Trang 1DAELIM INDUSTRIAL CO., LTD
METHOD STATEMENT PROJECT: HANOI PILOT LIGHT METRO LINE
Section Nhon - Hanoi Railway Station
PACKAGE: LINE-ELEVATED SECTION PACKAGE NUMBER: HPLMLP/CP-01
METHOD STATEMENT FOR SHORED EXCAVATION
Location: Tu Liem, Cau Giay, Dong Da and Ba Dinh – Ha Noi City
PROJECT IMPLEMENTATION CONSULTANT: SYSTRA S.A
January, 2015
Project Reference: DLM-IMP-PPG-WVO-J07-00001-E-1A
Trang 2
PROJECT: HANOI PILOT LIGHT METRO LINE
Section Nhon - Hanoi Railway Station
PACKAGE: LINE-ELEVATED SECTION PACKAGE NUMBER: HPLMLP/CP-01
METHOD STATEMENT FOR SHORED EXCAVATION
Location: Tu Liem, Cau Giay, Dong Da and Ba Dinh – Ha Noi City
PROJECT IMPLEMENTATION CONSULTANT (SYSTRA S.A.)
Trang 3Contractor Approval / Revision Record Sheet
Revision
Contractor specific comments:
Trang 41 INTRODUCTION OF PROJECT 6
1.1 INTRODUCTION 6
2 SCOPE OF WORK 6
2.1 GENERAL 6
2.2 SCOPE 7
2.3 REFERENCE 7
3 CONSTRUCTION PROCEDURE 8
3.1 QUANTITY OF WORK 8
3.2 REFERENCE TO BORE HOLE 17
3.3 SCHEDULE OF WORK 21
4 PERSONNEL ORGANIZATION 22
4.1 PERSONNEL ORGANIZATION FOR MAIN CONTRACTOR 22
4.2 PERSONNEL ORGANIZATION FOR SUB – CONTRACTOR SPECIAL BRIDGE 23
4.3 PERSONNEL ORGANIZATION FOR SUB – CONTRACTOR TYPICAL BRIDGE 24
5 MATERIALS, EQUIPMENT AND MANPOWER 25
5.1 MATERIALS 25
5.2 EQUIPMENT 25
5.3 MANPOWER 26
6 CONSTRUCTION METHOD 27
6.1 CONSTRUCTION FLOW CHART 27
6.2 DETAIL OF CONSTRUCTION METHOD 28
6.2.1 MOBILIZATION AND PREPARATION WORKS 28
6.2.2 CONSTRUCTION OF COFFERDAM (STEEL SHEET PILES) 28
6.2.3 CONSTRUCTION OF COFFERDAM (STEEL SHEET PILES) 29
6.2.3.1 Excavation Stage 1: About install struts and wales 29
6.2.3.2 Excavation Stage 2: Excavation by machine until design level and hauling out of excavated material 30 6.2.3.3 Excavation Stage 3: Trimming and leveling work 30
6.2.3.4 Construction for temporary drainage system (Dewatering) 30
6.2.3.5 Cleaning up site 30
7 QUALITY CONTROL 31
8 HEALTH, SAFETY AND ENVIRONMENT CONTROL 31
8.1 HEALTH AND SAFETY CONTROL 31
8.2 ENVIRONMENT CONTROL 32
8.3 HAZARD ANALYSIS 32
9 TRAFFIC CONTROL 33
10 APPENDIX 33
10.1 APPENDIX 1: METHOD DRAWING 34
10.1.1 SHORED EXCAVATION METHOD DRAWING FOR TYPICAL BRIDGE 34
10.1.2 SHORED EXCAVATION METHOD DRAWING FOR SPECIAL BRIDGE 34
10.2 APPENDIX 2: INSPECTION AND TESTING PLAN 35
10.3 APPENDIX 3: TYPICAL SCHEDULE FOR SHORED EXCAVATION OF 01 PILE CAP 36
Trang 5Abbreviations MRB Hanoi Metropolitan Railway Management Board
PIC Project Implementation Consultant (SYSTRA S.A.)
