
The total cost of flood control projects of the Brantas Project is estimated to be approximately \85 billion at 1988 prices On the other hand, the estimated savings
in flood related damages to residential, agricultural and social capital is estimated
to be \13.5 billion per annum From these figures alone, the flood control projects can be considered very effective In addition, there must have been invaluable effects brought about by the projects such as the stabilization of livelihoods, improvement of living environments, sophistication of land use, urban development, and promotion of industrialization
(c) Agricultural Production and IrrigationAgriculture is the key industry in the Brantas Basin and, reflecting the serious economic conditions of the country, the Government of Indonesia stipulated self-sufficiency of rice production as the country’s top priority development objective in the first 25 year long-term development plan (PJP I 1969/70 ~ 1993/94) The basin has prospered as Java’s granary since the 1800s, largely due to the then-advanced irrigation system established by the Dutch colonials The irrigation facilities, however, deteriorated during World War II and for subsequent years of political and economic disorder after the war In addition, Brantas irrigation depended on the natural runoff
of rivers, as there were no large reservoirs in the basin
In view of the above, irrigation work was planned and implemented under the following three basic principles: 1) rehabilitation of the existing irrigation system, 2) development of new paddy fields where possible, and 3) supply of sufficient irrigation water through the construction of multipurpose dams in the upper reaches
Thanks to the irrigation projects, the irrigated paddy fields increased 77,000 ha
Trang 23or 25% of the total paddy fields in 1970 to a total of 324,000 ha or 100% in 1993
(Table 2.8) Trends in rice and unit yields are shown for the years 1970-93 in Table 2.9
During these 23 years, the paddy field area increased only 3% (10,000 ha), but the
rice production jumped by 87% and the yield per ha by 81% This was partially due
to the use of fertilizers and improved rice species However, the major factor was the
improved dry season runoff As a matter of fact, cropping intensity increased from
80-90% in the 1960s to 130% by 1993 In addition, the top priority objective of
self-sufficiency of rice production stipulated in the 25 year development plan (PJP I) was
accomplished in the basin in 1978, six years earlier than the target year of 1984
Table 2.8: Agricultural Land Use and Irrigation
Table 2.9: Rice Yields in Brantas Basin
(d) Sabo (Volcanic Disaster Prevention)
Mt Kelud erupts every 15 years on an average The eruption damage falls broadly
into two steps Firstly, an eruption causes the water pooled in the crater’s lake to
run down rivers mixed with ejecta, and the resultant mudflow hits agricultural
fields and houses, causing direct damage (primary damage) Secondly, volcanic ash
accumulates on mountainsides and is then washed down by rainfall This causes a rise
in the riverbeds of the lower reaches over time, eventually causing floods (secondary
damage)
To prevent this damage, two kinds of measures were undertaken: 1) to construct a
diversion tunnel to reduce the amount of water pooled in Mt Kelud’s crater lake, and
Trang 242) to construct sand pockets to check erupted earth.
The lake had 40 million m3 and 20 million m3 of water at the time of the 1919 and
1966 eruptions, respectively Following the vast primary damage, ejecta flowed into the main stream of the Brantas River, raising the riverbeds to as high as 1 ~ 2 m in some places, which consequently caused floods in the Brantas mainstream and the Polong River The years between 1951 and 1990 saw less primary damage since the lake was being drained through a diversion tunnel before the eruptions, reducing the water to 1.8 million m3 and 2.5 million m3, respectively The 1990 eruption occurred after sand pockets and the Sabo dams had been completed at the foot of Mt Kelud, which checked successfully the flow of ejecta into the main stream of Brantas which gave only a slight rise to the river beds
(e) Domestic and Industrial Water Supply to SurabayaDomestic and industrial water supply to Surabaya urban area increased rapidly thanks to the Brantas Project Water supply for domestic and industrial uses in 1970 was 123 million m3 per year and 335 million m3 in 2000 Demand for domestic water increased in accordance with the population growth and improvement of the living standard of the residents of Surabaya Water supply of domestic use, thus, increased from less than 100 million m3 in 1970 to more than 200 million m3
Owing partly to the reliable supply of industrial water, impressive industrial development was recorded Industrial production increased from Rp 41.9 billion in
1970 to Rp 7,723 billion in 2000, which occupied 58% and 77% of East Java’s total production, respectively In terms of the of the number of employees, it increased 30,000 in 1970 to 959,000 in 2000, which shared 9% and 45% of total employees in East Java, respectively
(iii) Contribution to Brantas Economy and National Development ObjectivesThe Indonesian Government historically has three basic priority development objectives; namely, development of human resources, enhancement of national life, and equitable distribution of income and eradication of poverty
(a) Human Resource DevelopmentThe first few Brantas projects commenced under the jurisdiction of different government offices such as the Irrigation Service of the Ministry of Public Works, Surabaya Municipal Irrigation Service, or the State Electric Power Corporation (PLN)
