Since the discounted cash flows are negative until year 3 and become positive by Year 4, the project pays back sometime in the fourth year.. Despite its higher payback, Project A still m
Trang 1Solutions to Chapter 7 NPV and Other Investment Criteria
1 NPVA = –100 + 40 annuity factor(11%, 4 periods) = $24.10
NPVB = –100 + 50 annuity factor(11%, 3 periods) = $22.19
Both projects are worth pursuing
2 Choose the project with the higher NPV, project A
3 If r = 16%, then NPVA = $11.93 and NPVB = $12.29 Therefore, you should now choose project B
4 IRRA = Discount rate at which 40 annuity factor(r, 4 periods) = 100
IRRA = 21.86%
IRRB = 23.38%
5 No Even though project B has the higher IRR, its NPV is lower than that of project
A when the discount rate is lower (as in Problem 1) and higher when the discount rate is higher (as in Problem 3) This example shows that the project with the higher IRR is not necessarily better The IRR of each project is fixed, but as the
discount rate increases, project B becomes relatively more attractive compared to
project A This is because B’s cash flows come earlier, so their present values fall less rapidly when the discount rate increases
6 The profitability indexes are as follows:
Project A 24.10/100 = 2410
Project B 22.19/100 = 2219
In this case, with equal initial investments, both the profitability index and NPV
will give projects the same ranking This is an unusual case, however, since it is rare for initial investments to be equal
7 Project A has a payback period of 100/40 = 2.5 years Project B has a payback period of 2 years
8 Project A
Trang 2Year Cash Flow ($) Discounted Cash Flow($) @ 11 percent Cumulative DiscountedCash Flow ($)
Assuming uniform cash flows across time, the fractional year can now be
determined Since the discounted cash flows are negative until year 3 and become positive by Year 4, the project pays back sometime in the fourth year Note that out
of the total discounted cash flow of $26.36 in Year 4, the first $2.24 comes in by 2.24/26.36 = 0.084 year Therefore, the discounted payback period for Project A is 3.084 years
Project B
Year Cash Flow ($) Discounted Cash Flow
($) @ 11 percent
Cumulative DiscountedCash Flow ($)
The discounted payback for Project B is 2 years + 14.35/36.55 = 2.39 years
9 No Despite its higher payback, Project A still may be the preferred project, for example, when the discount rate is 11% (as in Problems 1 and 2) Just as in
problem 5, you should note that the payback period for each project is fixed, but that NPV changes as the discount rate changes The project with the shorter
payback period need not have the higher NPV
10 NPV = 3,000 + 800 annuity factor(10%, 6 years) = $484.21
At this discount rate, you should accept the project
You can solve for IRR by setting the PV of cash flows equal to 3,000 on your calculator and solving for the interest rate: PV = 3000; n = 6; FV = 0; PMT = 800; compute i The IRR is 15.34%, which is the highest discount rate before project NPV turns negative
Trang 311 Payback = 2500/600 = 4.167 years, which is less than the cutoff So the firm wouldaccept the project
12 NPV = 10,000 + + + + = $2,378.25
Profitability index = NPV/Investment = 2378
13 Project at 2 percent discount rate
Year Cash Flow ($) Discounted Cash Flow($) @ 2 percent Cumulative DiscountedCash Flow ($)
$739.20 in Year 4, the first $693.60 comes in by 693.60/739.20 = 0.94 year
Therefore, the discounted payback for the project is 3.94 years, and thus the projectshould be pursued
Project at 12 percent discount rate
Year Cash Flow ($) Discounted Cash Flow($) @ 12 percent Cumulative DiscountedCash Flow ($)
Since the discounted cash flows become positive by Year 6, the project pays back
in 5 years + 116/405.6 = 5.28 years Therefore, given the firm’s decision criteria of
a discounted payback of 5 years or less, the project should not be pursued
As illustrated by the two scenarios above, the firm’s decision will change as the discount rate changes As the discount rate increases, the discounted payback periodgets extended
Trang 414 NPV = 2.2 + 3 annuity factor(r, 15 years) 9/(1 + r)15
When r = 6%, NPV = 2.2 + 2.538 = $0.338 billion
When r = 16%, NPV = 2.2 + 1.576 = $0.624 billion
15 The IRR of project A is 25.69%, and that of B is 20.69% However, project B has the higher NPV and therefore is preferred The incremental cash flows of B over A are –20,000 at time 0 and +12,000 at times 1 and 2 The NPV of the incremental
cash flows is $827, which is positive and equal to the difference in project NPVs
16 NPV = 5000 + – = –$197.70
