QUẢN LÝ TỔ CHỨC VÀ THỰC HIỆN DỰ ÁN XƯỞNG SẢN XUÂT TÀ VẸT BÊTÔNG DỰ ỨNG LỰC Chapter 1 General introduction about factory project for manufacturing concrete sleeper 4 Chap

Trang 1

QUẢN LÝ TỔ CHỨC VÀ THỰC HIỆN DỰ ÁN XƯỞNG SẢN XUÂT TÀ VẸT BÊ

TÔNG DỰ ỨNG LỰC

Chapter

1

General introduction about factory project for manufacturing concrete sleeper

4

Chapter

2

Management organization and implementation of projects each factory sleepers prestressed concrete

6

2.3 Monitor schedule, implementation cost, define variation 7

FOREWORD

Trang 2

project completed on time, within the approved budget and achieve technical requirements and quality of products and services by using the best method and condition

Project management includes 3 main phase: planing, implementation in which main contens is time management, cost and monitoring work packages in order to achieve the goal

- Planing: this phase is for building goal, identify works need to do, human resources need to implement the project and is process to indentify the action plan which should be shown in systematic diagrama

- Implementation: This is process to allocate resources includes: Budget, human, equipment and important is coordination and manangement schedule This phase defines time-line to implement each work and whole project (when started, when finished)

- Monitoring is process to check schedule of the project, analysis status, solve associated issues and report

Phases of project management builds a dynamic cycle from planning to implementation and monitoring and feedback following charts

Planing.

Monitoring

Implemationation

Goal identification Resouces analysis.

- Measure results.

- Compared to the target.

- Report.

- Solve the problem.

- Coordinate and schedule.

- Distribution of resources.

- To coordinate the effort.

- Encourage and motivate staff and employees.

-Cycle project management.

Trang 3

CHAPTER 1 INTRODUCTION TO PROJECT 1.1 Background of project

Following the plan of rail way transportation of Vietnam ti 2020 is to complete upgrading existing raiways to meet national and area standard Build a new line to make it into double lines and electrification line Hanoi-Vinh, Saigon- Nha Trang, continue to build new railways in order to create

a synchronous and moderm railways network

Currently all routes on Vietnam Railways are using wooden sleepers should

be recorded during use due to the impact of weather, climate, the wooden sleepers will be recorded each item should be replaced regularly Besides making use of wooden sleepers to write more and more scarce, so the need

to replace wooden sleepers with a material different from that survey research of Vietnam Railways has approved the construction of "The project workshop reinforced concrete sleepers tensioning rail for recording

"in the central region

Trang 4

1.2 Goal of the project

Investing in “ Building a factory to manufacture concrete strain using for point machine in railway” which is adapted to condition of Vietnam railways This is important and significant materially and spiritually to Vietnam railways:

- Live life of concrete sleeper is longer than wooden one so the time to repairing, replacement is longer

- Create condition to professionalize for manufaturing, pre-installation of sleeper at factory then transport to site to replace this can help to reduce time of block the railways

- Factory location is connected to railways and highway at Kimlien station

so it is flexible for transportation by railways and highway

- Utilize the existing land

- Attractive local, company labour so increase income for workers

- It is comfortable to supply for middle, southern and northern areas

- Apply newest technology into Vietnam railways

- Stablize activities of company, contribute stablization of company

- Manufacturing is an developing industry so investment into this project is very safe

1.3 Organization and human resource to implement the project

Construction project

manager

Construction project

manager Equipment installation project manager

Equipment installation project manager

Project Coordinator Coordinator Project

Trang 5

Model of project management

Plan for implementation, monitoring, analysis implementation process

of the project Execution of project is implemented via the head of

project manager Beside activities in project management and associated

logistic that Vietnam railways need to implement, implementation

process includes main steps:

Step 1: land clearance

Step 2: Designing

Step 3: Implementation plan

Step 4: Implementation periods, schedule

Step 5: Finishing implementation and bring the project into use

CHAPTER 2 MANAGEMENT ORGANIZATION AND IMPLEMENTATION THE

PROJECT 2.1 Planing for building manufacturing factory strain concrete sleeper

for in railways

Work description of project implementation the project

(week)

Human resource/ men

Trang 6

5 Construction 3,4 4 35

Schedule table of the project facility

- From the above planning table, time for project is 90 days (18 weeks)

- The project includes 6 work packages: plan and approve master plan,

investigate geographic, design , clarify and approve design, construction,

install equipments, finish

2.2 Implementation: Using resources to implement the project

Description allocation of human resource in project

Trang 7

Allocation human resources

- Assume there are 40 men in company

- Following Resources Graph in peak time needs 45 people, so missing 5

people

- Reallocate human resource: peak time happens in building wall and water

system Due to building wall is limited so water system is selected to adjust

for schedule from 2,25 weeks to 4 weeks, worker from 10 people will

reduce to 6 people and meet human resource of the company Following

table

2.3 Cheking schedule, implementation cost discover variations

Chose time for avaluation schedule is week 6

compeletion BCWP(6) ACWP(6)

90 days 31,300,000,000

750,000,00

Plan and approve

Trang 8

Design, clarify and

approve design 2 wks 100,000,000 50,000,000 25% 25,000,000 15,000,000

Evaluation:

Evaluate schedule: SV=BCWP(6) - BCWS(6) = ($25,000,000.00)

SV<0 project is delay

TV = SD-BCSP = 1

The project is delay 2 weeks

Cost variations: CV = BCWP - ACWP = $10,000,000.00

CV>0 Cost is under budget

SI= BCWP / BCWS = 0.97

SI<1 Work is delay behind schedule

CI = BCWP/ACWP = 1.01

CI>1 cost is under budget

2.4 Adjust schedule:

Original Adjustment Original reduction Reduction

Plan and approve

master plan

Investigate geographic 3 2 200,000,000 203,333,333 3,333,333

Design, clarify and

approve desgin

construction 4 4 12,500,000,000 12,500,000,000 1,218,750,000

Electric network 4 4 1,800,000,000 1,800,000,000 202,500,000

Trang 9

- Chose works which have small value to adjust

- The project schedule is reduced 3 weeks, total additional cost is

VND1,465,833,333

- Total cost after adjusting schedule is VND32,765,833,333

2.5 Evaluation project risk

Following the above table

Te: 15,17 Vcp: 1,53 Xích ma(S) : 1,236

* Probability X=13 week

Z=(X-Te)/S = -1,753

Refer to probability table is 95,99%

Probability of project schedule under 13 weeks is: 4,01%

Probability of project schedule from 13 to 15.17 weeks

* Probability X=17 week

- Z: 1,483%

Refer to probability table is 93,06%

Probability of project under 17 weeks is 93.06%

Probability of project from 15.17 to 17 weeks is

43.06%

Probability of project after 17 weeks is 6.94%

Project risks:

The budget of the project is mainly comes from mobilizing so if the project

Trang 10

Quantity of works is big with many packages which implemented at the same time so lead to constrain for management, coordination during implementation

Conclusion and comments

The project is in line with policy of government and support to industrialization and modernization in Railways Following goals for next year, Vietnam railway need to focus on industrial manufacturing system Investing in this project contributes in completion for the projects in repairing and replacement new railtracks

Suggested solution and comments for the project

Improve approve and design process

Be careful and accurate in costing of the project because it effects to all work packages during implementation phase

Building schedule also is very important phase and effects all phases of the project It effects directly to mobilizing budget, time and quality of implementation For this project, schedule

must be done by experience and professsionall engineers

Select experience contractors for implementation and designing, consultancy and supervisory in order to optimize time, cost and have good quality

Implement all phases of the project well

Always update information about economy, polictical which is related to the project to analysis and select investing options

References:

- Project management: Phd Phạm Thị Thu Ha