NATIONAL UNIVERSITY OF CIVIL ENGINEERINGPROJECT: CT2 APARTMENTPART IARCHITECTURE1.GENERAL21.1.Project information31.2.Architectural and used requirement.31.3.Climatic condition31.4.Hydrogeology42.ARCHITECTUAL BRIEF42.1.Solution for master planning and elevation42.2.Floor plan idea103.TECHNICAL AND INFRASTRUCTURE SOLUTION183.1.Ventilation solution.183.2.Lighting solution183.3.Traffic solution193.4.The solution of water supply193.4.1.Scope of works193.4.2.Design parameter193.4.3.Cold water supply system203.4.4.Hotwater supply system203.4.5.Drainage system213.4.6.Stormwater drainage system213.5.Electricity system.213.6.Fire protection system223.6.1.Tasks223.6.2.Solution of fire alarm system223.7.Information and security system:253.7.1.Telephone system25PART IISTRUCTURE1.SOLUTION IN STRUCTURE271.1.Solution for main structure271.2.Solution for floor271.3.Structure selection291.4.Solution for material291.4.1.Reinforced concrete302.SELECTION OF PREMILINARY DIMENSION OF ELEMENTS302.1.Preliminary dimensions of columns302.2.Preliminary dimensions of slab322.2.1.Slab of floor 15322.2.2.Slab of ground floor, attic and roof362.3.Preliminary dimensions of beams363.LOAD CASES383.1.Dead load383.1.1.Finish loads383.1.2.Dead load of wall423.2.Live loads433.3.Wind load454.CALCULATION INTERNAL FORCES OF FLAT SLABS484.1.Principles484.1.1.Internal forces484.1.2.Calculate the reinforcement494.1.3.Placing reinforcement in flat slab:504.2.Calculation for typical flat slab – 2st Floor514.2.1.Check deflection and punching condition514.2.2.Concrete Strip Design535.CALCULATION FRAME AXIS 4585.1.Calculation diagram585.2.Load combination585.3.Calculation method615.4.Internal forces combination625.5.Calculated beam reinforcement775.5.1.Principles775.5.2.Calculation of rebar of beam B15805.5.3.Calculation of shear reinforcementStirrup of Beam B15845.6.Calculation of reinforcement of columns855.6.1.Principle855.6.2.Calculation of column C4Basement896.FOUNDATION – AXIS 41016.1.Design document1016.1.1.Design document of building1016.1.2.Geologic document1016.1.3.Geologic section1036.2.Selection of foundation solution1036.2.1.Stamp pile1046.2.2.Bored pile1046.2.3.Method selection1046.3.Stamp pile foundation design1056.3.1.Preliminary dimension of pile1056.3.2.Loading capacity of piles determination1066.3.3.Determination of number and arrangement of piles1086.3.4.Design reinforcement for pile cap1166.3.5.Foundation beam system1176.3.6.General check of stamp pile foundation119PART IIICONSTRUCTION1.INTRODUCTION CONSTRUCTION CONDITION1261.1.Construction position1261.2.Geologic features1261.3.Building features1261.3.1.Architecture1261.3.2.Structure1261.3.3.Foundation1261.4.Construction condition1271.4.1.Material supply1271.4.2.Electricity and water supply1271.4.3.Transportation system1272.PREPARATION1282.1.Land clearance1282.2.Benchmarking, foundation layout.1283.CONSTRUCTION METHOD OF UNDERGROUND1293.1.General concept1293.2.Construction solution1293.3.Construction sequences.1293.3.1.Preparation for construction plan.1293.3.2.Locate benchmark of pile cap on plan.1293.3.3.Locate benchmark of pile on pile cap.1303.3.4.Preparation for piling work.1303.3.5.Pressing piles.1303.3.6.Testing the bearing capacity of piles.1313.4.Taking notes during piling1313.4.1.Site preparation:1313.4.2.Benchmarking and foundation layout on site:1313.4.3.In piling process:1313.4.4.Checking pile capacity1323.4.5.Construction problems1323.5.Safety on piling construction.1333.6.Calculation number of pile1333.7.Select piling generator1343.8.The sequence of pressing pile1383.9.The construction time of pressing piles1394.CONSTRUCTION METHOD OF SUPER STRUCTURE1404.1.Design formwork1404.1.1.Formwork and technical requests1404.1.2.Design formwork for column1474.1.3.Design formwork for beam1504.1.4.Design formwork for slab1565.GENERAL CONSTRUCTION METHOD1625.1.Columns construction1625.1.1.Surveying and positioning work1625.1.2.Reinforcing work1635.1.3.Installing column formwork1645.1.4.Concrete work1645.1.5.Uninstall formwork (removal)1655.2.Beams and slab construction1655.2.1.Installing formwork1655.2.2.Reinforcing work1665.2.3.Concrete work1675.2.4.Curing concrete1685.2.5.Uninstall formwork (removal)1695.2.6.Defects rectification1705.2.7.Staircase construction1705.3.Calculation work volume1715.3.1.Calculation of concrete volume1715.3.2.Choose construction machines1795.4.Construction method of finishing task1835.4.1.Brick up wall1835.4.2.Plastering1835.4.3.Gypsum wall1835.4.4.Screed concrete layer1845.4.5.Tiling1845.4.6.Waterproof layer1845.4.7.Electricity and water task1846.CONSTRUCTION SCHEDULE1857.CONSTRUCTION SITE LAYOUT1887.1.Define the quantity of materials needed for storage1887.2.Design temporary houses and temporary offices1897.3.Design water supply system1917.4.Power supply system1928.SAFETY IN CONSTRUCTION1948.1.Training, implement, examination of safety1948.2.Occupational safety in each stage of construction1948.3.Safety in working with equipment, machines on site1968.4.Environmental management197 PREFACEIn the career of building and protecting country, building and industrial construction are essential contributing important roles. Along with the national continuous development in the past years, fields of capital construction generally and civil engineering construction in particular have invested by Government and Party and had deservedly proud achievements. In the next years, in order to implement the career of modernization and industrialization, building and industrial construction must precede a step, serve purposes of socioeconomic development.In the recent years, the government is investing much in building and industrial construction; advanced constructing technologies are applied in Vietnam. To apply in fact, civil engineers level must be better and better. To satisfy demands of development, The National University of Civil Engineering (NUCE) is opening scope and raising quality of training.After learning and gathering knowledge in the National University of Civil Engineering (NUCE), now I designed a graduation project about the steel structure workshop. I am guided directly by Dr. Vu Anh Tuan in Department of timber and steel structure and Msc. Cao Tuan Anh in Division of Construction Technology and Management. I sincerely thank the lectures of the subject, especially Dr. Vu Anh Tuan and Msc. Cao Tuan Anh.Beside, I also thank to my family and friends who gived me lots of help during I did my project.I tried to do my project best with my knowledge, but it is not very good because of time and some other reasons. I hope advices, remarks and suggestions of teachers and all of you.Thank to you sincerely Ha Noi, June2016StudentNGUYEN XUAN TUNG PART IARCHITECTUREDrawing:•KT01 Elevation of the building.