Because NPV is negative, you should reject the offer You should reject the offer despite the fact that IRR exceeds the discount rate This is a “borrowing type”
project with positive cash flows followed by negative cash flows A high IRR in
these cases is not attractive: You don’t want to borrow at a high interest rate
17 a r = 0 implies NPV = 6,750 + 4,500 + (-18,000) = $-6,750
r = 50% implies NPV = 6750 + + 2
5.1
000,18
500,7
12.1
500,8
= $-2,029.08which is negative So the project is not attractive
However, you can note that the IRR of the project is 37.03 % Since the IRR of the project is greater than the required rate of return of 12%, the project should be accepted using this rule On balance, we would use the NPV rule and reject the project
19 NPV9% = –20,000 + 4,000 annuity factor(9%, 8 periods)
= $2139.28NPV14% = –20,000 + 4,000 annuity factor(14%, 8 periods)
= –$1,444.54
Trang 5The IRR is 11.81% To confirm this on your calculator, set PV = ()20,000; PMT = 4000;
FV = 0; n = 8, and compute i The project will be rejected for any discount rate above thisrate
20 a The present value of the savings is 100/r
The NPV=0 when the cost of capital =10% The savings are supposed to last
forever Therefore, there is no finite discounted payback period when cost of
capital is 10%
Trang 621 a NPV of the two projects at various discount rates is tabulated below
NPVA = –20,000 + 8,000 annuity factor(r%, 3 years)
From the NPV profile, it can be seen that Project A is preferred over Project
B if the discount rate is above 4% At 4% and below, Project B has the higherNPV
b IRRA = 9.70% [PV = (–)20; PMT = 8; FV = 0; n = 3; compute i]
IRRB = 7.72% [PV = (–)20; PMT = 0; FV = 25; n = 3; compute i]
22 We know that the undiscounted project cash flows must sum to the initial
investment because payback equals project life Therefore, the discounted cash
flows are less than the initial investment, so NPV must be negative
23 NPV = 100 + + = –1.40
Because NPV is negative, you should reject the offer This is so despite the fact thatIRR exceeds the discount rate This is a “borrowing type” project with a positive cash flow followed by negative cash flows A high IRR in these cases is not
attractive: You don’t want to borrow at a high interest rate
Trang 7The payback period for Project A is 3 years.
Project A does not pay back on a discounted basis since cumulative
discounted cash flows remain negative until the end of Year 4
The payback period for Project B is 2 years
The discounted payback period for Project B is 2 years + 173.55/1502.63 = 2.12 years
The payback period for Project C is 3 years
The discounted payback period for Project C is 3 years + 1010.52/3415.07 = 3.3 years
b Only B satisfies the 2-year payback criterion
Trang 8c You would accept Project B
26 a Cash flow each year = $5,000 – $2,000 = $3,000
NPV = –10,000 + 3,000 annuity factor(8%, 5 years) = 1,978.13
NPV is positive so you should pursue the project
b The accounting change has no effect on project cash flows, and therefore no effect on NPV
27 a The present values of the project cash flows (net of the initial investments)
are:
NPVA = –2100 + + = $400
NPVB = –2100 + + = $300
The initial investment for each project is 2100
Profitability index (A) = 400/2100 = 0.1905
Profitability index (B) = 300/2100 = 0.1429
Trang 9b If you can choose only one project, choose A for its higher profitability index.
If you can take both projects, you should: Both have positive profitability
index
28 a The less–risky projects should have lower discount rates
b First, find the profitability index of each project
Then select projects with the highest profitability index until the $8 million budget
is exhausted Choose, therefore, projects E and C
c All the projects have positive NPV All will be chosen if there is no rationing
29 a NPVA = –18 + 10 annuity factor(10%, 3 periods) = $ 6.87
NPVB = –50 + 25 annuity factor(10%, 3 periods) = $12.17
Thus Project B has the higher NPV if the discount rate is 10%
b Project A has the higher profitability index
Invest Profitability IndexProject PV ment NPV (= NPV/Investment)
c A firm with a limited amount of funds available should choose Project A
since it has a higher profitability index of 0.38, i.e., a higher “bang for the
buck.”
For a firm with unlimited funds, the possibilities are:
i If the projects are independent projects, then the firm should choose
both projects
ii However, if the projects are mutually exclusive, then Project B should
be selected It has the higher NPV
Trang 11Discounted payback period is 2 years + 3729.09/5037.72 = 2.74 years.
