WELL COMPLETION ACTIVITIESWell completion activities include: Conducting well test Setting production casing Running production tubing along with downhole equipments Installing s
Trang 1WELL COMPLETION and STIMULATION
Bài giảng được soạn bởi
Bộ môn Khoan – Khai thác Dầu khí Khoa Kỹ thuật Địa chất và Dầu khí Đại học Bách Khoa TP HCM
Trang 31 BASIC COMPLETION METHODS
Trang 4 Once the design well depth is
reached, the formation is tested
and evaluated
To complete the production well,
casing is installed and cemented,
and the drilling rig is dismantled
A service rig is brought in to
perforate the production casing
and run production tubing along
with downhole equipments
Production begins after surface
safety equipment installation
INTRODUCTION
30’’ CASING 20’’ CASING
13 3/8’’ CASING
7’’ LINER
RESERVOIR
SEA BED PLATFORM
Production casing (9 5/8)
Trang 5WHAT IS COMPLETION?
Well completion creates a
dependable pathway to the surface
for the hydrocarbons.
The term ‘completion’ describes
the assembly of downhole tubulars
and other safety equipments that is
required to enable the safe and
efficient production of oil or gas
from the well after it has been
drilled
Trang 6BASIC WELL COMPLETION TECHNOLOGY
Each drilled wellbore awaiting completion is unique Even nearby wells drilled to the same reservoir can have differencies in:
depths,
formation characteristics,
and hole sizes
A wide variety of equipment designs and procedures have been
developed to provide safe, efficient conduits from subsurface reservoirs to the surface in different situations
The ideal completion design
minimizes initial completion and operating costs,
Trang 7Natural Completions
Natural completions are those in which little or no stimulation is required for production Sandstone and carbonate systems with good permeability and mechanical stability are ideal for natural completions
TYPE OF COMPLETION
Trang 8TYPE OF COMPLETION
The design of a particular completion depends on:
1 The number and type of productive zones,
2 The expected pressures and flow rates,
3 The need to control sand production,
4 The need for artificial lift or stimulation the regulations
governing operations in the area.
Trang 9WELL COMPLETION ACTIVITIES
Well completion activities include:
Conducting well test
Setting production casing
Running production tubing along with
downhole equipments
Installing surface safety equipments
Starting production flow
Trang 10BASIC COMPLETION METHODS
Once we drill to the target and evaluate our well by
Mud analysis: density & viscosity
Well logging (electrical, ascoustic, nuclear, etc…)
Coring: at bottomhole or sidewall
Welltest: bottomhole pressure vs time -> reservoir properties Next decision is whether to complete or abandon it????
In the latter case:
set a cement plug or plugs in the hole,
possibly recover whatever casing can be removed,
and return the drill-site to its original condition
The more fortunate is one in which our well not only is productive, but
Trang 11The next step usually involves the running of the final string of casing - the production string
The manner in which this is done determines the basic completion
method and may follow one of several configurations: (interface between the wellbore & reservoir)
the openhole completion,
the liner completion,
the cased and perforated completion
• Without liner
• With linerBASIC COMPLETION METHODS
Trang 12 The openhole completion: the producing formation is not isolated by the casing, which extends only to the top of the producing interval.
The slotted liner completion: which is not cemented and not "tied back"
to the surface
BASIC COMPLETION METHODS
Trang 13 The cased and perforated completion
Without liner: cementing the production casing across the productive interval and then perforating the casing for production
With liner: a liner is cemented and perforated as a cased and perforated completion
BASIC COMPLETION METHODS
Trang 14 One of these configurations will be the basis for the completion design, which may incorporate:
one or multiple strings of tubing: single, dual, or triple, etc
and a variety of tubing components to facilitate production (production method): pumping, flowing, etc
from one or multiple zones: single or multiple zones
For our purposes, a cased and perforated well with a single tubing
string will serve to illustrate the typical completion procedure
BASIC COMPLETION METHODS
Trang 15Subsea production systems are wells
located on the sea floor, as opposed to
at the surface The safety equipments
are installed underwater on the seabed.
They enable early production from
deepwater, remote, and marginal fields.
Subsea production system offer a
means of producing field extremities not
reachable by directional drilling from
existing platforms, or where field
economics do not justify the installation
of one or more additional platforms.
SUBSEA COMPLETION
Trang 162 COMPLETION PROCEDURE
Trang 17COMPLETION PROCEDURE
After the contract casing crew runs the final casing,
cementing follows the usual procedure , although stage cementing may be necessary to cement an extremely long string
The production string has been hauled out to the location and the inside diameter checked to make sure that
imperfections will not prevent the subsequent running in of tubing and packers after the string is set
Trang 18 Special care: to prevent the possibility of future leaks
If stage cementing is necessary:
the bottom section is first cemented in place and then
a series of plugs are pumped down the casing to open ports that allow the upper end of the annulus to receive cement
After the cement has set, the inside of the casing must be
drilled out and
flushed clean of cement and other debris to a depth below that of the proposed completion
It is important that the inside diameter of the production casing be
COMPLETION PROCEDURE
Trang 19COMPLETION PROCEDURE
It is also important that the cement
form a competent seal between the
casing and borehole over the entire
openhole interval To ensure this,
an acoustic cement bond log is
sometimes run on wireline
to determine if voids exist
between casing and hole
because cement has bypassed the drilling fluid
Trang 20COMPLETION PROCEDURE
If the bond is poor in an area, particularly if the area is between
productive formations, a cement squeeze will be required
Often the cement bond log is run in conjunction with a gamma ray log and a casing collar log The drilling engineers can correlate this
gamma ray log with the logs run earlier during formation logging
This correlation is important because as we zero in on the target - the productive formation - our need to locate tools precisely relative to that formation is critical
The open hole logging sondes are subjected to a greater amount of
"drag" when being pulled up the hole, the depths at which formations
Trang 21COMPLETION PROCEDURE
If we were to perforate the casing according to the openhole log
depths, we might miss the formation entirely By using the correlation log and casing collar log to set packers and perforate, we are assured
of precise placement
At this point, many operators
move the drilling rig off location and
replace it with a less expensive, and often less powerful, completion rig
This gives the operator time to design the rest of the completion, provide for a sales contract, and order equipment
Trang 22 The casing may also be pressure tested,
and a filtered completion fluid may be circulated into the well to
displace the drilling mud prior to perforating
This fluid is usually a heavy brine, because it:
o provides the hydrostatic pressure needed to control the well,
Trang 23COMPLETION PROCEDURE
If perforating is to be done at this point,
the tubing is removed and
the perforating gun is lowered and positioned according to the correlation log and casing collars
It is critical that the gun be placed precisely;
once inaccurate perforations are made, they can only be plugged off with a costly cement "squeeze."
Trang 24COMPLETION PROCEDURE
With the well perforated, it may now be time to stimulate the well by either
acidizing or
hydraulically fracturing the formation
Acid can be used to dissolve formation-damaging particles left by the drilling mud or, in carbonate formations, to create flow passages by dissolving portions of the rock itself
Hydraulic fracturing involves the high-pressure pumping of fluid into the formation to split the rock apart and increase its flow capacity of tight formations
Trang 25COMPLETION PROCEDURE
Normally, a completion packer is run and set next, either incorporated into the tubing string or set independently on electric wireline
The packer is pressure tested to ensure its sealing ability (Many
shallow, low pressure wells, however, do not require a packer to isolate the casing from produced fluids.)
