To accomplish this goal, the company has done the project of setting up, implementation the HACCP system and gaining HACCP certification.. The Project of setting up, implementing and gai
Trang 1setting up implementing the HACCP system of bottled drinking water products in San Miguel Co
1 Project Overview:
San Miguel Co., Ltd Vietnam is a 100% foreign own company established in October
2004 The company specializes in production of bottled high quality drinks such as Shiki honey tea , juices of Del Monte brand
San Miguel Co., Ltd Vietnam aims at speeding up the current operation practices and quality food safety and will set up programs towards the ultimate goal of customer satisfaction, improving customer responsiveness and quality of food safety
To accomplish this goal, the company has done the project of setting up, implementation the HACCP system and gaining HACCP certification HACCP stands for Hazard
identifies hazards in production processes that can cause the finished product to be unsafe, and designs measurements to reduce these risks to a safe level
2 Importance of the Project:
HACCP is a system used to identify, assess and control hazards which have important implications for food safety HACCP is a system of creating the trust, showing food safety is managed effectively The HACCP system considers threats or any other factors that may cause harm related to the safety of the product and then implements control measures to ensure the product is safe to consumers HACCP is a system that is
extremely practical for food processing companies This system helps food processing enterprises control hazards from the stage of materials until consumed by the user, to ensure food safety
and stable development of enterprises
employees
Trang 2 For customers, HACCP certification is a guarantee to users by the manufacturer in terms of quality and safety of the product
3. Project Goals :
- Project duration: 10 months
The Project of setting up, implementing and gaining certification to "the hazard analysis and critical control points system " (HACCP) for bottled drinking water products in San Miguel Co., Ltd Vietnam started from October 2007 and finished on 8/2008 The project goal is the HACCP conformity certification by an independent Assessment Organization to the company's products and its production system
- The cost of the project includes the followings:
• Consultancy on HACCP system
• Training programs for all employees of the HACCP system
• Assessment Audit on HACCP system by an Independent Audit Agency
• provisions of appropriate resources for the project, inspection of equipment and machinery
• The operation and administrative costs
- The scopes of the project :
The scopes of the project implementation included manufacturing facilities of the company in Amata Industrial Zone, Bien Hoa City, Dong Nai and applied to all
products, including:
• Assorted juices of Del Monte brand for export
• Bottled tea Shiki for the domestic market
- The requirements when applying HACCP:
• To ensure implementation of prerequisite programs (GMP, SSOP ) to minimize the hazards to food This program included the design requirements for buildings and equipment; hygiene behaviours, personal hygiene; factory hygiene, sterilization, insects control; warehouses etc
Trang 3• To build a control system including the processes, control procedures, supporting
documentation etc
• To focus on continuous improvement: The improvement activities or innovation
steps are beneficial if done regularly for safety management system
4. Implementing the Project Plan
Implementation steps:
No
1
Step 1 : to find out
the scopes of
application of the
HACCP system
- Understanding the meaning of HACCP for the development of the company
- Orientation activities
- Defining the objectives and the specific conditions of HACCP application
2 weeks
2
Step 2: Setting up
the Steering
Committee for
HACCP project
- Establishment of HACCP Project Steering Committee, the control and food safety groups
• Groups included Dept/section leaders and representative(s) of the department in the scopes of HACCP application
• The HACCP project Manager on behalf of the Company Management directed application of the HACCP system and responsible for its implementation
1 week
3
Step 3: Assessment
of the production
facilities compared to
the standard
requirements
- Reviewing the operations, requirements and the current level of production facilities
• The assessment used as the basis for planning the resources needed to change or supplement the company facilities
• As a result, the company built up programs, project details to ensure controling hazards to food safety at all times
1 month
Trang 4Step 4:Training
schedule with
programs appropriate
to each level
- Training contents include:
• awareness of HACCP, GMP (Good Manufacturing Practice),
• Setting up the HACCP records &
documentation system
• Training Internal Auditors
2 months
HACCP system
documentation
- The documentation system built to meet the requirements of standards and operating requirements of food manufacturing facilities includes:
• The Company’s policy on food safety
• The Company’s goals of food safety
• The procedures required by the HACCP standard
• The records required by the HACCP standard
• The documents required to set up the organization, implementation and effective date
of the food safety system
2 months
Step 6:Implementing
food safety
management system
HACCP
- Promoting all employees fully aware of the HACCP system documentation
- Defining clearly the responsibilities and authorities relating to each specific process
- Guiding employees to comply with the approved documentation
1 month
of the safety
management system
and preparations for
certification
assessment audit
- Conductting internal audits and evaluation of results,
- Analysis of the results of the verification activities to determine the appropriateness of management systems for food safety
- Carry out corrective actions and necessary precautions
- Selecting the certification assessment organization to assess and issue the HACCP
3 months
Trang 5conformity certificate.
- Taking previous assessment in order to determine the level of perfection and the readiness of the management system of food safety while preparing for the formal
assessment
Audit
- Conducted by an independent, impartial Organization to to confirm the appropriateness
of food safety management systems with HACCP requirements
- Certification
1 week
Step 9:Maintaining
food safety
management system
after certification
- To maintain the safety management system
to meet the food requirements of the standard and continuous improvement toward satisfying the public requirements of customers and stakeholders
Continuous
5 Project Implementation:
Project organization
- Project Manager: the company’s production Manager is the HACCP project
Manager, assisted by a project clerk and a project Assistant
- HACCP Group Leader: Heads of Deptartments/sections hold relevant roles in
coordinating and mobilizing the resources for the project
- In each HACCP group, there are staff in charge of each field or each area
Trang 66 The stakeholders of the project:
- Stakeholers of the HACCP project includes:
company Employees will have to constantly acquire the knowledge, skills, and increase awareness of quality systems and food safety in the company
Department of Trade
- Role of stakeholders:
Trang 7 Company leaders: their commitment to implement food safety policies and stick
to the same system of food safety management is the most important conditions for the success of HACCP
company ensures the operation, maintenance and improvement of the effective and efficient HACCP system
developing and implementing management systems to the requirements of
HACCP
7. Monitor ing and Control ling the Project:
Project Monitoring is conducted by the HACCP Steering Committee including the HACCP Project Leader and the Coordinating teams as:
- HACCP Documentation Team
- GMP Implementation Team
- Internal Audit Team
Every week the HACCP Steering Committee meet to provide guidlines
1
2
3
4
5
Product description, purpose of use Setting up the production process Confirming the manufacturing
To make a list of all hazards Hazard Analysis
To identify the critical control points
to set up critical limits for each CCP
Trang 87
8
9
10
11
12
to set up monitoring system for each CCP
to set up corrective actions
to set up verification procedures
to complete HACCP plan
to get the plan approved
To evaluate the HACCP plan
To confirm HACCP plan &
Update HACCP plan
8 Project Closure
The Project of setting up, implementing and gaining certification to "the hazard analysis and critical control points system " (HACCP) for bottled drinking water products in San Miguel Co., Ltd Vietnam started from October 2007 and finished on August 2008 With the commitment of the Company Management, the hard work of the employees and the excellent leadership and coordination of the HACCP steering committee and efforts from all other stakeholders, The result followed that the company has complied to all requirements of the HACCP requirements and achieved HACCP certification of QUACERT in October 2008
With certification of conformity with the safety standards of HACCP system, the company's products have affirmed its quality This step confirms the development of the company's products on the market of Vietnam and this is also the prerequisite for
Trang 9promoting products export of the company With the certification of conformity of the HACCP system, the company’s brands and image of the company will also be increased, thereby improving their competitiveness by improving the confidence of consumers with the products Last but not least, meeting the requirements of the social community will ensure the company with sustainable development