Being responsible as the team leader working on the first phase of the project, specifically “co-operate with local authorities for land clearance, compensation, land preparation Backfil

Trang 1

PLANNING IMPLEMENTATION PROJECT ACTIVITIES

Credibility of the Hanoi People's Committee, the Corporation MAGACO specified project to build new urban areas in a commune in Tu Liem District, Hanoi According

to project documents, the project was officially approved and will begin

implementation from January 15, 2013 and ends on December 31, 2020 The total project budget is 500 trillion The land is mobilized to build new urban areas are mainly agricultural land, residential housing mixed farm of 60 households will be

relocated

Approved project consists of seven work following major components:

1 Compensation, site clearance and leveling;

2 Preparation and the temporary buildings in new urban areas for implementing the project;

3 The basic construction of high-rise buildings, luxury villas, infrastructure such as kindergartens, supermarkets;

4 Construction of the power transmission system from the power station is available

in the district to the construction of new urban areas;

5 Installation of electrical systems, electrical equipment for the construction of new urban areas;

6 Installation of water supply, sanitary installation equipment for apartment buildings, luxury villas, preschool facilities, supermarkets;

7 Build and perfect the system of internal roads new urban areas

To implement the project, the Corporation MAGACO has established the Project Management of 30 staff, engineers have a lot of experience to the organization, leaders deploy the project

You are a member of the Management Board on the project Your tasks is to assist the Project Management Committee building program, detailed work plan for the work

Trang 2

undertaken under the assignment.

According to the list of class, if you are listed in odd numbers will perform the first task if you are listed in even number will perform the second task Provided that, you will be submitted to the program according to the prescribed schedule, the late

submission will be penalized

The first task: You are in charge of the team made the first component of the project,

namely, "in conjunction with local authorities carry out the clearance, compensation, leveling and standard be the ground for the construction work Time to complete this work is June 20, 2013 " You have to build an action plan to implement this

component based on WBS and Gantt chart tool has been learned

The second task: You are in charge of the project implementation team made four

components of the project is "to build power transmission system from the existing power station in the district on the feet of new urban projects Deadline for completion

of this activity is to hand over the project to the Management Board before June 15,

2015 " You are responsible for the detailed planning of activities to perform specific tasks based on WBS and Gantt chart has been learned

Being responsible as the team leader working on the first phase of the project, specifically “co-operate with local authorities for land clearance, compensation, land preparation (Backfilling) for construction with the deadline on June 20, 2013’’, my detailed action plan is as follows:

Part I: Primary operation of the first task of the project

 The main work of the first task of the project is land clearance, compensation and land preparation This task can be divided into two main activities as “Land clearance and compensation” and “Backfilling”

 Land clearance and compensation consits of 20 categories (detailed table 1)

Trang 3

 Backfilling consist of 09 categories

Diagam of primary operation of the first task of the project

Site inspection carried out in Tu Liem District where the project will be implemented states that land is mostly farming land with relatively terrain and no ponds or lakes over the area of 200 m2 However, 60 farmer households plotted in the area and need removing

New urban Zone Construction Project MAGACO corporation

New urban Zone Construction Project MAGACO corporation

Land Clearance and Compensation Backfilling

Planning &

PMU

Planning &

÷17

Item3

÷17

Item1 8

Item1 8

Item1 9

Item1 9

Item2 0 Item2 0

Trang 4

Part II: Implementation of Land Clearance and Compensation

A- Work of Land Clearance and Compensation

Table 1

Item Content of work Implementin

g time Implement Unit

Department & PMU

2 Establish the Council for Compensation – Rehabilitation &

4

 Prepare lcadastral for land clearance

+ Demacration of individual house hold

+ Prepare cadastral for each lance clerance

 Revise the cadastral map to suit the current condition and

the cadastral map of the land acquisition area

 Make the list of the land clearance with the following

details : number of the land on the map, name of the land owner, area of the land with same purpose of the land use

+ Publicly posted the list of house holds whose land is cleared in

the People ‘s Committee, towns and Commune house

17-28/01/2013

CCR&R, Planning and Finance Department of district level, Ward People’s Committee, Employer