Project II has the lower discounted payback period at 2.74 years, and thus it isthe best choice under this decision criterion
(3) NPV at 6% for: Project I = $3031.19
Project II = $6434.82Since Project II offers a higher NPV, it is the best choice under this decision criterion
(4) IRRI = 6.29%
IRRII = 19.04%
Project II has the higher IRR and is, therefore, the better choice
(5) Profitability Index (PI) =
i
Investment Initial
NPV
PI Project I = 0 012
000 , 250
19 031 , 3
PI Project II = 0 26
000 , 25
82 434 , 6
Project II offers the highest ratio of net present value to investment; therefore,
we would choose Project II
b Of the two projects, Project II is the better choice It has lower payback and discounted payback periods In addition, Project II has the higher NPV, IRR and profitability index
32 PV of Costs = 10,000 + 20,000 annuity factor(12%, 5 years)
= 10,000 + 72,096 = $82,096The equivalent annual cost is the payment with the same present value, $22,774.[n = 5, i = 12, FV = 0; PV = ()82,096; compute PMT]
Trang 1233 Buy: PV of Costs = 80,000 + 10,000 annuity factor(12%, 4 years) 20,000/(1.12)4
= 80,000 + 30,373 12,710 = $97,663The equivalent annual cost is the payment with the same present value, $32,154.[n = 4, i = 12, FV = 0; PV = ()97,663; compute PMT]
If you can lease instead for $30,000, then this is the less costly option
You also can compare the PV of the lease costs to the total PV of buying:
30,000 annuity factor(12%, 4 years) = $91,120
which is less than the PV of costs when buying the truck
34 a The following table shows the NPV profile of the project NPV is zero at an
interest rate between 7% and 8% and at an interest rate between 33% and
34% These are the two IRRs of the project You can use your calculator to confirm that the two IRR’s are, more precisely, 7.16% and 33.67%
Trang 13Discount rate NPV Discount rate NPV
At very high rates, the positive cash flows are discounted very heavily, resulting in a negative NPV For mid-range discount rates, the positive cash flows that occur in the middle of the project dominate and project NPV is positive
Trang 1435 a Econo-cool costs $300 and lasts for 5 years The annual rental fee with the
b Luxury Air is more cost effective It has the lower equivalent annual cost
c The real interest rate is now 1.21/1.10 – 1 = 10 = 10%
Redo (a) and (b) using a 10% discount rate Because energy costs would normally be expected to inflate along with all other costs, we should assume
that the real cost of electric bills is either $100 or $150, depending on the
model
Equiv annual real cost to own Econo-cool = $ 79.14
plus $150 (real operating cost) = 150.00
$229.14
Equiv annual real cost to own Luxury Air = $ 93.72
plus $100 (real operating cost) = 100.00
$193.72Luxury Air is still more cost effective
Trang 1537 The equivalent annual cost of the new machine is the 4-year annuity with present value equal to $20,000 This is $7005 This can be interpreted as the extra yearly charge that should be attributed to the purchase of the new machine spread over its life It does not yet pay to replace the equipment since the incremental cash flow provided by the new machine, $10,000 – $5000 = $5000, is less than the equivalentannual cost of the machine.
38 a The equivalent annual cost (EAC) of the new machine over its 10-year life is
found by solving
EAC annuity factor(5%, 10 years) = $20,000
EAC 7.7217 = $20,000
Therefore, EAC = $2590 Together with maintenance costs of $2000 per year,
the equivalent cost of owning and operating is $4590
The old machine costs $5000 a year to operate, and is already paid for (We assume it has no scrap value and therefore no opportunity cost.) The new machine is less costly You should replace
b If r = 10%, the equivalent annual cost of the new machine increases to $3255,
so the equivalent cost of owning and operating it is now $5255, which is higher than that of the old machine Do not replace
Your answer changes because the higher discount rate implies that the
opportunity cost of the money tied up in the forklift also is higher
Trang 1639 For the fourth quarter of 2007 business investment in Machinery and Equipment (M&E)increased by 3.4% to $123.7 billion For all of 2007, business investment in M&E rose
by 8.3%
For example, the capacity utilization rate for the fourth quarter of 2007 in the food industry was 79 %, paper was 86.6 % and machinery was 82.2 % The capacity
utilization rate can be an indicator of the likelihood of future capital spending If
the capacity utilization rate is close to 100 %, then it is highly likely that capital
spending will increase in order to further increase capacity The information was
compiled from ”The Daily”, Economic indicators, Summary tables published by
Statistics Canada This information is available through the Statistics Canada
website by using the following web link:
http://www.statcan.ca/english/dai-quo/econind.htm
40 a Present Value =
PV = = $100,000
NPV = –$80,000 + $100,000 = $20,000
b Recall that the IRR is the discount rate that makes NPV equal to zero:
– Investment + PV of cash flows when discounted at IRR = 0
the discount rate, it pays to wait: the value of the tree is increasing faster than the
discount rate When the tree is older and the growth rate is less than r, cutting
immediately is better, since the revenue from the tree can be invested to earn a rate
of r, which is better than the tree is providing
42 a Time Cash flow
0 5
1 30
2 28
The following graph shows a plot of NPV as a function of the discount rate
NPV = 0 when r equals (approximately) either 15.61% or 384% These are
the two IRRs
Trang 17b Discount rate NPV Develop?
EFFECTIVE ANNUAL COST
Ultra Fast = $55,707.49/PV factor =$55,707.49 /3.605 = $15,452.84Medium Fast= $68,808.13/PV factor =$68,808.13/3.037 = $22,656.61Recommendation – buy Ultra Fast which costs less
b) Effective Annual Cost without salvage value
Ultra Fast = 60,814.33/3.605 = $16,869.44
Medium Fast = 72,780.12/3.037 = $ 23,964.48
c) With salvage value:
Ultra Fast’s effective annual cost at the end of 4 years = $53,392.38/3.037 =
$17,580.63 This is lower than Medium Fast (EAC = $22,656.94) Hence, we should purchase Ultra Fast which will be replaced by Hyper 3MM in 4 years Without salvage value: