Alternatively, an AQL can be stated as the proportion of total units to be produced in a process that can be defective as preestablished by an appropriate maximum determined by zero-2..
Trang 1Special Production Issues: Lost Units and AccretionQuestions
1 An accepted quality level (AQL) is the proportion of total units
to be produced in a process without defects as preestablished by
an appropriate minimum that is determined by management
Alternatively, an AQL can be stated as the proportion of total units to be produced in a process that can be defective as
preestablished by an appropriate maximum determined by
zero-2 Shrinkage refers to loss of inputs because of natural processes
such as evaporation or oxidation Spoiled units cannot be
economically reworked to bring them up to standard Defective units can e economically reworked because the incremental revenueexceeds the incremental cost of the rework Both spoiled and defective units do not meet quality specifications upon
inspection
3 A tolerated loss level may be set because losses are inherent in
the production process (e.g., shrinkage) or there are known
defects in materials used or in production processes For
example, management may know that a particular production processperforms within tolerances only 99.5 percent of the time
Accordingly, management may allow for 5 defects out of every 1,000 units produced Although management could invest in
technology that would reduce the level of defects, the new
technology may be too costly relative to the existing level of defects With this cost/benefit analysis, management has
concluded that a certain level of defects is preferred to no defects
165
Trang 24 Examples of defective units include the following: a car that
has been painted the wrong color; the delivery of personal
possessions to the wrong address by a moving company; an
incorrectly mounted transmission in a new automobile; a piece of lumber that has been cut too long for its intended application; and a fishing reel that has been assembled without a required bearing
Examples of spoiled products/services include the following:
a tire that that has treads which are irregularly positioned on the tire (e.g., treads that would not be parallel to the road); atax return prepared by an accounting firm that was audited by theIRS and determined to have large errors; a cake that has been cutinto pieces that are too small; a tree that died because it was trimmed so severely by a landscaping service; loss of a patient’ssight caused by a surgeon’s error during an operation
5 Normal loss refers to an expected reduction in production
quantity based on the production technology and production
practices of the company Abnormal loss refers to a quantity of loss above the normal loss quantity Normal loss creates an expected cost of production so the cost of such a loss is
inventoriable; abnormal spoilage cost is not expected, and, thus,
it is not inventoriable
6 Abnormal losses would be more likely to be preventable than
normal losses because abnormal losses are less likely to be
caused by factors that are inherent in the materials or
production methods For example, a known amount of material loss(waste) is to be expected if lower quality materials are
utilized However, any loss beyond the expected amount would likely be caused by other factors that are subject to management control, e.g., production errors
7 A continuous loss is one that occurs (more or less) uniformly
throughout the production process A discrete loss is one
that occurs at a specific stage or in a specific production
process
8 A discrete loss occurs at a specific point in the production
process For accounting purposes, discrete loss is assumed tooccur immediately prior to inspection In reality, the loss could have occurred anywhere before the inspection point and, thus, the lost units should have had no additional conversion (and/or, possibly, materials) added to them It is impossible
to have continuous monitoring for losses in most production
processes, so conversion costs are incurred until inspection and assigned to all units that have passed the inspection
point (even though some units that have not reached the
inspection point could also be lost)
Trang 39 Any time a decline in the value of an asset occurs that is
unexpected, it is considered a loss of the period Abnormal losses are unplanned for and are in excess of normal losses Therefore, the cost associated with them should not be
considered a product cost and should not be allocated to good production The units themselves have no value and cannot be considered assets, so their costs are expired and belong on the income statement The cost is removed by debiting a loss account (such as "Loss from Abnormal Spoilage") and crediting Work in Process Inventory