It was, however, soon recognized that the Brantas Project, being a multipurpose Project, would be difficult to carry out within the framework of a single project Thus, the Brantas River Basin Development Executing Office (the Brantas Office)
Trang 25was created in 1965 as a body under the direct supervision of the Ministry of Public
Works, with Mr Suryono appointed as the first General Manager The Brantas Office
was vested two years later in 1967 with the authority broadly covering the office
operations and the project execution including hiring of staff and laborers, the decision
of their treatment, and budget administration Since then, the Brantas Project has
been pursued literally under the “One Management” philosophy
The trends in the number of staff at the Brantas Office are shown in Table 2.10
(excluding general laborers) The Brantas Project employed in its 1970s peak a large
number of staff, up to 7,300 Almost all 7,000 were technical staff In other words,
the Brantas Project trained and fostered, mostly through On-the-Job-Training (OJT),
7,000 engineers and technicians During this period, it was estimated that there
existed almost 30,000 engineers and technicians in Indonesia at large Of these, 7,000
were from the Brantas Project, which accounts for over 20% of the national total of
engineers and technicians
The Faculty of Engineering of Brawijaya University in Malang City, where the
Brantas Office was located, was established in 1963 in close collaboration with the
Brantas Office or Prof Ir Suryono, in particular, who was appointed as the Dean of
the Faculty from 1963 through 1982 During the early stages, the Brantas Project was
the cradle of the Faculty of Engineering and later the Faculty became a foreground
of education for the young engineers of the Brantas Project Thanks to the close and
continuous relationship between them, the Faculty produced 498 graduates by 1983,
and 72 of them (14%) joined the Brantas Office From Table 2.10 below, it is obvious
that most of the staff with the university degree were recruited from the Faculty of
Engineering of Brawijaya University
The Brantas Office, in addition, delivered various types of lectures based on the
practical fieldwork experiences of the Brantas Project to engineering students of other
Universities such as ITB (Institute of Technology Bandung), Institute of Technology
Surabaya and Meurdeka University of Malang
Trang 26Table 2.10: Number of Brantas Office Staff
During the early stages of the Brantas Project (between the early 1960s and the mid-1970s), nearly 50 expatriate consultants per annum on an average were assigned
to a number of on-going projects However, the number reduced gradually and toward the end of the 1990s, down to four or five The number of foreign consultants assigned
to projects varies as they differed a lot in scope and characteristics The Karangkates Dam project implemented from 1962 to 1973 involved 318 foreign consultants and construction guidance engineers in total, or 32 per annum on an average, while the Wlingi Dam from 1972 to 1977 required 44 foreign consultants in total, or 4.4 per annum on an average The reduction of expatriate consultants implies that the local consultants and/or engineers and planners of the Brantas Office acquired considerable technical skills and replaced the foreign consultants Needless to say, the role of Indonesian engineers and planners as well as Indonesian consultants in formulating the M/P II, III and IV increasingly and acceleratingly expanded
(b) Sprouted-out Private/Semi-private Companies
As a result of the human resource development, the Brantas Office sprouted out three independent organizations with a substantial number of its staff during 1980s Namely, P.T Indra Karya (a consulting company) was practically re-established with
500 employees in 1981, P.T Brantas Abipraya (a construction company) was newly established with 519 employees in 1985 and Perum Jasa Tirta (a water resources management public corporation) with 439 employees in 1990, and the Brantas Office was squeezed into a smaller entity as shown in Table 2.11 Thus, the Brantas Office was directly involved in expanding the private sector of the country
Trang 27Table 2.11: Number of Staff Distributed to Each Organization
(c) Development of Economic Welfare
The primary objective of the Brantas Project was to develop basic economic
infrastructure related to water resource development, which in turn accelerated
agricultural development and industrialization through private investment and
which raised the regional economic welfare of the area often measured in GDP In
this sequence the Brantas Project contributed to the improvement of the economic
conditions of the people residing within the entire Brantas Basin
The Indonesian GDP per capita of 1993 was US$674, with that for Java coming
near to the national per capita GDP In comparison, the GDP per capita for the
Brantas Basin was $884, well above the national average And in the same year, it is
recorded that the GDP per capita of Surabaya City was $1,464 which is close to that
of Jakarta, the most developed city in Indonesia These facts prove that the Brantas
Project contributed considerably to lifting up the level of economic welfare of the
people residing in the basin
In terms of farmer household income, a similar fact was observed In 1993, the
average annual income per farming household was Rp 1.63 million for Indonesia as a
whole, while it was Rp 1.52 million for East Java and Rp 1.76 million for the Brantas
Basin As can be seen, the annual growth rate in the 1970s was 0.1% for Indonesia, 1.0%
for East Java and 4.5% for the Brantas Basin This fact as well as figures shown in
Table 2.12 lay a sufficient foundation to believe that the Brantas Project substantially
impacted the income of farming household
Table 2.12: Average Annual Income per Farming Household