•KT02 Crosssection AA and BB of the building.•KT03 Ground and first floor plan.•KT04 3rd6th floor plan and roof plan. 1.GENERALIn the recent years, Vietnam’s economy has changed dramatically along with the rapid growth of the other countries in Asia. The reconstruction and construction of infrastructure is needed in the open door period. On the other hand, the demand of housing is very necessary to resolve land issues as well as changing the urban landscape to deserve with the stature of a large city.Ha Noi is the capital of Viet Nam. This capital has been center of political, economy, culture, education and entertainment of the country. Ha Noi capital with approximate 6.6 million in population. The land of the city is now depleted while the demand of land for business is increasing. Therefore, the construction of a highrise building that combines both commercial and leasing agencies is essential and appropriate to deal with those above issues. Because of these reasons, the “CT2 Apartment” is licensed to build. Figure I.1. Construction position 1.1.Project informationName of building:CT2 Apartment Building.Investor:Viet Han Group.Address:Tran Thu Do St Hoang Mai District Ha Noi.The North adjacent to N3 Phap VanTu Hiep ApartmentThe South adjacent to Carofi buildingThe West adjacent to residential areaThe East adjacent to Tran Thu Do StreetArea of site: 600m2Building construction area: 272m2Total floor area: 1904.36m2The building consists of 7 above stories, an attic with swimming pool, roof and a basement.Grade of building: Grade III according to TCVN.Types of building: Apartment.1.2.Architectural and used requirement.Used requirements: to ensure safety, indefectibility and demand of public. Layout reasonable apartments, to ensure sanitation, facilitate transportation and living.Architectural requirements: to aesthetic and consistend with the trend of social development. Consistend with the overall architecture of the building of new urban and local air. Take full advantage of ventilation and natural lighting, to ensure facilitate transportation, quick and safe escape and timely for people when the incident occurred.Design building include the basement to keep the car, the other floor layout household room, on the roof layout swimming pool and technical room.Building full layout transportation system in both horizontal and vertical to suited for traffic problems in the building.1.3.Climatic conditionThe building is located on Hoang Mai district, Ha Noi city. In which is typical for the northern climate, is characterized by tropical monsoon climate: hot summers and rainy, dry winters and less rain. Because of its location in the tropical monsoon climate to Hanoi to receive yearround solar radiation is abundant and high temperature. The amount of radiation a total annual average of Hanoi is 122,8kcalcm2 and the average air temperature annual is 23,6oC. Due to the influence of the sea, humidity, the average rainfall is quite large in Hanoi. The average relative humidity is 79% annually, the annual average rainfall is 1245mm per year and an average of 114 rainy days. From May to September is hot and rainy season (1682mm rainfall year), this time is often stormy, wind levels from level 8 to level 10 and sometimes up to level 12. From November to April next years later that is winter, dry weather. There have a transition period between the two seasons (April and October).Hanoi has 4 seasons: Spring, summer, fall, winter. There is sometime freezing temperatures down to the 2,70C (thang1 1955) and is the most intense heat with temperatures up to 42,80C in Hanoi (May 1926).The study area is dominated by the Hanoi climate is considered harsh with high moisture and high humidity, large amplitude, cool northeast monsoon. Beside, the last weather is good, the temperature and humidity in accordance with the average human comfort, cool southeast monsoon. The design architecture is exploited the advange and disadvanges of the weather.1.4.HydrogeologyBase on the Area Geological of Soviet Union (former) recorded at Hanoi Masterplaning Construction Institute, most studied area is located on the 2nd partition geology; is considered favorable level for construction. Structure from top to bottom is silty clay layer (thickness of 57 meters) plastic clay clay hard fightingplastic clay soft clay. A small section in the south lies on the third partition geology is not favorable assessment for construction. When implementing specific projects for geological exploration drilling in the study area to solution processing structure suitable foundation works.2.ARCHITECTUAL BRIEF2.1.Solution for master planning and elevationThe complex form is appartment with 7 floor in the center of project. The cover outer walls were painted and tiled to created special view for the project. Using architecture square columns with groove pattern, doors and windows glass door layout by arch steel frame combined with a balcony used to get light, ventilation and aesthetically created for the project. The combined idea with the medium height, the concrete segments and vintage ornamental pattern is used effectively not only the environment, but also healthy surroundings. The main idea illustrate that the living space is good orientation, environment and can view