10 The method of neglect requires no specific computations
regarding spoiled units; all costs are assigned to good units.The cost of spoiled units that have been found at an
inspection point will be assigned to all units that have
passed the inspection point Thus, the method of neglect
assigns spoilage costs by simply ignoring (neglecting) the spoiled units
The method of neglect is appropriate if loss is considered to be incurred continuously and is considered
normal
11 The method of neglect raises the cost per equivalent unit
because no costs are assigned to the spoiled units
Therefore, good units bear all costs, including the costs of producing the spoiled units
12 If spoilage is incurred for all (or most) jobs in a job order
costing system, the estimate of overhead used in setting the predetermined overhead rate should include an amount for the net cost of spoilage This will allow the cost of normal, general spoilage to be spread over all jobs produced If spoilage is related to a single job, the cost of that spoilageshould be assigned to the job that gave rise to it If any abnormal spoilage is incurred in a job order system, its cost should be assigned to the period as a loss
13 Accretion is an increase in the number of units or the volume
of a product that occurs through the addition of materials (e.g., water or other fluids) or through processing (e.g., heat causing expansion) Although the total cost of the
predecessor department is unaffected, the cost per unit
calculated by the predecessor department would decline in the successor department because of the increase in units
14 The cost per unit might have declined in the second department
because of an increase in the number of units caused by the addition of materials or the expansion of the units
transferred in If the company manufactures bread, the rising
of the dough would cause an increase in the volume of dough transferred in from the Mixing Department
Trang 415 If the defects are considered normal, the treatment of rework
costs depends on whether an actual or a normal cost system is
in effect If an actual cost system is used, the rework costswill be added to the component costs of the period and be allocated to all units completed In a normal cost system, the rework costs will have been estimated and included in the development of the overhead application rate; actual rework costs would be assigned to Manufacturing Overhead
If the defects are abnormal, the costs of production and rework costs for the defective units should be accumulated andassigned to a loss account
16 The important managerial concern is to control spoilage and
defective work rather than to account for it Measuring its cost is the first step in controlling spoilage/defects Usingthe method of neglect or otherwise spreading the cost of the lost units to good production minimizes the degree of control that can be exerted by management
17 Certain fluctuations occur in any production process
Statistical process controls can be used to determine if
fluctuations in a process are within normal and tolerable limits, or exceed tolerable limits In short, the SPC methodscan be used to determine whether a process is in control SPCcharts can also be used as indicators of the points at which the process is out of control and thus helps managers
understand why fluctuations occur in a process so that actionscan be taken to reduce such fluctuations
18 Each student will have a different answer No solution
Trang 520 a Annual cost of spoilage = 200 × 50 × $8.50 =
$85,000
Alfred would be able to save up to $85,000 per year
by purchasing the regulator The amount he would pay would be based on the expected life of the regulator and (in a discounted cash flow framework) on the cost of capital of the firm In addition to these factors, Alfred would want to consider how long the company intends to keep the machinery that currently prints the packing boxes, the costs of operating and installing the regulator, the costs of training personnel to operate it and the utility and maintenance costs for the machine (ifdifferent from those currently experienced)
be to purchase all of its boxes in a single transaction rather than in 12 different batches In such a case, thetotal spoilage cost incurred would only be $425 (50 boxes
× $8.50)
d The spoilage cost-per-box figures differ substantially because of the number of units produced in the batches In part (b), the batch costs of spoilage were spread over 550 good units; in part (c), the costs
of spoilage for each batch were spread over only 20 units