Trang 28(d) Poverty Reduction and Income DistributionThe second long-term development plan (PJP II 1994/95~2018/19) was aimed at balanced development of the entire nation with a focus on future regional development
of the eastern part of Indonesia as well as poverty reduction The Master Plan III (1985/86~2002/03) pre-fetched this national development thinking The M/P, as a matter of course, paid special attention to the balanced development of the basin Development projects implemented under the M/P I and M/P II focused on the economic efficiency and priority needs, based on the review of the previous master plan and the development conditions to date Over a 25-year period, many local residents benefited from the projects implemented under the M/P I and II During this period, however, it was impossible to achieve a perfectly balanced development; disparity in development level and living standards of the people in the Brantas Basin was created Against this background, M/P III was formulated in such a way as to develop the lagging regions such as Ngrowo, Widas basin, the upper regions of Lesti, and the surrounding areas too Thus, the Brantas Project would thereby contribute to poverty reduction and equitable income distribution to a wider degree
In addition to the above, some other development impacts were recognized First, the people’s mindset in the basin changed considerably The local residents not only accepted the value of modern living but also motivated themselves to access modern amenities and facilities They also accepted the modern way of work customs and ethics Second, as the reputation of the Brantas Project prevailed internationally, several LDCs who were interested in developing their own river basins sent official missions to Indonesia to study the Brantas Project Bangladesh, Egypt, Viet Nam and Ghana are the countries in point Third but not the last, the projects constructed in the Brantas Project were replicated as national projects in other parts of Indonesia by Brantas-men and Brantas School graduates who were invited and transferred to those projects Those projects include, among others, Klara Irrigation Project (Sulawesi), Tajun and Nawangan Dam (Central Java), Rora Besar Dam (West Nusa Tenggara), Batujai Dam (Lombok Island) and Juran Sate Irrigation (Lombok Island)
2.2 Institutions Developed during the Course of the Brantas Project by Stakeholders
In this sub-section, institutions developed during the course of the Brantas River Basin development, which are believed to have had direct and indirect impacts on the Brantas Project, are identified on a stakeholder-by-stakeholder basis There are 3 stakeholders on the Japanese donor side; namely, the Japanese Government, JICA and JBIC, and 4 stakeholders on the Indonesian recipient side; namely, the Indonesian Government, BAPPENAS, DGWRD of Ministry of Public Works and the Brantas Office All the stakeholders made their best efforts to carry out their roles and
Trang 29responsibilities in a more efficient and effective way or to reduce transaction costs in
the North’s terminology, and, to this end, developed a variety of institutions
(1) Japanese Government
(i) Coordinated Procedure between Planning Assistance (Technical Assistance by ODA
Grants) and Implementation Assistance (Financial Assistance by ODA Loans)
The Government of Japan developed a sequential procedure between technical and
financial assistance at an early stage of its aid to Indonesia The case of Brantas fits
in this formula As a result, the Brantas Project lasted over 40 years until almost all
priority projects recommended in the 4 Master Plans were implemented In a way, the
commitment of the first M/P assistance seems to have meant unwritten commitments
for the following technical assistance and financial assistance for a number of projects
Consequently the way Japan assisted the development of the Brantas River Basin
proved to be more effective, and more efficient with more benefits accruing
(ii) High Level ODA Dialogue Mission to Indonesia
Prior to starting every 5-year development plan (REPLITA), the Government of
Japan made it a rule to send a high-level policy dialogue mission on ODA to Indonesia
and to reach a fundamental understanding on development policies and strategies of
the country for the coming 5 years The results were readily reflected in Japan’s ODA
policies and the actual ODA itself to Indonesia
Thus, the dialogue between the Japanese Government and the Indonesian
Government was an important ceremony to deepen the understanding on their
respective roles and responsibilities for the succeeding 5 years
(iii) Continuous and Annual Commitment of ODA/AID at CGI/IGGI
In 1966, the governments of 14 countries, including Japan, the United States, West
Germany and the Netherlands, formed the Inter-Governmental Group on Indonesia
(IGGI) and its first conference was held in Tokyo, at the request of Indonesian
government for the furtherance of economic assistance Until 1991, economic
cooperation to Indonesia by donor countries and international organizations had
been pledged at the annual conference of IGGI In that year, IGGI was transformed
into the “Consultative Group for Indonesia” (CGI) whose fundamental characteristics
were to be the same as those of IGGI Thus, it has been the practice of Japan to make
an annual commitment of ODA through the CGI And Japanese commitment has
been based on an “add-up” of specifically identified technical and financial assistance
projects Table 2.13 shows that Japan, IBRD and ADB were the major donors and they
jointly aided more than 80% of the total aid to Indonesia, each providing aid almost
equally
Trang 30This modality of logistics was used to economize the time and labor of tedious and lengthy commitment procedures that the Japanese Government would, otherwise, have gone through.