The tubing must then be "spaced out." This requires that a length of tubing be removed from the upper end so that it can be "landed" in the tubing head, which is some distance bellow the rotary table
Once the tubing has been landed in the tubing head, a temporary plug can be set inside the tubing while the BOP stack is removed and the surface flow control equipment ("Christmas tree") installed This plug
is then removed through the Christmas tree, and the well is completed
Trang 26COMPLETION PROCEDURE
Of course, this procedure will vary according to
the specific brands of equipment being installed,
the characteristics of the well,
and the policies of different companies,
but the essential sequence of operations will be followed
One variation is the procedure for perforating, which may be done after the tubing has been run
This approach allows the formation to be perforated and immediately
"cleaned up" by allowing it to flow as soon as the perforations are created
Trang 27COMPLETION PROCEDURE
The rig will often be moved off location at this point, allowing the well to brought on production On an offshore platform, the rig may be skidded
to the next well slot
If a rod pump is required on the well, it may be installed at this time and the necessary rods and downhole pumping mechanism run into the tubing
If gas lift valves have been incorporated into the tubing string, gas may be used to blow the completion fluid out of the tubing and permit the well to flow on its own
In some cases, the well will be "swabbed in" at this point, by running a close-fitting plunger into the tubing on wireline and pulling it back up, thereby displacing the completion fluid in the tubing and allowing the formation to flow
Trang 28COMPLETION PROCEDURE
After an initial well test, which may be conducted with temporary test facilities, the flow line needed to produce the well on a continuous basis
will be connected
Trang 293 PERFORATING
Trang 30 The use of cemented steel casing to line the wellbore and isolate
producing zones is only practical when a method for easily reopening those zones for production exists
Jet perforating is the procedure whereby an explosive charge is used
to selectively open passages to the formation through the casing and cement sheath This method:
the most widely used today, because of its versatility and power
Having evolved from the military bazooka, the jet perforator relies
on a conical-shaped charge of explosives to produce a high pressure stream of particles
Bullet perforators fire metal projectiles at the inside of the casing to penetrate casing, cement, and rock
This technique has pressure, temperature, and penetration
Trang 31 Jet perforating guns consist of
a carrier with a series of explosive charges linked together by a
detonating cord
A variety of gun designs exist; they vary according to:
- the gun is to be run on an electric conductor line or attached to the bottom of the tubing;
- the gun is to be run through the casing on electric line or tubing, or
is to be lowered through the tubing on electric line;
- the gun is retrievable following detonation or is expendable (meaning it is destroyed when the gun is fired);
- the diameter and length of the perforation desired
Trang 32 Wider, longer perforations require
larger, stronger jet charges,
and, larger guns to hold them
The charge itself is held in a metal case
that is linked to similarly shaped charges
by a detonating cord ending in an electric detonator
When the gun is fired, an electric current
from the surface sets off the blasting cap detonator, which secondarily ignites the
Trang 33When a charge is fired
The metallic liner collapses to form a stream of
high pressure, high velocity jet particles
Traveling at 30,000 ft/sec (9100 m/sec), the jet
stream strikes the casing at some 15x10 6 psi (100x 106kPa) a fraction of a second after detonation, to form a perforation.
a) before detonation b) after detonation , showing collapsing liner & swelling casing.
c) volatilizing metal liner and formation of particle
d) jet lengthens as process continues
Trang 34 Retrievable hollow carrier guns have cylindrical steel bodies with
closed ports opposite each jet charge
Fully expendable guns enclose the charges in a frangible aluminum or ceramic case that disintegrates on firing
while semiexpendable guns consist of wire or metal strip carriers that are retrieved after firing
Through-casing and through-tubing guns of these types differ primarily
in the diameter of the gun
• 3 to 5 inches [7.6 to 12.7 cm] for casing guns,
• 1 to 2 inches [2.5 to 5.1 cm] for tubing guns
Trang 35Type of perforating guns
• Retrievable hollow carrier guns
• Fully expendable guns
• Semi expendable guns
Trang 36PERFORATING GUNS
Trang 37 Conventional underbalanced perforating is usually carried out after
tubing has been run and equipment is installed to control the sudden pressure surge when the higher pressure formation is opened to the lower pressure wellbore
Trang 38 For a typical formation the difference between wellbore and formation pressure may be 300-500 psi (2000-3500 kPa)
For a low permeability formation, the typical difference between
wellbore pressure and formation pressure may be 2000 psi (13,800 kPa) or higher -> the immediate surge of formation fluids to prevent the clogging of the perforation tunnels with debris
When a maximum pressure differential is desired, a tubing-conveyed perforating gun may be used
it is possible to have the tubing run empty with a ported vent, which opens when the packer is set
Trang 39 In addition to perforation diameter and length, two important
considerations in all types of perforating are
the shot density
and phasing of the perforations
The shot density, or shots per foot, is usually 2, 4, 8,12, or 16 holes in each foot of perforated interval
Trang 41 The decision about the interval to be perforated is often made by the geologist
or by the engineer and geologist responsible for the area in which the well is drilled.
Consideration will be given to maximizing flow rate and minimizing production problems such as produced sand, water coning, or excessive gas production in an oil well
The decision is often made after careful review of the log and core data back at the company office
The geologist's input concerning net pay, sidewall core descriptions, and the areal extent of sand intervals can be crucial in determining the best interval to be perforated.
One of the advantages of the cased and perforated completion: ability to
selectively stimulate specific formations.