the scenery outside.The purpose of the project is to create an architecture simple and minimum to optimize the efficiency of land use and environmental conditions.The Serves Area of all the project is the space which combined with landscape garden, to create a master plan with high uniformity and harmony with landscape architecture.Vertical transportation included stair and elevatorProject is a high rise building. Its height is 26.4m with 7 floors, an attic and a roof with elevation: Ground floor elevation : 0.000m. 1st floor elevation: +3.2m. 2nd floor elevation: +6.40m. 3rd floor elevation: +9.60m. 4th floor elevation: +12.8m. 5th floor elevation: +16.0m. 6th floor elevation: +19.20m. Terrace elevation: +22.40m. Roof floor elevation: +24.90m. Figure I.2. Elevation AD Figure I.3. Elevation 15 Figure I.4. Section AA Figure I.5. Section BB 2.2.Floor plan ideaSolution condominium space research aimed at the average income, so the functional organization plan toward affordable investment, saving up energy use in buildings, then, competitive pricing in the marketing is better than neighboring buildings, the solution include:The aim is that the naturally ventilated and naturaly light is in all the rooms. The floor plan is created as the Ishaped, corridor is along between the blocks. There is 3 unit in each floor and 1 groups of lift, stairs is convenient transportation and safety fire protection in accordance with current building codes to each apartment.Entrance located between maximizing the size of the room with outside space.RoomAreaGenerator14.06m2 Water pump5.18m2Storage19.98m2Securiry8.51m2Elevator and stair14.28m2Parking area168m2 Because of the Vietnam climatic conditions and Vietnamses inhabition, the layout of the plan is very important, It affects in habit population in the appartment, so there is the studies spatial for the layout of apartments. It is hot in summer and cold in the winter cold, especially in the spring air humidity high and there are very few sunny days this season, so the bedroom is layout to ensure natural ventilation, the naturally ventilation is always the first concern. The most bedroom of unit is taken away, on alternating vertical combination is the logia which the aim of creating a microclimate environment, limiting the impact adverse climate for apartments. Living rooms are adjacent to the open space outside and connected to the kitchen area, directly to logia which create perfect unit. On the other hand, The investor in air conditioner is in the logia This is also where the heat of the air conditioning system, helping to form architectural aesthetic worth. Function of each floor: Basement: Basement area is used for parking area, security room, storage, electrical technical room, water pump... Total area 230m2Table I.1. Area of basement room Figure I.6. Basement plan Ground floor: included reception room, two apartment, a gymnasium and elevator area.Table I.2. Area of ground floor roomRoomAreaHall6.6m2 Reception27.8m2Gymnasium19.1m2Elevator and stair19.24m2Apartment N0181.7m2Apartment N0274.7m21st, 2nd, 3rd, 4th, 5th, 6th Floor: Included 3 apartment and elevator areaTable I.3. Area of typical floor roomRoomAreaElevator and stair19.24m2Apartment N1186.9m2Apartment N1274.7m2Apartment N1391.46Attic and Roof: Included swimmong pool, washing room, elevator technical room, water tank and terrace.Table I.4. Area of Attic roomRoomAreaElevator and stair19.24m2Swimming pool62.5m2Water tank46.6m2Washing room13.5m2 Figure I.7. Plan of ground
Trang 1NATIONAL UNIVERSITY OF CIVIL ENGINEERING PROJECT: CT2 APARTMENT
PART I-ARCHITECTURE
1 GENERAL 2
1.1 Project information 3
1.2 Architectural and used requirement 3
1.3 Climatic condition 3
1.4 Hydrogeology 4
2 ARCHITECTUAL BRIEF 4
2.1 Solution for master planning and elevation 4
2.2 Floor plan idea 10
3 TECHNICAL AND INFRASTRUCTURE SOLUTION 18
3.1 Ventilation solution 18
3.2 Lighting solution 18
3.3 Traffic solution 19
3.4 The solution of water supply 19
3.4.1 Scope of works 19
3.4.2 Design parameter 19
3.4.3 Cold water supply system 20
3.4.4 Hot-water supply system 20
3.4.5 Drainage system 21
3.4.6 Storm-water drainage system 21
3.5 Electricity system 21
3.6 Fire protection system 22
3.6.1 Tasks 22
3.6.2 Solution of fire alarm system 22
3.7 Information and security system: 25
3.7.1 Telephone system 25
PART II-STRUCTURE 1 SOLUTION IN STRUCTURE 27
1.1 Solution for main structure 27
1.2 Solution for floor 27
1.3 Structure selection 29
1.4 Solution for material 29
1.4.1 Reinforced concrete 30
2 SELECTION OF PREMILINARY DIMENSION OF ELEMENTS 30
2.1 Preliminary dimensions of columns 30
2.2 Preliminary dimensions of slab 32
2.2.1 Slab of floor 1-5 32
2.2.2 Slab of ground floor, attic and roof 36
2.3 Preliminary dimensions of beams 36
3 LOAD CASES 38
Trang 2NATIONAL UNIVERSITY OF CIVIL ENGINEERING PROJECT: CT2 APARTMENT
3.1 Dead load 38
3.1.1 Finish loads 38
3.1.2 Dead load of wall 42
3.2 Live loads 43
3.3 Wind load 45
4 CALCULATION INTERNAL FORCES OF FLAT SLABS 48
4.1 Principles 48
4.1.1 Internal forces 48
4.1.2 Calculate the reinforcement 49
4.1.3 Placing reinforcement in flat slab: 50
4.2 Calculation for typical flat slab – 2st Floor 51
4.2.1 Check deflection and punching condition 51
4.2.2 Concrete Strip Design 53
5 CALCULATION FRAME AXIS 4 58
5.1 Calculation diagram 58
5.2 Load combination 58
5.3 Calculation method 61
5.4 Internal forces combination 62
5.5 Calculated beam reinforcement 77
5.5.1 Principles 77
5.5.2 Calculation of rebar of beam- B15 80
5.5.3 Calculation of shear reinforcement-Stirrup of Beam B15 84
5.6 Calculation of reinforcement of columns 85
5.6.1 Principle 85
5.6.2 Calculation of column C4-Basement 89
6 FOUNDATION – AXIS 4 101
6.1 Design document 101
6.1.1 Design document of building 101
6.1.2 Geologic document 101
6.1.3 Geologic section 103
6.2 Selection of foundation solution 103
6.2.1 Stamp pile 104
6.2.2 Bored pile 104
6.2.3 Method selection 104
6.3 Stamp pile foundation design 105
6.3.1 Preliminary dimension of pile 105