(iv) Procurement Conditions of Loans ~Shift from Tying to UntyingThe Government of Japan, in compliance with DAC resolution of 1974, started to relax its procurement conditions from tying to untying In Indonesia, the LDC untying condition (procurement is tied to Japan and LDCs) was first introduced in 1973 and applied to a couple of loan projects (one of them was the Karangkates project), and this condition was applied to an increasing number of project loans as the years went by
In 1979, the general untying condition was introduced and applied to several projects, and this condition was applied to more loan projects as time passed by By 1988, the general untying condition was applied to practically all loan projects
Thus, most of the Brantas projects committed from 1973 onwards were implemented
in a more economical and efficient manner
Table 2.13: Aid Commitments to Indonesia by Major Donors on CGI Basis
(2) JICAJICA is the sole agency of technical assistance (T/A) of Japanese ODA JICA provides various kinds of T/A such as Development Studies, Acceptance of Trainees, Dispatch of Experts, Japan Overseas Cooperation Volunteers, Emergency Disaster Relief, and the development studies (or the pre-investment studies) are one of the most important JICA’s T/A activities
Trang 31(i) Pre-Investment Studies for the Brantas Project
For the term of over 40 years Japan (JICA) sponsored 4 Master Plans for the
Brantas River Basin Development The first comprehensive master plan commenced
in 1961 and it was periodically reviewed in order to update its contents to cope with
the changing conditions and needs of the subsequent master plans The four master
plans are listed below
The First Master Plan covering 1962 to 1973, prepared by NK and sponsored by
Japanese reparation fund: Comprehensive Report on the Kali Brantas Overall
Project, 1961
The Second Master Plan covering 1974 to 1985, prepared by NK and sponsored
by the Overseas Technical Cooperation Agency of Japan (OTCA): Report on the
Brantas River Basin Development Plan, 1973
The Third Master Plan covering 1986 to 2003, prepared by NK and sponsored
by Japan International Cooperation Agency (JICA): Final Report for the Study
of Widas Flood Control and Drainage Project Part I & Part II Study, 1985 (I) and
1986 (II)
The Fourth Master Plan covering 2004 to 2015, prepared by NK and Nikken
Consultants Co., Ltd and sponsored by JICA: Operation, Maintenance and
Rehabilitation of Brantas River Basin Development, 1998
In addition, feasibility studies for a few dozen projects identified and prioritized in
the M/Ps were carried out by JICA’s assistance and subsequently implemented by
Japanese financial assistance under JBIC
This comprehensive plan making mechanism was considered to be one of the best
ways to prepare long-term development plans and feasibility studies
(3) JBIC
JBIC’s ODA wing is the sole agency of the Japanese ODA loan to LDCs The volume
of ODA lending operations of JBIC used to be as large as a half of that of IBRD and
International Development Association (IDA) combined and its lending conditions
were between of IBRD and IDA
(i) Annual Cyclical Modality on JBIC Loans Commitment to Indonesia
Since the very beginning of Japan’s ODA loan assistance, JBIC in collaboration with
the Japanese Government and the Government of Indonesia had developed an annual
Trang 32cyclical modality of Yen loan commitment and consolidated it as below during the first few years of CGI.