21 a 10,000 + 60,000 = 70,000 units
b 60,000 × 0.05 = 3,000 units
c Abnormal loss = Total units – (Completed Units + EI units
+ Normal loss) = 70,000 - (58,200 + 8,000 + 3,000) = 70,000 – 69,200 = 800 units
Trang 6d Units Material Conversion
Beginning inventory (10%) 10,000Units started 60,000Units to account for 70,000Transferred out 58,200 58,200 58,200Ending inventory (60%) 8,000 8,000 4,800Normal shrinkage 3,000
Abnormal shrinkage 800 800 800Units accounted for 70,000 67,000 63,800
22 a - d Units Material Conversion
Beginning inventory (20%; 30%) 8,000
Gallons to account for 188,000
Beginning inventory completed 8,000 6,400 5,600Gallons started and completed 174,600 174,600 174,600
Total gallons transferred 182,600
f Cost of abnormal spoilage is treated as a period cost
23 a Units Material Conversion
Beginning inventory 40,000
Pounds to account for 465,000
BI completed 40,000 0 6,000Started & completed 405,000 405,000 405,000Ending inventory 10,000 10,000 2,500Normal spoilage 2,000
Abnormal spoilage 8,000 8,000 5,600Units accounted for 465,000 423,000 419,100
b Ending inventory:
Material (10,000 × $2.40) $24,000 Conversion (2,500 × $4.70) 11,750
c Abnormal spoilage:
Material (8,000 × $2.40) $19,200 Conversion (5,600 × $4.70) 26,320 Total cost (treated as a loss) $45,520
Trang 724 a Normal spoilage allowed = 30,000 pounds × 8% = 2,400 pounds
Units Material ConversionBeginning inventory (30%) 9,000
Pounds to account for 39,000
Beginning inventory completed 9,000 0 6,300Pounds started and completed 22,500 22,500 22,500Total pounds completed 31,500
Ending inventory (20%) 5,400 5,400 1,080Normal spoilage 2,100 0 0Pounds accounted for (FIFO) 39,000 27,900 29,880
b Total Material ConversionBeginning inventory cost $ 6,200
Cost to complete (conversion: 6,300 × $0.30) 1,890
Total cost of beginning inventory $ 8,090
Started & completed (22,500 × $0.65) 14,625 $22,715Ending inventory:
25 a Normal spoilage = 20,000 ÷ 20 = 1,000 units
Units Material ConversionBeginning inventory 4,000
Units to account for 24,000
Beginning inv completed 4,000 4,000 4,000Started & completed 16,000 16,000 16,000Ending inventory 3,000 3,000 1,800Normal spoilage 1,000 1,000 1,000Units accounted for (WA) 24,000 24,000 22,800
b Total Material Conversion Beginning inventory $ 24,592 $ 12,252 $12,340 Current period 175,448 112,548 62,900 Total costs $200,040 $124,800 $75,240
Cost per EUP $8.50 $5.20 $3.30
Trang 8a & b Units Material Conversion
Beginning inventory 500,000 500,000 500,000 Pounds started and completed 10,900,000 10,900,000 10,900,000
2 The memo should discuss how evaporation would lead
to a loss of water content in the potato Such losses are very common in vegetable processing
Beginning inventory 750
Units to account for 18,000
Beginning inventory completed 750 750 750Units started and completed 14,250 14,250 14,250
Defective units 1,800 1,800 1,800Units accounted for 18,000 18,000 17,640
b Regular Pro- Rework Total Cost duction Cost + Cost = Cost ÷ EUP = per Unit
DM $126,000 $3,240 $129,240 18,000 $7.18Conv $41,013 $1,323 $42,336 17,640 $2.40
c The actual costs of reworking would be charged to manufacturing overhead and the overhead application rate(s)would include a charge for rework
Trang 9d Abnormal rework costs are accumulated and assigned to a
loss account
Regular Pro- Cost duction Cost EUP per Unit
DM $126,000 18,000 $7.00Conv $41,013 17,640 $2.325
28 a Appraisal; the food can be compared to the
customer’s order before delivery to the table
b Prevention; this error could be prevented by marking an
invoice “paid” at the time a check is issued
c Prevention; only actions taken prior to the breakage
would be effective in minimizing the loss
d Although neither method would be entirely effective,
prevention measures could be taken such as using technology that minimizes evaporation losses
e Prevention; all parts could be made such that only the
correct mates could be fastened together
f Appraisal; the error would be discovered by visual
inspection
Problems
29 a Total shrinkage = Total units to account for – Units
transferred – Ending inventory = (1,000 + 125,000) – 110,000 – 3,000 = 126,000 – 113,000 = 13,000
b Maximum normal shrinkage = 125,000 × 10% = 12,500 pounds
For accounting purposes, it is simply ignored, which means its costs will be spread over all good units produced
c Abnormal spoilage = 13,000 – 12,500 = 500 pounds Its costs will be treated as a loss of the period
d
Total Material Conversion
Beginning inventory 1,000
Started 125,000
To account for 126,000
Beginning inventory 1,000 1,000 1,000Started and completed 109,000 109,000 109,000Ending inventory 3,000 3,000 900Normal spoilage 12,500
Abnormal spoilage 500 500 500