5

+ Make and evaluate the overall plan for land acquistion through

CCR & R to get People’s Comitee of district leval ‘s approval

+ Make overall plan for compensation budget to get People ‘s

Committee of distric leval and CCR & R’ approval

29-13/02/2012

CCR&R, Planning and Finance Department of district level, Ward People’s Committee, Employer

6 + Make anouncement about land acquisition after the plan 14/02/2013 CCR&R, Planning and

Trang 5

+ Make anouncement to the land owner the reason for land

acquisition

+ Make announcement about the estimated compensation,

rehabilitaion support, new job creation, time for moving and

handover the land acquisition stated in the overall

Finance Department of district level, Ward People’s Committee, Investor

7

Organize meeting with local people to inform land recovery

decision, deliver declarations of lands, assets on land, population,

records of Land dimension Collect declarations of lands, assets

on land, population

15-18/02/2013

Working team, Ward People’s Committee and bodies under Ward.

8 Inspect current situations, make inspection minutes, clarify

declared details of assets, plants, vegetables of households. 19-21/02/2013

Working team, Ward People’s Committee and bodies under Ward

9 Publicly the result of ò the verification, validation ò the result 22/02/2013 Working team,

Investor

10

Make draft detailed plans for CCR & R of the house holds whose

have house of land acquired through evaluation of draft ò

compensation plan.

23-25/02/2013 Working team,

Investor

11

+ Publicly list and collect opinions on draft of detailed solution

for compensation, rehabilitation and resettlement at working

office of Ward People’s Committee.

+ Inspect solutions with complaints (if any).

26-28/02/2013 Working team,

Employer

12 Answer all complaints and queries of people (if any 01/03/2013

Working team, Ward People’s Committee, Investor

13 Complete, accept compensation solution after they have been

14

Department of Natural Resources and Environment advices the

District People’s Committee in land recovery decisions to land

users.

4-6/03/2013 CCR&R

15 Submit to District People’s Committee for decision on detailed 7-10/02/2013 CCR&R

Trang 6

and general solution for compensation, rehabilitation and

resettlement

16 Make decide on solution for compensation, rehabilitation and

Tu Liem Distrit People’s Committee

17

Publicly list detailed solution for compensation, rehabilitation

and resettlement approved by the District People’s Committee,

deliver approval decision and solution for compensation,

rehabilitation and resettlement to each household, inform the time

to receive funds of compensation, rehabilitation and resettlement,

time to get resettlement, time to handle area

14-19/03/2013 Working team, Ward

People’s Committee

18

+ Build payment plan for compensation, rehabilitation and

resettlement

+ Make payment plan for compensation, rehabilitation and

resettlement.

20-21/03/2013 Working team,

Investor

19 Handle area (after payment of compensation, rehabilitation and

resettlement or after handling resettlement houses and lands. 22-23/03/2013

CCR&R, Working team, Ward People’s Committee, Employer, People whose land is withdrawn

20

Enforce households that do not accept compensation for land

Working team, Ward People’s Committee, Investor, Police of Ward

Note:

Council for Compensation – Rehabilitation & Resettlement is reffered as CCR&R.

A- Gantt diagram for land clearance and compensation.

Trang 7

Details in gantt chart 1

Part III: Backfilling

1) Diagram of work implementation

Investor

Bidder representative

Site steering commitee

Dept of Planning Materials - Equipment Equipment

Dept of Planning Materials - Equipment Equipment

Dept of Technical Progress of Project

Dept of Technical Progress of Project

Dept of industrial safety

Dept of industrial safety

Work Executive

Team

Work Executive

Team

Geodesic Team

Geodesic Team

Water &

Electric Executive

Water &

Electric Executive

Plaster Team

Plaster Team

Site Cleaning Team

Site Cleaning Team

Trang 8

2) Analysis of work items:

Them main work is backfilling

Implementation time from 24/3/2013 to 20/6/2013

Bảng 2

Hạng

mục Nội dung công việc

Thời gian thực hiện

Thời gian thực hiện

Số ngày thực hiện

Người phụ trách

Head of Planning – Materials – Equipment Department

Head of Planning – Materials – Equipment Department

3 Remove organic soil, transport

Heads of Labour Safety and Project Technical – Progress Departments

Safety and Project Technical – Progress

Trang 9

5 Fill black sand, roll and

Heads of Labour Safety and Project Technical – Progress Departments

Heads of Labour Safety, Project Technical – Progress and Planning – Materials – Equipment Departments

1) GANTT diagram for Backfilling

2) Based on the above mentioned planning, we have got GANTT diagram (Table

of project’s progress) in gantt chart 2:

Phần IV: Dự toán kinh phí thực hiện

PROJECT COST ESTIMATE

Project : New Urban Zone Item : Land Clrearance, Compensation and Backfilling

Unit : VND

Value before

Value after

Trang 10

(1) (2) (3) (4) (5) (6) (7)

1

Cost for

preparing

investment

project and land

clearance solution 2 %*500 billion 10,000,000,000 1,00,000,000 11,000,000,000

2

Cost for

compensation of

land clearance 60*1.7billion 102,000,000,000 10,200,000,000

112,200,000,000

3

Cost for

implementing

project G1+G2+G3 318,337,000,000 31,833,700,000 350,170,700,000 Gxd

3.2 Water drainage G2 17,600,000,000 1,760,000,000 19,360,000,000

3.3

Cost for building

contemporary

houses G3 3,798,000,000 379,800,000 4,177,800,000

4 Cost for PM 2%*Gxd 6,366,740,000 636,674,000 7,003,414,000 GQLDA

5

Cost for

consultancy and

implement of the

project 13,698,041,110 1,784,253,505 19,626,788,558 GTV

5.1 Cost for design 2%*Gxd 6,366,740,000 636,674,000 7,003,414,000

5.2

Cost for inspecting

detailed drawings 0,15%*Gxd 477,505,500 47,750,550 525,256,050

5.3

Cost for inspecting

estimation 0,153%*Gxd 487,055,610 48,705,561 535,761,171

5.4

Cost for suprvising

the project 2%*Gxd 6,366,740,000 636,674,000 7,003,414,000

6.1

Cost for inspection

and approving

account 0,3%*Gxd 955,011,000 95,501,100 1,050,512,100

6.2 Cost for auditing 0,6%*Gxd 1,910,022,000 191,002,200 2,101,024,200

Trang 11

7 Provision cost 22,520,089,056 2,164,503,922 24,684,592,978

7.1

Provision cost for

additional works (1+2+3+4+5)*5% 22,520,089,056 2,164,503,922 23,809,543,147 GDP1

Remarks:

+ Fund for project (compensation, land clearance and backfilling) is calculated as 10% of

total fund for the whole project.

+ Estimated compensation to each household is 1.7 billion Vietnamese dong.

Phụ luc I:

Appendix I:

Legal basis for implementation of the project.

(Details of Item 1)

1 2003 Land Law

2 Decree No 197/2004/NĐ-CP dated 03/12/2004 of the Government on

compensation, rehabilitation and resettlement in the event of land recovery

by State

3 Decree No 84/2007/NĐ-Cp dated 25/5/2007 of the Government with

additional provisions on issuance of land use right certificates; on land

recovery; on exercise of land use right; on order and procedures for

Trang 12

compensation, assistance and resettlement when the State recovers land; and

on resolution of complaints about land

4 Decisions of Hanoi People’s Committee allowing MAGACO to implement

the project of new urban zone in Tu Liem District, Hanoi City

5 Decision No 62/2008/QĐ-UBND dated 31/12/2008 of Hanoi People’s

Committee issuing Regulations on prices of land types in Hanoi City in 2009

6 Notice No 14/TB-STC-QLCS dated 21/01/2009 of Hanoi Department of

Finance on announcing unit price as the basis for compensation, assistance

to vegetables, animals on lands of land clearance in Hanoi City

7 Decision No 40/2008/QĐ-UBND dated 22/10/2008 of Hanoi People’s

Committee issuing prices of building new houses, temporary houses, structures in Hanoi city

8 Maps of Hanoi City, Tu Liem District, map of project border.

9 Approved detailed map of the project.

10 Approval documents relating to the project.