August to September: Selection of Candidate Projects by Each Executing
Agency of the Government of IndonesiaNovember to January: JBIC’s Sector Survey Mission to Indonesia (Policy
Dialogue on Sectoral Development and Discussion of Future Priority Projects in All the Sectors)
January: Finalization of Candidate Projects for Japan’s ODA Loan
Assistance by BAPENAS (vis-à-vis Blue Book)January to February: ODA Loan Request from BAPPENAS to Japanese
Government via Embassy of Japan in JakartaMarch to April: Mission of Japanese Government (Ministry of Foreign
Affairs, Ministry of Finance, Ministry of International Trade and Industry and Economic Planning Agency) to Indonesia
March to May: JBIC Appraisal Mission to Indonesia for Final Selection
of JBIC’s Loan Projects
June to July: Pledge by Japanese Government at CGI MeetingSeptember to October: Conclusion of Exchange of Notes between Japanese and
Indonesian GovernmentSeptember to October: Signing of Loan Agreement between JBIC and Indonesian
Government
This annual cycle made the entire lending operations of JBIC ready to
stand-by, easy to schedule, effective and efficient in terms of cost and timesaving All the Brantas basin projects pledged at CGI were processed to the implementation stage in
a readily prepared and in a timely fashion
(ii) Procurement Guidelines and Procedures of JBIC Loan ProjectsJBIC carried out its project implementation in accordance with two guidelines:
“Guidelines for the Employment of Consultants by JBIC Borrowers” and “Guidelines for Procurement under JBIC Loans” These guidelines laid the foundations for fair, competitive and transparent procurement of consultant services as well as goods and services (contractors) and contributed to the minimization of ill practices of procurement such as those that included corruption, collusion and nepotism Needless
to say, they are quite similar to those of MDBs such as the IBRD and ADB
Furthermore, they gave positive impacts on the consolidation of Indonesian domestic procurement rules and regulations The latest Indonesian procurement guidelines (the
Trang 33Presidential Decree No 16 of 1994 and Ministerial Decree No 158/KDTS/1995) were
stipulated in line with the international guidelines
(iii) Delegation of Procurement Authorities to JBIC Jakarta Office from JBIC HQ
In 1988, JBIC shifted its procurement authorities from its HQ to the Jakarta
Office In this way, the chief representative of the JBIC Jakarta Office was given
full authority to approve or not all contracts as well as contractual procedures
Accordingly, the Jakarta Office increased its staff by assigning HQ staff and started
to employ highly educated Indonesian staff as professionals Both the Japanese
and the Indonesian staff quickly acquired professional knowledge on international
procurement through continuous on-the-job-training
Thus, the transfer of procurement authorities aimed to upgrade quality and speed
of procurement works As a result, for instance, while it took at least two weeks to
complete a contract approval before the transfer, it was reduced into a few days after
the transfer
(iv) Meetings and Workshops for Project Monitoring and Supervision as well as
Disbursement and Procurement Promotion
In 1988, JBIC and the Government of Indonesia agreed in the Master Agreement
(in the case of Indonesia, common clauses applicable to all loan agreements were
extracted and bundled into one agreement which is called “Master Agreement”) that
they exchange views with regard to the progress, completion and operation of the
project and furnish all such information to each other As a result, several methods of
project monitoring and supervision vis-à-vis disbursement and procurement promotion
were stipulated as below
Annual Action Program
In reality, however, JBIC, in collaboration with other stakeholders, established and
carried out the following six workshops/meetings to promote project implementation
(a) Workshop on Procurement and Disbursement
In April every year, the JBIC Jakarta Office hosts, with the help of BAPPENAS,
a workshop on procurement and disbursement concerning JBIC’s Yen loan projects
for newly appointed Indonesian counterpart officers of Executing Agencies (incl
Trang 34DGWRD) The JBIC’s professional staff of Jakarta Office headed by the deputy chief representative gives a series of lectures and they study together with the Indonesian officers problematic cases of past projects.
