One-storey industrial building with 2 spans and 13 frames constructed by assembly methodfrom a range of different structure members including concrete columns, roof and wall panels,crane
Trang 1NATIONAL UNIVERSITY OF CIVIL ENGINEERING
DIVISION OF CONSTRUCTION TECHNOLOGY AND MANAGEMENT
CONSTRUCTION TECHNOLOGY II PROJECT
Requirement: Design assembly method for Industrial building using
Trang 2One-storey industrial building with 2 spans and 13 frames constructed by assembly methodfrom a range of different structure members including concrete columns, roof and wall panels,crane runway beams, concrete roof frames, and opening windows These components havealready been fabricated in factories, then delivered to construction site for installing.
Length of building: 12x6 = 72 (m), so there should be one settlement joint
Width of building: L = 2 x 18 = 36 (m)
1 Building cross-section:
BUILDING CROSS SECTION
Trang 3BUIDLING PLAN
2 Structure parameters:
Trang 7II SELECTING EQUIPMENTS:
1 Selecting hanging and tying equipments:
β - Inclined angle of cable and vertical direction, β=00
m - Ratio related to the difference in the value of tensile forcewithin the two branches of cable, m=1
n - Number of steel cable, n=2
Trang 8 Length of each steel cable: lbc= 1.5 + 3.3 = 4.8 (m)
β - Inclined angle of cable and vertical direction, β=00
m - Ratio related to the difference in the value of tensile forcewithin the two branches of cable, m=1
n - Number of steel cable, n=2
e
q = × × +γ l q = × × + =
SQct
Trang 91.2 Crane runway beam
Crane runway beam (CRB) is a structure member working in horizontal direction, so wechoose an ordinary equipment for hanging and tying with semi-automatic lock The way how
to hang and tie is shown in the following figure
where:
1- Steel cushion block2- Steel cable
3- Semi-automatic lock4- Pipe section for inserting cable
Crane runway beam (CRB) is a structure member working in horizontal direction, so wechoose an ordinary equipment for hanging and tying with semi-automatic lock
Tensile force of cable is determined by the below formula:
cosβ
ttP
β - Inclined angle of cable and vertical direction, β=450
m - Ratio related to the difference in the value of tensile force within thetwo branches of cable, m=1
Trang 10n - Number of steel cable, n=2
Frictional belt weight: qfb=30kg
qe = γ.l + qfb= 1.06 x 4.89 x 2 + 30 x 2= 70.84 kg = 0.071 T
1.3 Concrete roof panels:
Panels have 2 dimesions 3x6 (m) with the weigh of 2.3 T ,we use four steel cables with aself-balacing ring
Tensile force in each cable is calculated by:
cosβ
ttP
S k
m n × ×
= × 1.1 2.3 2.53 T
tt
m=0,75 (four cables-branches)n=4
β= 450 (for safety purpose, calculate with β=450)
Trang 11 Length of each steel cable: l= 6 (m)
qe= 0.59 x 6 x 4= 14.2 (kg) = 0,01 (T)
1.4 Concrete wall panels:
cables with a self-balacing ring
Tensile force in each cable is calculated by:
cosβ
ttP
S k
m n × ×
= × 1.1 2.3 2.53 T
tt
m=1n=2
reason, calculate with β=450)
Trang 12 Weight of equipment for lifting:
qe= 4.5 x 1.06 x 2= 9.54 (kg) = 0,01 (T)
1.5 Steel frame:
Because contructing these components at high place, steel roof frames need to be erected on the ground in order to ensure safety and then be hanged and installedsimultaneously Tools for hanging and tying are equipped semi-automatic lock and self-balancing ring
pre-The steel roof frames have long span, so hanging bar is used to assist the process oferecting Supported positions are chosen at joints of frames to avoid moment and shear forceappearing within frames
The steel roof frames have L=18m in length, we choose hanging bar with code
Ptt= 1,1.P= 1.1 x (5+1.2)= 6.82 (T)n= 2
m= 1β=30o
Trang 13Selecting cable 6x37x1 with diameter D=24 mm, tensile strength (140 kg/cm2), failureforce F= 24300 (kg)
Frictional belt weight: qfb=30 kg
qe= γ.l + qfb+ G= 1.99 x 5 x 2 + 30 x 2 + 455= 534.9 (kg) = 0.53 (T)
2 Lifting and installing data calculation:
Selecting crane tower base on the following parameters:
Hrq – height of hook
Lrq - length of working jib
Qrq - lifting capacity
Rrq - working radius
2.1 Calculating lifting & installing data of column
Assembling column without obstacles
=> working jib with αmax = 750
HL: height to install element HL = 0
a : distance from ground to height of lifting cable a = 0.5 m
hm : height of element hm = 13.3 m
he : length of lifting cable he = 1.5 m
hh : height of pulley, hook hh = 3.47 m
Trang 14H h
Working radius of jib :
S=Lmin×cos 75 17.8 cos 75 4.6(m)= × =
Minimum working radius of crane:
HL: height to install element HL = 0
a : distance from ground to height of lifting cable a = 0.5 m
hm : height of element hm = 13.3 m
he : length of lifting cable he = 3.47 m
hh : height of pulley, hook hh = 3.47 m
Jib length :
Trang 15H h
Working radius of jib :
S=Lmin×cos 75 17.8 cos 75 4.6(m)= × =
Minimum working radius of crane:
Rrq = S + r
→R rq =4.6 1.5 6.1+ = m
2.2 Calculating lifting & installing data of crane runway beam
