IMPROVE AND RENOVATE THE NETWORK SYSTEM LAN/WAN OF THIEN LONG STATIONERY GROUP CONTENT Task’s content • Identify the key issues • Wisely use related and updated documents • Quality of
Trang 1IMPROVE AND RENOVATE THE NETWORK SYSTEM LAN/WAN OF THIEN LONG STATIONERY GROUP
CONTENT
Task’s content
• Identify the key issues
• Wisely use related and updated documents
• Quality of the researched documents from good related sources
• Use examples as well as methods and business circumstance from working place in order to reinforce for arguments and conclusions
Task executing process
• Prove the clear theoretical understanding about the topic
• Thorough analysis and synthetic capabilities of theories and concepts related in referred documents to support the task
• Comprehensiveness in demonstrating an argument consistently and coherently
• Starkness in expressing ideas/ argument/ evidence
Overview of presentation and Structure of task execution
• The minimum level of presenting Assignment’s structure is including: cover page,
table of content, introduction, body, conclusion and references
• Spelling mistakes, grammar and syntactic
• Strong attach to details/ reading and adjusting
• Rightly use referred quotation and references
PROJECT
Trang 2IMPROVE AND RENOVATE THE NETWORK SYSTEM (LAN/
WAN) OF THIEN LONG STATIONERY GROUP
Execution unit: HiPT Company Total project duration: 90 days Starting date of project: 01/04/2010.
Total budget for project: 90.000 USD
I/ PROJECT INTRODUCTION
This is the project of improvement and renovation the Network system (LAN/WAN), Server, Email of Thien Long Stationery Group As establishment history, from one small manufacturing company, nowadays, Thien Long develops strongly to Group with larger scale from day to day The existing network system, server and email could not adapt to the increasing demand of development for both current and future situation Therefore, Thien Long Group has decided to create the Project of Improvement and Renovation the Network system (LAN/WAN), Server and Email
II/ OVERVIEW AND CURRENT STATUS OF THE NETWORK SYSTEM
1/ The Local- Area Network (LAN)
As existing infrastructure, the computer internal cabling network has been built and used for a quite long time In production process, arising from the demand
of developing the company in market, human resources as well as other equipment serving for working as computer, this network is essential to be broadened and expanded adapting need for each specific period of time Gradually, the system is changing to be different compared to the initial structure as well as the technical and aesthetic features
Trang 3The current cabling system is rather complicated because it was not invested synchronically and unifyingly Since system being broadened temporarily with issue-immediate-confronting idea, part of it was laid floating on the floor, worming
in the walls, another part was fixed by temporary string knots without protection tube or by sticking-plaster (arising from the demand of working desk location changing or adding more working plots) The existing cabling system is using diversified kinds of cables with different quality standards (UTP CAT5) that leads
to the slow connected capability as multi-layer classification (the number of users is increased, so system is broadened by add more switches and used any node to uplink backward the previous switch) Internet connecting equipment (Hub, Switch…) is not synchronized and could not be protected in good and safe environment (protection cabinets, thermal dispersion…)
2/ Wide- Area Network (WAN):
Previously, due to the need of development was slow; there were only one manufacturing factory and one office However, these days, as the expansion and demand of development be broadened, more and more factories, offices, stores, agencies… are opened in different places across the country From that, the demand
of connecting all those places appears With the old system, it could not adapt the increasing demand; therefore, it is necessary to build the wide-area network
3/ Server system
Server system equipped before is becoming old with low configuration and incapacity Thus, the system could not meet the demand of improvement of Thien Long Group
4/ Email system
The old email system leading to common issues of email unable to be received, email losing; spam mail often received, etc… moreover, the development
in number of employees, all of them making the email system could not adapt the workload
III/ THE IMPORTANCE OF NETWORK SYSTEM RENOVATION
As analyzed above, the network, server and email renovation has significant important role to business of Thien Long Group In case not renovating and improving,
Trang 4Thien Long Group has no chance to develop not only in current situation but also in future
IV/ OBJECTIVE, SCALE OF RENOVATING INVESTMENT
With the rise of information technology today, as well as the application of informatics technology for work, business, and production, the execution of improvement and renovation the current system is absolutely matched with increasing demand is inevitable It has to make sure the system work smoothly with security, data security and good processing speed
The renovation needs to be taken simultaneously and uniformly in large scale for the purpose of synchronizing technical standard of cabling system, starting-terminal equipment, server and email During the work of new system, it is regulated that the construction has no effects on current operation of existing system (the existing system will be removed right after the new system is finished)
V/ IDENTIFY & DESCRIBE THE ROLE OF KEY HUMAN RESOURCES OF PROJECT AND CONCERNED PARTIES
1 In term of Thien Long Group
a Project manager: IT department manager
- is the person who has the power, responsibility, jurisdiction and liability to explain the final result of the entire project
- is the person who takes responsibility of network model specialty and network equipment needed to purchase
- is the person who allocates works for colleagues within project, prepares work execution plan together with the starting and ending date of project
- is the person who prepares the budget plan for the whole project
- is the person who makes decisions, plans, organizes, leads, controls, communicates and builds supportive environment for project
b Employee and co-workers supporting project
- Number of employees from IT department:
Trang 5Take in charge and has authorities of part of assigned work within project
- Purchasing department
Take in charge and have responsibilities of buying equipment and materials that are right categories and with the best quality
- Accounting department
Take in charge and have responsibilities of paying sufficiently and timely
- Human resources & Administration department
Attendance checking, payroll making and other benefits for employees taking part in the project
- Electricity technical department
Taking in charge and have responsibilities of designing and executing the work of electric wire system and power sources for project
- Security department
Taking in charge and have responsibilities of supervising and controlling the materials in or out the company and the appearance of projecting people within the company’s area
2 In term of the party who executes the work
After the tender, HiPT Informatics Company is chosen as the work executing party for project
HiPT Company takes responsibilities of executing the work with proper techniques and expertise as well as following the working schedule as contract signed with Thien Long group
VI/ EXECUTING DURATION AND ENDING DATE OF PROJECT
- Duration of work executing is 90 days
- the starting date of project is 01/04/2010
VII/ WORK BREAKING DOWN STRUCTURE (WBS)
PROJECT
Trang 6VIII/ ORDER OF OPERATIONS
IX/ TOTAL BUDGET FOR PROJECT
LOCAL AREA
NETWORK
(LAN)
WIDE AREA NETWORK (WAN)
Network
equipment
installation
Network cable
setting up
Wide area network equipment installation
Server purchasing
Email copyright purchasing
Lease line subscription
Server installation
Email installation
START
LAN
WAN
END
Trang 7TOTAL AMOUNT 90.000
X/ PROJECT EXECUTION SCHEDULE
XI/ PROJECT CONTROLLING AND SUPERVISING
- Supervise the work being done by project executing party on daily basis
- After one week, project is checked all the done items
- Checking the working schedule
- Checking all the purchased materials on base of right categories, specifications, and quality
Trang 8- If meeting difficulties during the executing period, project team will meet and discuss to find solutions
- For every 30 days, meeting for consideration and assessment of project is held
- When each items of LAN, WAN, SERVER, EMAIL is done, it will be tested, played trial as well as assessed the operating level and only is accepted if everything goes smoothly On the contrary, it will be repaired until the quality and operation are deemed to be well
- When the checking results of all items are well-operated, items will be taken over for acceptance
XII/ CONCLUSION
With the nowadays trend of development, Informatics is the significant breaking-through of human headway If there is not informatics, for sure, the development of society is not reached the high level as these days
Informatics in general and Network cable in particular, together, support greatly for the development of Companies, among them is Thien Long Stationery Group As realizing the importance of this trend, Board of Directors of Thien Long Group has no ponderation of investing in the renovation and improvement Local Area Network (LAN), Wide Area Network (WAN), Server, Email, etc…
This project was very successful with right schedule as well as quality It also contributes in great ratio to the development as well as brings the benefits for Thien Long Group
Reference documents
- Curriculum of Prof BRIAN O`REILLY
- Project Manager of Olaf Passenheim
Trang 9TABLE OF CONTENTS
-o0o -I/ PROJECT INTRODUCTION 3
II/ OVERVIEW AND CURRENT STATUS OF THE NETWORK SYSTEM 3
III/ THE IMPORTANCE OF NETWORK SYSTEM RENOVATION 4
IV/ OBJECTIVE, SCALE OF RENOVATING INVESTMENT 4
V/ IDENTIFY & DESCRIBE THE ROLE OF KEY HUMAN RESOURCES OF PROJECT AND CONCERNED PARTIES 5
VI/ EXECUTING DURATION AND ENDING DATE OF PROJECT 6
VII/ WORK BREAKING DOWN STRUCTURE (WBS) 6
VIII/ ORDER OF OPERATIONS 7
IX/ TOTAL BUDGET FOR PROJECT 7
X/ PROJECT EXECUTION SCHEDULE 8
XI/ PROJECT CONTROLLING AND SUPERVISING 8
XII/ CONCLUSION 9