(b) Annual Action Program Workshop
As a method of project monitoring and supervision, the Annual Action Program (AAP) was introduced formally in 1988 The AAP stipulates the detailed and concrete processing schedule for every JBIC project and its target amount of disbursement for the fiscal year which should be realized by the Executing Agencies (incl DGWRD) and is agreed by JBIC and BAPPENAS who represents the Executing Agencies of all the line ministries The AAP, then, is an important guiding tool for managing the project during the fiscal year The Executing Agencies are responsible for keeping the schedule stipulated in the AAP and give daily attention to the progress of project implementation Monitoring procedures of procurement and making necessary arrangements for achieving the target of project progress and disbursement are the main components of project management In order to keep track of the APP, a quarterly review meeting is also held between JBIC, BAPPENAS, the Executing Agencies such as DGWRD and Ministry of Finance
(c) Weekly Issues Meeting between JBIC and BAPPENASThe deputy chief representative of the JBIC Jakarta Office and one of the Indonesian professional staff have weekly meetings with officers of the BAPPENAS Japan desk to discuss issues which require urgent settlement JBIC’s intention is to cause BAPPENAS to instruct the Executing Agencies to take necessary actions to avoid delay in planned implementation schedules of the project
(d) Quarterly Review Meeting between JBIC, BAPPENAS, Executing Agencies and Ministry of Finance
On a quarterly basis, all the stakeholders of JBIC project implementation gather together at BAPPENAS and review the progress of all on-going projects in line with the AAP If there are any problems and/or issues, responsible stakeholders are requested to take necessary actions without delay
(e) Regular Progress Meeting between JBIC and the Executing Agency on a Staff BasisStaff of the JBIC Jakarta Office meet the officer in charge of the project of the executing agency on a regular basis to monitor progress of project implementation, in addition to day-to-day communication Issues that can not be solved at the staff level are usually brought to the Weekly Issues Meeting between JBIC and BAPPENAS
Trang 35(f) Quarterly Review Meeting between JBIC and the Executing Agency
This is the meeting between the deputy chief representative of the JBIC Jakarta
and the Director General of DGWRD Its aim is to share the knowledge about the
state of affairs of project implementation with the Director General and confirm issues
and problems that need to be solved under his initiatives
All these meetings and workshops were programmed to avoid delays in procurement
and fund disbursement vis-à-vis prompt and timely project monitoring and
supervision
(v) Local Cost Financing Schemes
JBIC provides loans primarily for foreign currency procurement of goods and
services needed for the implementation of a project, while the local currency portion
for local procurement is, in principle, financed by the recipient countries Over the
years, however, cases of developing countries requesting local cost financing has
increased, reflecting their tight budgetary situation
In view that the expansion of the local cost financing makes it probable not only to
prevent new and on-going projects from being delayed or interrupted due to shortages
of local currency funds, but also to assist high priority projects with a high local cost
component, which had not been implemented because of budgetary constraints on
the part of the recipient government, JBIC evolved its local financing scheme in three
separate stages
The first is the “local cost financing loan” that JBIC introduced for Indonesia in
1971, 72 and 73 for the projects committed for assistance in each respective year This
assistance was initiated to cope with Indonesian budgetary shortage caused by high
inflation which took place during 1962-67 Five Brantas projects committed in 1970
and one Brantas project committed in 1973 benefited by this scheme After more than
10 years of absence, the local cost financing loan assistance was revived once again
In 1986, 87 and 88, the Government of Indonesia suffered an acute shortage of local
currency funds due to the sharp drop in oil prices and the subsequent decrease of
budgetary revenue To assist the government during this short fall in revenues, JBIC
revived the local cost financing loan scheme to assist the then on-going JBIC projects
Seven Brantas projects were benefited by this scheme Further, the same type of loans
for IBRD- and ADB-assisted projects were separately extended to Indonesia in 1988
by JBIC
On reflection of the experience of the early 1970s, JBIC gradually developed another
local financing scheme which entailed a certain percentage of the local currency
Trang 36portion of each project cost to be assisted Towards the latter half of the 1980s, JBIC solidified its policy and internally established a “30% Financing Scheme” which implies that 30% of local currency component, in addition to full foreign currency component, of the project is entitled to be covered by a JBIC loan.