Assembling of crane runway beam without obstacles
=> Select working jib follow : αmax = 750
Lifting capacity : Qrq = Ptt + qe = 3.63+ 0.07 = 3.7 T
Requirement height:
Hrq = HL + a + hm + he + hh
With :
HL: height to install element HL = 10 – 0.7 = 9.3 m
a : height of lifting element a = 0.5 m
Trang 16hm : height of element hm = 0.8 m
he : length of lifting cable he = 2.4 m
hh : height of pulley, hook hh = 1.5 m
Working radius of jib :
S = Lmin x cos750 = 13.45 x cos750 = 3.48 m
Minimum working radius of crane:
Rrq = S + r
→R rq =3.4 1.5 4.98( )+ = m
2.3 Calculating lifting & installing data of roof frame and opening window:
Assembling of crane runway beam without obstacles so we choose working jib as follow :
αmax = 750
Trang 17HL: height to install element HL = 13.3 – 0.7 = 12.6 m
a : height of lifting element a = 0.5 m
hm : height of element hm = 2.45 + 2.6 = 5.05 m
he : length of lifting cable he = 1 m
hh : height of pulley, hook hh = 1,5 m
Working radius of jib :
S = Lmin x cos750 = 19.93 x cos750 = 5.16 m
Minimum working radius of crane:
Rrq = S + r
→R rq =5.16 1.5 6.66( )+ = m
Trang 182.4 Calculating lifting & installing data of roof panel
Without fly jib H L = 17.75 m
HL: height to install element HL = 13,3 – 0.7 + 2.45 + 2.6 = 17.75 m
a : height of lifting element a = 0.5 m
hm : height of element hm = 0.4 m
he : length of lifting cable he = 6cos(45)=4.24 m
hh : height of pulley, hook hh = 1,5 m
With hc – level of the slewing ring of the crane (from the ground surface)
Trang 19w ar ch c' 75
t
H h ctg
Trang 20Working radius of jib :
0
19.03 1.5
cos 75 3 1 8.70( )sin 75
Minimum working radius of crane:
Rrq = S + r
→R rq =8.70 1.5 10.2( )+ = m
2.4 Calculating lifting & installing data of wall panel
Assembling of crane runway beam without obstacles
=> Select working jib follow : αmax = 750
Lifting capacity : Qrq = Ptt + qe = 2.53+ 0.01 = 2.54 TRequirement height:
Hrq = HL + a + hm + he + hh
With :
HL: height to install element HL = 13.3– 0.7 =12.6 m
a : height of lifting element a = 0.5 m
hm : height of element hm = 3 m
he : length of lifting cable he = 4.5cos(45)=3.18 m
Trang 21hh : height of pulley, hook hh = 1.5 m
Working radius of jib :
S = Lmin.cos750 = 19.96 x cos750 = 5.17 m
Minimum working radius of crane:
Required parameters Crane parameters
Qrq Rrq Hrq Lmin Type of crane Q R H
1 Column Middle 9.62 6.1 18.77 17.8
MKG-25BR/18.5m 9.7 7.5 21Side 8.63 6.1 18.77 17.8 8.7 8 20.5
2 Crane ruway beam 3.7 5 14.2 13.1
III CONSTRUCTION METHOD:
Determine crane position based on lifting parameters of crane and construction site
Rmax
1 Columns installation:
columns respectively.(self-weight of side and middle columns are 8.7 and 9.7 respectively
1.1 Crane position:
Trang 22For each axis A, B, or C, number of postions for crane to install columns is:
14 n= 5 positions
Mark column centers on foundation surface Prepare supporting equipment
Check columns’ dimensions, connection between columns and crane runway beams.Prepare aggregates for concrete mixing batches
Use 5 wedges and 4 cables to temporarily fix each column Adjust column’s level andposition
Clean the columns’ bottoms and fix them to the foundation with fast setting mortar
Fixing process includes 2 phases:
Trang 23- Phase 2 : After concrete mortar reaches 80% strength, remove wooden wedges and
fill the foundation socket with mortar
2 Crane runway beam installation:
2.1 Crane position:
Trang 24Crane MKG10 (L=18m);with Q=3.7T => Rmin=4m; Rmax=6m.
Each position can be used to install 2 Crane runway beams
=> There are 6 x 3=18 postions in total to install all crane runway beam for the building
2.2 Construction method:
Preparation :
Trang 25Check CRBs’ dimensions, connecting bolts.
Check the hanging system
Prepare connecting components such as bolts, welder, welding machine
Installation:
Hang and lift CRB up Use rope system to adjust CRB positions on column’s console.Use steel plate to adjust level of CRB (if necessary)
Use bolting and welding connections to fix the CRBs to the columns
3 Roof frame and opening window installation:
3.1 Crane positions:
Trang 26Crane MKG-25BR (L=28.5m) with Q=7.5T => Rmin=6m; Rmax=9m.
3.2 Construction method:
Preparation:
Only install the roof frame if the concrete connections of columns reach at least 70%strength
Locate roof frame position for precise errection
Use steel hanging equipment with 4 hooking points at nodes of the steel truss
Strengthen the stee truss before erecting
Prepare working platform for the workers
Trang 274 Roof panels installation:
Check and permanently fix the roof panels
Trang 285 Wall panels installation:
Direction: from lower to higher positions
Check and adjust before permanently fixing
Trang 29IV TECHNICAL PARAMETERS OF CONSTRUCTION:
1 Crane moving path:
Trang 302 Hiring time of crane:
Trang 31Machine quantity Labor
Machine Shift Man-day
1 Side-columns 28.00 3.92 47.32 4.00 1.00 12Middle columns 14.00 1.96 23.66 2.00 1.00 12
4 Wall panel 144.00 2.59 12.96 4.00 1.00 4