6.3.2 Loading capacity of piles determination 106
6.3.3 Determination of number and arrangement of piles 108
6.3.4 Design reinforcement for pile cap 116
6.3.5 Foundation beam system 117
6.3.6 General check of stamp pile foundation 119
PART III-CONSTRUCTION 1 INTRODUCTION CONSTRUCTION CONDITION 126
Trang 3NATIONAL UNIVERSITY OF CIVIL ENGINEERING PROJECT: CT2 APARTMENT
1.3.1 Architecture 126
1.3.2 Structure 126
1.3.3 Foundation 126
1.4 Construction condition 127
1.4.1 Material supply 127
1.4.2 Electricity and water supply 127
1.4.3 Transportation system 127
2 PREPARATION 128
2.1 Land clearance 128
2.2 Benchmarking, foundation layout 128
3 CONSTRUCTION METHOD OF UNDERGROUND 129
3.1 General concept 129
3.2 Construction solution 129
3.3 Construction sequences 129
3.3.1 Preparation for construction plan 129
3.3.2 Locate benchmark of pile cap on plan 129
3.3.3 Locate benchmark of pile on pile cap 130
3.3.4 Preparation for piling work 130
3.3.5 Pressing piles 130
3.3.6 Testing the bearing capacity of piles 131
3.4 Taking notes during piling 131
3.4.1 Site preparation: 131
3.4.2 Benchmarking and foundation layout on site: 131
3.4.3 In piling process: 131
3.4.4 Checking pile capacity 132
3.4.5 Construction problems 132
3.5 Safety on piling construction 133
3.6 Calculation number of pile 133
3.7 Select piling generator 134
3.8 The sequence of pressing pile 138
3.9 The construction time of pressing piles 139
4 CONSTRUCTION METHOD OF SUPER STRUCTURE 140
4.1 Design formwork 140
4.1.1 Formwork and technical requests 140
4.1.2 Design formwork for column 147
4.1.3 Design formwork for beam 150
4.1.4 Design formwork for slab 156
5 GENERAL CONSTRUCTION METHOD 162
5.1 Columns construction 162
5.1.1 Surveying and positioning work 162
5.1.2 Reinforcing work 163
5.1.3 Installing column formwork 164
5.1.4 Concrete work 164
5.1.5 Uninstall formwork (removal) 165
5.2 Beams and slab construction 165
5.2.1 Installing formwork 165
5.2.2 Reinforcing work 166
Trang 4NATIONAL UNIVERSITY OF CIVIL ENGINEERING PROJECT: CT2 APARTMENT
5.2.3 Concrete work 167
5.2.4 Curing concrete 168
5.2.5 Uninstall formwork (removal) 169
5.2.6 Defects rectification 170
5.2.7 Staircase construction 170
5.3 Calculation work volume 171
5.3.1 Calculation of concrete volume 171
5.3.2 Choose construction machines 179
5.4 Construction method of finishing task 183
5.4.1 Brick up wall 183
5.4.2 Plastering 183
5.4.3 Gypsum wall 183
5.4.4 Screed concrete layer 184
5.4.5 Tiling 184
5.4.6 Waterproof layer 184
5.4.7 Electricity and water task 184
6 CONSTRUCTION SCHEDULE 185
7 CONSTRUCTION SITE LAYOUT 188
7.1 Define the quantity of materials needed for storage 188
7.2 Design temporary houses and temporary offices 189
7.3 Design water supply system 191
7.4 Power supply system 192
8 SAFETY IN CONSTRUCTION 194
8.1 Training, implement, examination of safety 194
8.2 Occupational safety in each stage of construction 194
8.3 Safety in working with equipment, machines on site 196
8.4 Environmental management 197
Trang 5NATIONAL UNIVERSITY OF CIVIL ENGINEERING PROJECT: CT2 APARTMENT
PREFACE
In the career of building and protecting country, building and industrial construction are essential contributing important roles Along with the national continuous development in the past years, fields of capital construction generally and civil engineering construction
in particular have invested by Government and Party and had deservedly proud achievements In the next years, in order to implement the career of modernization and industrialization, building and industrial construction must precede a step, serve purposes of socio-economic development.
In the recent years, the government is investing much in building and industrial construction; advanced constructing technologies are applied in Vietnam To apply in fact, civil engineers level must be better and better To satisfy demands of development, The National University of Civil Engineering (NUCE) is opening scope and raising quality of training.
After learning and gathering knowledge in the National University of Civil Engineering (NUCE), now I designed a graduation project about the steel structure workshop I am
guided directly by Dr Vu Anh Tuan in Department of timber and steel structure and Msc Cao Tuan Anh in Division of Construction Technology and Management I sincerely thank the lectures of the subject, especially Dr Vu Anh Tuan and Msc Cao Tuan Anh.
Beside, I also thank to my family and friends who gived me lots of help during I did my project.
I tried to do my project best with my knowledge, but it is not very good because of time and some other reasons I hope advices, remarks and suggestions of teachers and all of you.
Thank to you sincerely
Ha Noi, June-2016
Student
NGUYEN XUAN TUNG
Trang 6NATIONAL UNIVERSITY OF CIVIL ENGINEERING PROJECT: CT2 APARTMENT
Trang 7PART I
ARCHITECTURE
Drawing:
KT-01- Elevation of the building
KT-02- Cross-section A-A and B-B of the building
KT-03- Ground and first floor plan
KT-04- 3rd-6th floor plan and roof plan
Trang 81 GENERAL
In the recent years, Vietnam’s economy has changed dramatically along with the rapidgrowth of the other countries in Asia The reconstruction and construction ofinfrastructure is needed in the open door period On the other hand, the demand ofhousing is very necessary to resolve land issues as well as changing the urban landscape
to deserve with the stature of a large city
Ha Noi is the capital of Viet Nam This capital has been center of political, economy,culture, education and entertainment of the country Ha Noi capital with approximate 6.6million in population The land of the city is now depleted while the demand of land forbusiness is increasing Therefore, the construction of a high-rise building that combinesboth commercial and leasing agencies is essential and appropriate to deal with thoseabove issues Because of these reasons, the “CT2 Apartment” is licensed to build
Figure I.1 Construction position-
Trang 91.1 Project information
Investor: Viet Han Group.
Address: Tran Thu Do St - Hoang Mai District - Ha Noi.