Taking the 30% policy further, in 1989 JBIC introduced a new scheme called the
“Pro-rated Local Cost Financing Scheme” This scheme determines the total amount
of JBIC loan by multiplying the total project cost by a certain percentage (presumably larger than 70%), without determining which procurement component is to be financed
as a foreign or local currency portion As of March 1993, for instance, the upper limit
of the total loan amount was set at 85% of the total project cost or the total foreign exchange cost, whichever is larger
These innovative schemes were invented, to a large extent, to cope with the Indonesian budget difficulties which seriously hampered project implementation at times
(vi) Post-Evaluation and Post-Monitoring
As the last step in a project cycle (Project Identification, Preparation, Appraisal, L/
A Negotiation and Board Presentation, Implementation and Supervision, and Evaluation), JBIC post-evaluates and post-monitors all projects and judges how successful they are and extracts lessons learned for future projects The few dozen projects implemented in the Brantas Project are no exceptions Generally speaking, those individual projects were proved to have produced more or less satisfactory benefits and returns A bundle of projects implemented under each M/P were all reviewed carefully and all the lessons learned were integrated into the successive M/P based on the “One Plan” philosophy
Post-This integration of lessons of post-evaluation and post-monitoring was expected to offer solutions and precautions to various problems to be envisaged throughout the project cycle
(vii) Technical Assistance Schemes of JBIC JBIC created three kinds of T/A facilities on a grant basis, namely, SAPROF (Special Assistance for Project Formation), SAPI (Special Assistance for Project Implementation) and SAPS (Special Assistance for Project Sustainability) These facilities are implemented in up-stream, middle-stream and down-stream phases
of the project cycle, respectively JBIC employs consultants/experts, using its own budget fund, to carry out the T/As These 3-facilities are briefly described below
Trang 37(a) SAPROF
Adequate project preparation is an essential prerequisite for successful implementation
of any development project Even where a feasibility study has been completed, JBIC
sometimes learns that the results are not fully adequate as a basis for a decision
concerning JBIC financing The cause is often that the borrowing country/government
(Borrower) had difficulties in completing sufficient project preparation because of such
factors as time constraints and/or lack of the necessary resources
In 1988, JBIC introduced the SAPROF scheme to assist prospective Borrowers in
drawing up a complete implementation program for each project
(b) SAPI
While responsibility for project implementation rests with the Borrower, JBIC
keeps track of progress, through its own project supervision making appropriate
recommendations for attainment of smoother implementation of the project
JBIC monitors the overall schedule of the project, procedure required by the loan
agreement and disbursement of loan fund JBIC also pays attention to such matters
affecting the project as socio-cultural factors, the environment, institution-building
and technology transfer These are, in fact, sometimes too complex and diverse to deal
with completely at the stage of project implementation To deal with these complex
issues satisfactorily, JBIC introduced the SAPI scheme in 1992
SAPI studies and identifies problems which may hinder effective implementation of
a particular project and proposes remedial measures to solve those problems on an
as-needed basis
(c) SAPS
Operation, maintenance and management (OMM) have a crucial role to play in
achieving the objectives of a development project, once physical implementation has
been completed The primary role of JBIC is to make loan funds available, while OMM
are primarily the Borrower’s responsibility Nevertheless, to the extent permitted,
JBIC endeavors to keep track of project performance after completion in order to
ascertain whether the project actually attains the targets, as JBIC feels a continuing
interest in the project as the development finance institution assisting it
In the course of such endeavors, JBIC sometimes finds that a project is showing
poor performance In such a case, JBIC has usually done what it could, if so requested,
in collaboration with the Borrower or Executing Agency, to help to solve the problems
facing the project As a vehicle for bringing such collaboration into being, JBIC
introduced in 1986 a scheme, called SAPS, specially designed for projects whose
physical implementation has been completed but have yet to yield the intended
benefits because of OMM problems
Trang 38While these three facilities were meant to supplement project preparation (i.e feasibility study), project implementation (i.e physical construction) and post-implementation performance (i.e benefits), respectively, the Brantas Project utilized 5 SAPSs in 1987, 1991, 2000 (2 cases) and 2001.
(4) Indonesian Government(i) Request for ODA Projects to Japan and CGIIndonesian Government made it a rule to prepare a Blue Book annually in which all the priority development projects were listed Based on the Blue Book, as discussed
in 2.2-(1)-(iii) above, the Government requested the international donor community to help implement the listed projects at CGI The major donors have been Japan, IBRD and ADB Each of these institutions traditionally shared approximately 1/3 of the total annual commitment The projects financed by Japan (JICA and JBIC) were all committed at CGI in one way or another Needless to say, the Brantas region projects were all included in the commitment statement at CGI
This modality of logistics was meant to save the time and labor to fill the annual resource gap for Indonesia At the same time, the Government of Indonesia could envision the picture of Japanese ODA for the following fiscal year in advance
(ii) Indonesian Budgetary System for Foreign-Assisted ProjectsThe Government of Indonesia has tried hard to secure and allocate a budget to foreign-assisted projects The Indonesian budget was composed of “Recurrent Budget” and “Development Budget” BAPPENAS was responsible for the development budget and the Ministry of Finance for the recurrent budget BAPPENAS, primarily