Accounted for (WA) 126,000 113,500
Trang 10Material Conversion Total
Beginning WIP costs $ 1,020 $ 195 $ 1,215Current costs 118,155 33,225 151,380Total costs $119,175 $ 33,420 $152,595Divide by EUP 113,500 111,400
Cost per EUP $1.05 $0.30 $1.35
Cost Assignment
Transferred out (110,000 × $1.35) $148,500Ending inventory:
Material (3,000 × $1.05) $3,150 Conversion (900 × $0.30) 270 3,420Abnormal spoilage (500 × $1.35) 675 Total cost accounted for $152,595
e The easiest way to decrease shrinkage loss is to buy
higher quality material Higher quality ground beef would have a lower fat content and consequently would shrink less Although raw material prices would
increase, the cost of conversion per pound of finished product would likely decline because of the reduced loss
30 a Units completed = (BI + Started) – EI – Defects = (5,000
+ 70,000) – 6,000 – 400 = 75,000 – 6,400 = 68,600
b Maximum normal spoilage = 70,000 × 1% = 700 units
Beginning inventory 5,000
Started 70,000
To account for 75,000
Beginning inventory 5,000 5,000 5,000 5,000Started and completed 63,600 63,600 63,600 63,600Ending inventory 6,000 6,000 0 4,200Normal spoilage 400 400 0 380Abnormal spoilage 0 0 0 0
Accounted for (WA) 75,000 75,000 68,600 73,180
Material Boxes Conversion TotalBeginning WIP costs $ 21,900 $ 0 $ 7,680 $ 29,580Current costs 315,600 75,460 270,404 661,464Total costs $337,500 $75,460 $278,084 $691,044Divide by EUP 75,000 68,600 73,180
Cost per EUP $4.50 $1.10 $3.80 $9.40
Trang 11Good units completed (68,600 × $9.40) $644,840
Normal spoilage
Material (400 × $4.50) $1,800Conversion (380 × $3.80) 1,444 3,244Total cost of good units $648,084
Cost per unit = $648,084 ÷ 68,600 = $9.45 rounded
If there would have been no defective units, the cost would have been $9.40 because the method of neglect would not have been used
d Material (6,000 × $4.50) $27,000
Conversion (4,200 × $3.80) 15,960 Total cost of ending WIP $42,960
31 a
Matthew ToolsCost of Production Report
for AugustBeginning inventory 1,000Transferred in 50,800Units to account for 51,800Normal spoilage (650)Abnormal spoilage (350)Ending inventory (1,800)Transferred out 49,000 Units Trans In Material Labor OH
BI 1,000 1,000 1,000 1,000 1,000Units S & C 48,000 48,000 48,000 48,000 48,000Ending inventory 1,800 1,800 0 720 1,170Normal spoilage 650 650 0 650 650Abnormal spoilage 350 350 0 350 350Units accounted for 51,800 51,800 49,000 50,720 51,170 Total Trans In Material Labor OH
BI cost $ 7,355 $ 6,050 $ 0 $ 325 $ 980Current costs 235,557 149,350 12,250 23,767 50,190Total costs $242,912 $155,400 $12,250 $24,092 $51,170Divided by EUP 51,800 49,000 50,720 51,170Cost per EUP $4.725 $3 $0.25 $0.475 $1.00Cost Assignment
Transferred out
Good units (49,000 × $4.725) $231,525
Normal spoilage (650 × $4.475) 2,909 $234,434Ending inventory:
Trang 12b Loss on Abnormal Spoilage 1,566
Work in Process - Grinding 1,56632
Big Piney FurnitureCost of Production Report
for April 2003Beginning inventory 2,000
Beginning inv $ 32,312 $ 15,020 $ 2,130 $ 4,118 $ 11,044Current costs 310,714 137,080 13,800 46,270 113,564 Total $343,026 $152,100 $15,930 $50,388 $124,608Divide by EUP 16,900 13,500 14,820 14,160Cost per EUP $22.38 $9 $1.18 $3.40 $8.80Cost Assignment
Transferred out
Good units (13,300 × $22.38) $297,654
Normal spoilage (200 × $22.38) 4,476 $302,130 Ending inventory:
Transferred in (3,000 × $9) $ 27,000
Labor (1,200 × $3.40) 4,080
Overhead (600 × $8.80) 5,280 36,360 Abnormal spoilage
Transferred in (400 × $9) $ 3,600
Labor (120 × $3.40) 408
Overhead (60 × $8.80) 528 4,536
Finished Goods Inventory 302,130
WIP Inventory-Lamination 302,130Loss on Abnormal Spoilage 4,536
WIP Inventory-Lamination 4,536
Trang 13Big Piney FurnitureCost of Production Report
for April 2003Beginning inventory 2,000
Beginning inv $ 32,312
Current costs 310,714 $137,080 $13,800 $46,270 $113,564 Total $343,026
Divide by EUP 14,900 11,500 13,220 12,760Cost per EUP $22.80 $9.20 $1.20 $3.50 $8.90Cost Assignment
Transferred in (3,000 × $9.20) $ 27,600
Labor (1,200 × $3.50) 4,200
Overhead (600 × $8.90) 5,340 37,140 Abnormal spoilage
Transferred in (400 × $9.20) $ 3,680
Labor (120 × $3.50) 420
Overhead (60 × $8.90) 534 4,634
Finished Goods Inventory 301,252
WIP Inventory-Lamination 301,252Loss on Abnormal Spoilage 4,634
WIP Inventory-Lamination 4,634
Trang 1434 Maximum normal spoilage = 70,000 × 3% = 2,100 units
Ronald CompanyCost of Production Report
for May 2003 Units Material ConversionBeginning inventory 5,600
Total Material Conversion
Beg inventory cost $ 7,632 Current costs 106,168 $74,400 $31,768
Material (7,500 × $1) $7,500
Conversion (2,500 × $0.44) 1,100 8,600Abnormal spoilage
Material (400 × $1) $ 400
Conversion (400 × $0.44) 176 576