The North adjacent to N3 Phap Van-Tu Hiep Apartment
The South adjacent to Carofi building
The West adjacent to residential area
The East adjacent to Tran Thu Do Street
Area of site: 600m2
Building construction area: 272m2
Total floor area: 1904.36m2
The building consists of 7 above stories, an attic with swimming pool, roof and abasement
Grade of building: Grade III according to TCVN
Types of building: Apartment
1.1 Architectural and used requirement.
Used requirements: to ensure safety, indefectibility and demand of public Layoutreasonable apartments, to ensure sanitation, facilitate transportation and living
Architectural requirements: to aesthetic and consistend with the trend of socialdevelopment Consistend with the overall architecture of the building of new urban andlocal air Take full advantage of ventilation and natural lighting, to ensure facilitatetransportation, quick and safe escape and timely for people when the incident occurred.Design building include the basement to keep the car, the other floor layout householdroom, on the roof layout swimming pool and technical room
Building full layout transportation system in both horizontal and vertical to suited fortraffic problems in the building
1.1 Climatic condition
The building is located on Hoang Mai district, Ha Noi city In which is typical for thenorthern climate, is characterized by tropical monsoon climate: hot summers and rainy,dry winters and less rain Because of its location in the tropical monsoon climate toHanoi to receive year-round solar radiation is abundant and high temperature Theamount of radiation a total annual average of Hanoi is 122,8kcal/cm2 and the average airtemperature annual is 23,6oC Due to the influence of the sea, humidity, the average
Trang 10rainfall is quite large in Hanoi The average relative humidity is 79% annually, the annualaverage rainfall is 1245mm per year and an average of 114 rainy days From May toSeptember is hot and rainy season (1682mm rainfall / year), this time is often stormy,wind levels from level 8 to level 10 and sometimes up to level 12 From November toApril - next years later that is winter, dry weather There have a transition period betweenthe two seasons (April and October).
Hanoi has 4 seasons: Spring, summer, fall, winter There is sometime freezingtemperatures down to the 2,70C (thang1 1955) and is the most intense heat withtemperatures up to 42,80C in Hanoi (May 1926)
The study area is dominated by the Hanoi climate - is considered harsh with highmoisture and high humidity, large amplitude, cool northeast monsoon Beside, the lastweather is good, the temperature and humidity in accordance with the average humancomfort, cool southeast monsoon The design architecture is exploited the advange anddisadvanges of the weather
1.1 Hydrogeology
Base on the Area Geological of Soviet Union (former) recorded at Hanoi Masterplaning
& Construction Institute, most studied area is located on the 2nd partition geology; isconsidered favorable level for construction Structure from top to bottom is silty claylayer (thickness of 5-7 meters) - plastic clay - clay hard - fighting-plastic clay soft clay Asmall section in the south lies on the third partition geology is not favorable assessmentfor construction When implementing specific projects for geological exploration drilling
in the study area to solution processing structure suitable foundation works
1.1 Solution for master planning and elevation
The complex form is appartment with 7 floor in the center of project The cover outerwalls were painted and tiled to created special view for the project Using architecturesquare columns with groove pattern, doors and windows glass door layout by arch steelframe combined with a balcony used to get light, ventilation and aesthetically created forthe project The combined idea with the medium height, the concrete segments andvintage ornamental pattern is used effectively not only the environment, but also healthysurroundings The main idea illustrate that the living space is good orientation,environment and can view the scenery outside
The purpose of the project is to create an architecture 'simple' and 'minimum' to optimizethe efficiency of land use and environmental conditions
The Serves Area of all the project is the space which combined with landscape garden, tocreate a master plan with high uniformity and harmony with landscape architecture
Trang 11Project is a high rise building Its height is 26.4m with 7 floors, an attic and a roof withelevation:
- Ground floor elevation : 0.000m
- Roof floor elevation: +24.90m
Trang 12BUILDING CT2 ALUMINUM GLASS WINDOWS
ALUMINUM GLASS WINDOWS
ALUMINUM GLASS WINDOWS
ALUMINUM GLASS WINDOWS
EMULSION PAINT FRIEZE
CARVED CONCRETE ROOF
+22400 +24900 +26400
Trang 13EMULSION PAINT FRIEZE
JOINT OF GRANITE STONE 10X10
SPLIT STONE WALLING
EMULSION PAINT
FRIEZE
-1600
±0,000 +3200 +6400 +9600 +12800 +16000 +19200 +22400
+24900 +26400
5 4
3 2
1
Figure I.3 Elevation 1-5
Trang 145 4
3 2
1
-1600
±0,000 +3200 +6400 +9600 +12800 +16000 +19200 +22400
+24900 +26400
F1 F2
F4 F4 F4 F4 F4 F4 F7
F7 F8
F5
F5 F5 F5 F5 F5 F5
Figure I.4 Section A-A
Trang 15A B C D
-1600
±0,000 +3200 +6400 +9600 +12800 +16000 +19200 +22400
+24900 +26400
ROLLER DOORS F1
F2 F4 F4 F4 F4 F4 F4 F7
F7
F8 F8
Figure I.5 Section B-B
Trang 161.1 Floor plan idea
Solution condominium space research aimed at the average income, so the functionalorganization plan toward affordable investment, saving up energy use in buildings, then,competitive pricing in the marketing is better than neighboring buildings, the solutioninclude:
The aim is that the naturally ventilated and naturaly light is in all the rooms The floorplan is created as the I-shaped, corridor is along between the blocks There is 3 unit ineach floor and 1 groups of lift, stairs is convenient transportation and safety fireprotection in accordance with current building codes to each apartment
Entrance located between maximizing the size of the room with outside space
Because of the Vietnam climatic conditions and Vietnamses inhabition, the layout of theplan is very important, It affects in habit population in the appartment, so there is thestudies spatial for the layout of apartments It is hot in summer and cold in the wintercold, especially in the spring air humidity high and there are very few sunny days thisseason, so the bedroom is layout to ensure natural ventilation, the naturally ventilation isalways the first concern The most bedroom of unit is taken away, on alternating verticalcombination is the logia which the aim of creating a microclimate environment, limitingthe impact adverse climate for apartments Living rooms are adjacent to the open spaceoutside and connected to the kitchen area, directly to logia which create perfect unit Onthe other hand, The investor in air conditioner is in the logia This is also where the heat
of the air conditioning system, helping to form architectural aesthetic worth
Function of each floor:
Basement:
Basement area is used for parking area, security room, storage, electrical technical room,water pump Total area 230m2
Table I.1 Area of basement room
Trang 17Ground floor: included reception room, two apartment, a gymnasium and elevator area.
Table I.2 Area of ground floor room
Table I.3 Area of typical floor room
Attic and Roof: Included swimmong pool, washing room, elevator technical room,
water tank and terrace
Table I.4 Area of Attic room
Trang 18BEDROOM
WC
SHOE CABINET
KITCHEN WC WC
WC
SHOE CABINET STORAGE
GYMNASIUM
RECEPTION ROOM
HALL B
Trang 19Figure I.8 Plan of 1st floor
BEDROOM
BEDROOM
BEDROOM BEDROOM
BEDROOM
BEDROOM
ELECTRICITY BOX FIRE HYDRANT
BEDROOM
BEDROOM
WC
WC WC
WC
WC WC
SHOE CABINET
SHOE CABINET
KITCHEN
B B
Trang 20BEDROOM
BEDROOM
BEDROOM BEDROOM
BEDROOM
BEDROOM
BEDROOM
SHOE CABINET
SHOE CABINET
SHOE CABINET
ELECTRICITY BOX FIRE HYDRANT
B B
WC
WC
WC WC
Trang 21Figure I.10 Attic plan
1026 2774
1026 2774
713 556
Trang 22TECHNICAL ROOM
+22400 +24900
SWIMMING POOL
Trang 23Internal wall is brick wall 110mm combining with partition inside building.
External wall is brick wall 220mm
Gypsum suspended ceiling is used with aluminum frame on each floor
Overall, the layout must ensure ventilation and natural light
Based on the using feature and requirements of sanitation, ventilation for each area, thehigh of each floor is selected as the following:
Central air condition is arranged on the technical floor
Combining both natural light and artificial lighting
Indoor lighting systems are designed by lighting standards (TCXD 16: 1986)
Trang 24Lighting in the apartment, halls use fluorescent lamps; lighting in hallways, lobby use150mm down-light lamps or compact bulbs; lighting in other areas such as stairs,garages, warehouses, the WC… mainly used incandescent bulbs, ensuring minimumilluminance in the region
The exit light (EXIT) are located in all the aisles and main entrance of the house such asthe lobby, stairs, corridors and some other public areas
Lamps of the stairs escape are controlled centralized power in the cabinet room
Electric lighting system is protected by a system of Circuit Breaker installation inelectrical controller, lighting control switches mounted on the wall next to the door orwalkway, in the most favorable position
1.1 Traffic solution
According to vertical direction: including 2 core systems in the center 2.4mx2.4m with 2elevators to serve internal traffic, transport goods The systems of elevator and staircaseare arranged at the center of the building Hence it is convenient when moving andexiting when happening fire
According horizontal direction: corridors are designed from the vertical traffic spot.Hence it is convenient to move around floors
1.1 The solution of water supply
1.1.1 Scope of works
The scope of the design of water supply system includes the following parts:
Cold water supply system including the connection point to the city water supplynetwork, water tanks, pumps, valves, piping of the whole project
Hot water design local for each apartment, include bathroom and kitchen
The drainage water after going through the septic tank will be discharged into the sewernetwork in the city
Vent pipe will connect with sanitary sewer drain grey, sanitary sewer drain black andsanitary equipment The septic tank have a vent pipe privite
The septic tank will be designed to treat all wastewater from the toilets, kitchen of thebuilding before escaping into the city sewer
Plumbing system includes:
- Drainage system
- Water supply system
- Storm-water drainage
Trang 25Velocity in vertical pipes and water main pipe supplying water from1.5 to 2m/s.
Velocity water flowing in the branch pipe water supply to2.5m/s
The minimum hydrostatic pressure of the water supply system is150kPa (1,5bar)
The maximum hydrostatic pressure of the water supply system is600kPa (6,0bar)
Criteria for water supply: 200 lít/person/day (for apartment)
Criteria for drainage: 100% Criteria for water supply
1.1.1 Cold water supply system
Water supply for domestic demand of condominiumis supply from the water supplysystem of urban Water supply underground tank pass float valve From undergroundtank use transport pump (1 activities, 1 preventive) have capacity Q= 13m3/h – H=45mforward domestic water tank on the roof floor after supply equipment use water ofcondominiums
Underground tank include water for fire fighting and for living and a tank on the rooffloor each tank Underground water tanks constructed of reinforced concreteunderground inside the building Rooftop water tanks using GRP tank assembly Thetank is divided into compartments for ease of washing
Water supply pipes using polypropylene (PP-R) pipes for cold and hot water supply.All the cold water pipe in the house (except water supply pipe from the pump to the tankroof) over pressure is 10bar
Hot water pipe and water supply pipe from the pump to the tank roof over pressure is20bar
All pipes come in ceiling, in wall or in technical boxs
Water supply section will be combined with the following items:
Install valves for sanitary equipment groups
Waterproof devices and pressure relief valves installed at the boundary points of thewater supply
Water supplying system: Water is supplies by water supplying system of the city andcontain in underground water tanks of the building Water follow is controled by gauges.After that, water is pumped by pumps system and contained in roof water tanks Water issupplied to restrooms of building by water pipe system from roof water tankautomatically Pipe system is hidden in floors, walls and technical boxes
1.1.1 Hot-water supply system
Hot water system will be designed for the toilet and kitchen of the apartment Waterheater types and capacities may be used for this project
Trang 261.1.1 Drainage system
Waster water from apartment will go to underground septic tank at basement And then,
it goes to general sewage system of urban via manhole After waster water will go tosewage treatment plant of area
Drainage toilet pipes and wash-water drainage pipes in the house are designed into twoseparate systems and vented to the roof
Horizontal draining pipes go on celling, on the floor, along with vertical draining pipes intechnical box leading to septic tank
Vertical pipe for equipment use uPVC have pressure is 6 bar
Main pipe for equipment use uPVC have pressure is 10 bar
This pipe is slope, toward vertical pipe Slope depends on diameter, general choosei=2%
1.1.1 Storm-water drainage system
The total rainfall for the entire area will be calculated rainfall intensity in Hanoi City is484.6 l/s/ha = 174 mm/h
Storm-water drainage pipes will be designed for the yard and the roof of the building.Rainwater from the roofs and balconies of apartments were collected in the rainwaterfunnel in vertical axis, to get out of the storm drain manholes outside the home
Arrange one system of storm-water drainage manholes and and reinforced concrete drainaround the building, collecting the entire storm-water and drainage water flowing into theexisting manholes of the area
Storm-water drainage of basement will be collected by trench system after get out thestorm drain system
1.1 Electricity system.
Electric system: 3 phase electric from local electric cabinet comes to electricalengineering room After that, electric is distributed to all rooms Moreover, there is agenerator to supply electric automatically for elevator and hallway when electric systemget incidents
Using power was delivered from power system of the city, building has transformer,beside there is a stand by generator in base floor
Lighting system ensures illumination from 20 - 40 lux Special is middle corridor that isneeded lighting all night and day for ensuring transportation All offices haveunderground power line and electric tablet Other rooms have more lighting requirementthat was installed high quality lighting equipment
There are some devices using electricity in the building:
Trang 27Kinds of ceiling fan, wall fan, ventilation fan
Air conditioner was arranged for all area that have requirement
Electric tablets, jack, switch were arranged in advantage area and safe for user, avoidfire risk in operation duration
Power feed solution
Information system and signal: hidden in the wall, including television cable, telephonecable and internet cable
All of building was needed arranging electric distribution chamber in advantage area forlaying electricity cable for equipment that using electricity in building That distributionchamber was arranged in technical room
From transformer that is outside building feed electricity for distribution chamber byunderground cable From distribution chamber to cubicle, charging device use electricitycable that were hidden in wall or slab
In distribution chamber, we arranged each cubicle for each floor of building, so managedand followed electricity using duration in building more easily
Distribution electricity from cubicle to flat by cable system that hidden in wall
In each room has electricity distribution tablet that was hidden in wall Electricity linefrom distribution chamber of flat to switch, jack and from switch to charging was reeve
in plastic tube that was hidden in wall
Arrangement a cubicle for priority device, charging such as: pump house, automaticrescue, elevators
Using automatic circuit – breaker for controlling and detecting each cable line, eacharea, in each room that used electricity
1.1 Fire protection system
1.1.1 Tasks
Automatic fire alarm system
Exit lighting system – emergency lighting
1.1.1 Solution of fire alarm system
1.1.1.1 Description of system
According to the nature, characteristics and capabilities of the intended use of thebuildings and departments Solution design of the system will be arranged regularthermal detectors and block types are connected through module address communication.Bells and lights will be connected through the communication module bells and lights.Requirements of fire alarm systems:
Fire alarm system must detect quickly and accurately the fired area
Trang 28Fire alarm in the floor is divided by area, and is shown in the centre of addressable firealarm.
Fire alarm system consists of parts: fire alarm cabinets, fire detectors (smoke and heat),emergency fire alarm buttons and fire alarm horn combined lights, signal wires andcontrol cables
1.1.1.1 Fire alarm cabinets
Fire alarm used for the building is the type of addressable fire alarm center In fact, thecontrol center is a processor received signals by the detectors, process and send the firealarm signals On the LED screen displays accurately the location of fire alarm and willgive the alarm notice, simultaneously display the necessary notice on the control screen
In addition, the center also functions to check the status of system activities such aspower supply, controller, fuses, line, memory…
Center operates continuosly by the power grid 220V-AC In addition, center cabinet isalso installed backup battery (dry battery type 24V-DC) When the power is interrupted,the center will be automatically transferred to work by backup power mode
Capacity battery backup must ensure continuous operation for at least 12 hours in normalmode and 1 hour if fire occurred
Fire Alarm Center is located in the technical room in 1st floor, wall mounted 1.5m fromthe floor
1.1.1.1 Fire detectors.
These types of fire detectors will be used:
For lobby and hallways Smoke firedetectorsFor technical room,
detectorsFor fire detection in different areas where the installation of automatic fire detectors(smoke and heat), the fire alarm automatically detects the signal characteristics of a fireand automatically transmits to the fire alarm center to handle
Use the fire alarm indicator lights when impacted
The detector are designed to ensure fire detection and functional specifications asstandard
1.1.1.1 Linking wire:
Trang 29Signal cable of fire alarm systems must be put in the wall, ceiling and to take measures
to protect against short wire or being broken (insert in a metal pipe or other protectpipes) If cable is installed on the wall, it must have measures to against rats or othermechanical causes damage the cable The trans-ceiling hole, wall after finishingconstruction must be cleaned and sealed with non-combustible materials
1.1.1.1 Emergency fire alarm button
The fire alarm button box with buttons that are protected by the glass will be installedalong all exits and allow alarm manually Everyone who discovered fire can activate thefire alarm by pressing the button in the fire alarm button box
1.1.1.1 Fire alarm bells and lights.
As the alarm when fire occurs due to fire alarm control signal Alarm bells combinedlights are located in areas where many people pass by in order to notify all personsresponsible for fire fighting
1.1.1.1 Exit lights and emergency lights
Arranged and equipped according to TCVN 3890:2009 as follows:
Power supply: Use common power supply of project, with backup power supplies toensure a minimum operating time of 2h
Emergency lights: Ensure minimum luminous intensity at any point along the exits notless than 1lux
Exit lights: The system ensures only way (traffic) during an incident
Equipment system: The entire equipment of systems used to meet TCVN or equivalent
1.1.1.1 Installation fire alarm devices
The installation of smoke alarms in place to design, make sure to install buildingcomponents meet the standard manufacturer's instructions This work is only done whenthe entire line system has been installed satisfactory inspection, the detector only whenthe system is mounted to the ceiling of the building has been completed
Before being put into installing these devices are effective test code quality, test theoperation of the equipment
After you've installed the equipment inspect the entire signal wiring system to the firealarm, fire alarm, fire alarm buttons and fire alarm central box
Install fire alarm center: conduct fire alarm test before being installed After installation
is complete we will operate the entire system, check the operation of each detector, eachbutton press, every fire alarm and the function of the fire
Calibration test equipment and systems
Complete the test in phases
Test Procedure according to manufacturer instructions
Trang 30Inspection procedures prescribed equipment suppliers and equipment.
1.1 Information and security system:
1.1.1 Telephone system
Phone system includes a direct phone line will be equipped for the building Thetelephone cable connection cabinets are installed at each floor Floor Wiring Closets will
be installed in the technical room floor at a height 1.8m above the finishing floor
The network consists of cable 30x2x0.5 signal lines will be equipped for the building.The fiber optic network connecting cabinets were installed at each floor Floor WiringClosets will be installed in the technical room floor at a height 1.8m above the finishingfloor Single cable will connect to Junction Box installed in the Apartment floor at aheight 1.8m above the finishing floor
All wire cable data & telephone & television will in p20 PVC
Trang 31PART II
STRUCTURE
Requirement:
Structure solution for building
Determine load cases
Calculation internal forces and internal forces combination
Designing frame axis 4 (typical slab, frame, foundation)
Drawing:
KC-01- Frame reinforcement from basement to 3rd floor
KC-02- Frame reinforcement from 4th to roof
KC-03- Slab reinforcement of typical floor
Trang 321 SOLUTION IN STRUCTURE
1.1 Solution for main structure
Basic bearing structure for building
Frame system
This system is created from vertical bars (columns) connecting with horizontal bars(beams), called “node” The plane frames are connected to each other in order to make aspace frame
In order to increase the horizontal rigidity of frame, braces are added at some span alongits height This component works as a horizontal rigid wall
Brace framing system
For high rise building, horizontal load is big so that the wall plates are designed to bearall horizontal and vertical loads The horizontal load is transferred to wall plates throughframe and slab system that is absolutely considered as rigidity in its plane Therefore,rigid frame has efficient lateral stiffness so that it can resist lateral loads together withshear walls
Advantages:
By using brace framing system we can remove the concentration of stress at column connection This system will have torsional rigidity if the walls are connected toeach other It also has great horizontal load bearing capacity, so that this system issuitable for building requiring partition space (house, hotel…)
beam-Disadvantages:
Using space is limited by walls so that it can located on elavators pit, staircase andboundary wall
1.1 Solution for floor
To building, slab system has big effect on the working of structure Select structure
Trang 33Not saving space.
Mass slab system with four ribs
Consist of vertical beam system which divides slabs to smaller slabs with 4 ribs
Advantages:
Decreasing the number of column inside the building Therefore, that saves using spaceand makes the architecture of building more beautifully The structure is suitable for thebuilding which is required the high level of aesthetic and big using space
Disadvantages:
Not saving, complicated construction
When the area of floor too large, we need to arrange more main beam Thus, thedisadvantage is big height of beam
Slab without beam:
Advantages:
The height of structure elements is small Thus, that decreasing the height of building.Saving using space
Easy to divide space
Easy to arrange water and electric technology system
Suitable for building which has medium
Construction of the method is faster than beam-slab method, because of not be takingtime by reinforcing formwork, reinforcing steel of beam
Because, the height of beams decreases, vertical transportation decreases and cost ofconstruction decreases
Horizontal load decreases, because of the height of building decreases
Trang 34The thickness of slab is big to ensuring the bending resistance ability and anti-punctureability Thus, the weight of slab is big.
Pre-stressed slab without beam.
Advantages:
Fix some disadvantages of “slab without beam” method:
Decreasing the thickness of slab and weight of slab Thus, decreasing the horizontal loadand vertical load
Increasing the stiffness of beam
Loading diagram become optimal
Disadvantages:
Designing and construction is complexity
Cost of equipment is high
1.1 Structure selection
The features that directly affect to structural solution of building:
The height of the typical storey is small, just 3.2 m It is needed to pay attention to slabsolution to ensure the clear height
Columns span is nomal (7.0 m in longitudinal and 4.0 m in horizontal) This building isused for living so more brick walls are installed
Lift system is located in the center of the building (in longitudinal direction) combinedwith stairs
Number of storey: 9 Height: 26.4 m
From those above analysis, the CT2 Building seems to be suitable with frame system
structure
With above features, frame and slab without beam is chosen for building structure
1.1 Solution for material
Choosing materials for bearing structure of high rise building must based on thefollowing basic standards:
Materials must have rate between strength and weight as much as possible
High deformability will overcome the low bearing capacity of materials or structure.Low decomposition: those materials are preferred to be used when the building issubjected by repeated load
High monolithism: When vibrating, building shouldn’t separate its components
Reasonable costs: Ahigh bearing capacity building is always connected to reasonable
Trang 351.1.1 Reinforced concrete
Advantages:
Nowadays, reinforced concrete is commonly used due to the development of science andtechnology This kind of structure is simply constructed and has common materials,stable to environment Furthermore, we can utilize the high compression of concrete andhigh tension of steel because of their cooperation For high rise building, reinforcedconcrete structure has high reliability about strength and stability
Disadvantages:
Reinforced concrete structure requires big size component, high self weight This causesthe complex choosing solution in structure It is difficult to fit reinforced concretestructure with architecture design
Therefore, based on the above analysis and supply capacity, construction schedule, localmaterials, the CT2 Tenement House (9 stories, 26.4 m high) is suitable with reinforcedconcrete:
Concrete B25: Rb = 145 kG/cm2, Rbt = 10.5 kG/cm2
Rebar type AI: Rs = 2250 kG/cm2 and AII: Rs = 2800 kG/cm2
1.1 Preliminary dimensions of columns
Columns are using concrete grade B25 with Rb=14.5 MPa and Rbt=1.05 MPa
The column dimension is calculated by:
b
kNAR
Legend: k =0.9-1.5-the factor taking into account the effect of bending moment,depending on design cases
Rb=14.5 MPa: Compressed strength of concrete
N m.S.q : Axial force caused by vertical loads, it can be determineapproximately
m- Number of floor transmit to columnS- Transmission area
q- Distributed load on 1m2 slab
Trang 36Si=8.4m 2 Si=17.0m 2 Si=17.0m 2 Si=8.4m 2
Trang 37Table II.1 Load bearing area of columns
P(daN)
Rb(Mpa)
Slab thickness was chosen by punching condition
Slab thickness without drop:
Where: l2, l1- Distance between two edge column in longitudinal and horizontal
q- Total loads include dead loads and live loads (kPa)
1
k 1 for middle slab =1,3 for boundary slab with boundary beam =1,6 for boundary slab without beam
Trang 39Table II.2 Slab thickness according punching condition
Check on punching conition:
Loads(kPa)
L1(m)
L2
hs(cm)
Choose(cm)
Boundary
slab
10
20
10,1
6,
10,1
Trang 40Figure II.2 Punching diagram