a planning ministry, thus, controlled both the development planning and the development budgeting Over the years, BAPPENAS in collaboration with the Ministry
of Finance and the line ministries developed the fiscal discipline, the allocation discipline and the operational discipline Under this system, the Government developed more systematic budgetary discipline to manage the “Development Budget” Those budgetary disciplines were consolidated over time thanks to disciplined foreign development assistance as well as relatively successful long-term economic growth
All in all, this budgetary system was introduced to secure efficient and effective budget appropriation for national development projects including the Brantas Project
(iii) Meetings and Workshops for Project Monitoring and Supervision as well as Disbursement and Procurement Promotion
As stated in 2.2-(3)-(iv), in 1988, the Government of Indonesia and JBIC agreed to hold, in the Master Agreement, the following six workshops and meetings on a regular
Trang 39basis: “Workshop on Procurement and Disbursement”, “Annual Action Program
Workshop”, “Weekly Issues Meeting between JBIC and BAPPENAS”, “Quarterly
Review Meeting between JBIC, BAPPENAS, Executing Agencies and Ministry of
Finance”, “Regular Progress Meeting between JBIC and the Executing Agency on
a Staff Basis”, and “Quarterly Review Meeting between JBIC and the Executing
Agency”
These meetings and workshops were programmed to avoid delays in procurement
and disbursement vis-à-vis prompt and timely project monitoring and supervision
(5) BAPPENAS
(i) Political Commitment vis-à-vis Priority Projects on the Blue Book
The Blue Book is the state of the art institution in the history of Indonesian
socio-economic development BAPPENAS was solely responsible for the national
development planning as well as development budgeting and, therefore, played a
most important role in preparing the Blue Book The Blue Book is a book which is
prepared annually and contains a list of priority candidate projects to be assisted
by foreign donors The Blue Book is compiled through a particular inter-ministerial
procedure First, the line ministries prepare a list of high priority projects and send
it to BAPPENAS BAPPENAS, then, scrutinizes all those projects and selects the
top priority projects from the national developmental point of view It is, therefore,
believed that the projects listed in the Blue Book themselves are proved to be a
reflection of the political commitment It is interesting to learn that in Indonesia
there are no foreign-assisted projects which were cancelled totally by the Indonesian
Government once the implementation started, which implies that the Blue Book is the
authoritative document
Thus, the Blue Book system equaled the efficient and effective selection procedure of
national priority development projects
(ii) Meetings and Workshops for Project Monitoring and Supervision as well as
Disbursement and Procurement Promotion
Similarly as discussed in 2.2-(3)-(iv), BAPPENAS as the representative and window
ministry of foreign aid projects in Indonesia took part in 4 higher level meetings
and workshops for project monitoring and supervision as well as disbursement and
procurement promotion; namely, “Workshop on Procurement and Disbursement”,
“Annual Action Program Workshop”, “Weekly Issues Meeting between JBIC and
BAPPENAS” and “Quarterly Review Meeting between JBIC, BAPPENAS, Executing
Agencies and Ministry of Finance”, and practiced a strong supervisory role over the
line ministries It is understood that the reason why BAPPENAS had such influential
Trang 40power on each project was that it had budgetary authority over national development planning and the projects therein
These meetings and workshops were held to avoid delays in procurement and disbursement vis-à-vis prompt and timely project monitoring and supervision
(6) Ministry of Public Works -Directorate General of Water Resources Development: DGWRD-
(i) Sectoral Development Planning Exercises by DGWRDOne of the DGWRD’s roles in water resources development is to formulate development plans in which policies, strategies and projects/programs are spelled out, and to provide infrastructure facilities for water resources development
The executing agencies of line ministries, regardless of their intention, seem to have consolidated a unique method of plan making over time They, instead of making the development plan from scratch, usually made the most use of various development studies such as master plans and sector plans, which were often supported by foreign assistance They then made it a rule to scrutinize those plans and select their own appropriate policies, strategies and projects/programs for REPELITAs and the Blue Book
(ii) Meetings and Workshops for Project Monitoring and Supervision as well as Disbursement and Procurement Promotion
Similarly as discussed in 2.2-(3)-(iv) and 2.2-(5)-(ii), DGWRD as the Executing Agency participated in all the related workshops and meetings often together with other stakeholders such as CIPTA KARYA, JBIC, BAPPENAS, and other Executing Agencies for the sake of project monitoring and supervision as well as disbursement and procurement promotion Out of 6 workshops and meetings listed in 2.2-(3)-(iv), DGWRD attended 5 except “Weekly Issues Meeting between JBIC and BAPPENAS”
(7) Brantas Office(i) The Brantas Office and Relationship between the Brantas Office and Individual Project Site Offices
During the first several years, the Brantas Project was managed under a few government bodies While water resources development projects were under control
of the Ministry of Public Works, the Karangkates Project belonged to PLN (State Electricity Corporation) and the Selorejo Project was under control of the East Java Provincial Irrigation Office In view that the Brantas Project was too complex to be governed and executed by various different government bodies, the Brantas River Basin Executing Office was newly established in 1965 as the unified executing office to