DLM Daelim Industrial Co., Ltd
Project References
1 DLM-IMP-PPG-WVO-J07-00001-E-1A Method statement for shored excavation
Trang 61 INTRODUCTION OF PROJECT
1.1INTRODUCTION
Hanoi Pilot Light Metro Line, section Nhon - Hanoi Railway Station is a major project for Hanoi City.According to the Hanoi Transportation Master Plan till 2020, total length of HPLML (Line 3) shall reach21,5km from Nhon to Hoang Mai.The first phase of this line, and part of this Contract is from Nhon toHanoi Railway Station, with about 8.5 km elevated section and 4.0 km underground section This lineincludes 12 stations (with 8 elevated and 4 underground stations) The Depot is located at Nhon with area
of 150,550m2
The CP01 Contract’s work scope is Viaduct Line at Elevated Section, including the construction ofviaduct structures which link along the National Road No32, Ho Tung Mau, Xuan Thuy, Cau Giay andinterfaces with underground section at the beginning of Kim Ma Street The contract shall be completedand within 30 months from the date of the Commencement Date
Both metro and structure alignment follow the current and/or planned median road Viaduct structures aredivided into standard viaducts which cover most of the elevated section and special viaducts where long orspecial spans are required to pass over major constraints (2nd Ring Road, 3rd Ring Road, Nhue River).Other non-typical structure consists in Cross Over (metro line requires switches), ramps to depot andunderground sections and Y-bridge (branches off to depot) The overview of the project is shown in photobelow:
Shored Excavation shall be undertaken in accordance with clause “3.4 - Shored excavation, Part II,Chapter II-2” of Technical Requirement This method is generally applied to Shored excavation to thedesign bottom elevation for all pile caps using shoring system
Trang 7This method also includes disposal of unsuitable excavated material, dewatering works and related works
to be free from the accumulation of ground water and artificial runoff water inside excavated area ShoredExcavation shall be done in accordance with the perimeters and slope as indicated on the approvedworking drawing
2.2SCOPE
The Contractor shall set up and submit method of shored excavation The Contractor can adjust methodfor shored excavation in accordance with the actual condition on the site or at the direction of ConsultantEngineer All adjustments will be reviewed and approved by the Consultant Engineer, Employer
After obtaining consent from the Consultant Engineer, Employer, the Contractor will carry out shoredexcavation
Shored excavation part including:
Shored excavation for pilecap type I (Standard pile cap)
Shored excavation for pilecap type II (Cantilever pile cap)
Shored excavation for pilecap type III (Special pile cap)
The Contractor will use method of excavation works of foundation pit by excavator and manpower
2.3REFERENCE
Reference document:
- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Section 3 Earthwork.
- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.4.Shored excavation
-Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.3.Common excavation.
- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.5 Preparation andinspection of foundations
- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.8 Grade preparation.
- Contract Package 04/2014/HD-TCXD, PART II - Chapter II-2, Sub-Section 3.9 Water Control
- Construction Management Plan, document No : DLM – IMP – PPG – ZCO – J00 – 00001 – E
- Quality Plan, document No : DLM – IMP – PPG – ZPQ – J00 – 00001 – E
- Delivery Management Plan, document No: DLM – IMP – PPG – ZPO – J00 – 00001 – E
- Traffic Management Plan, document No: DLM – IMP – PPG – ZPO – J00 – 00004 – E
- H&S Management Plan, document No: DLM – IMP – PPG – ZSO – J00 – 00003 – E
- Environment Management Plan, document No: DLM – IMP – PPG – ZSO – J00 – 00002 – E
- Security Management Plan, document No: DLM – IMP – PPG – ZSO – J00 – 00001 – E
Trang 83 CONSTRUCTION PROCEDURE
3.1QUANTITY OF WORK
The estimated quantity is as followings table Below quantity is only reference Final quantity shall becalculated in accordance with approved working drawing Topographic survey of original ground whichhad been approved shall be applied to calculate the quantity for structure excavation
Trang 9No Type of bridge Pier
Trang 10Width (m)
Trang 11Width (m)
Trang 15Width (m)
Trang 173.2REFERENCE TO BORE HOLE
Based on alignment geological borehole, we have reference table of geological boreholes in accordance
Trang 18with pier position Reference table is established for piers of Typical Bridge and Special Bridge.
With dimension, depth and geology of borehole at position of piers, Contractor calculated and proposedall piers in alignment have to use sheet piles cofferdam during excavation process
Also, at position of pier caps with dimension (10.9x7.4x3.5m và 5.6x4.8x3.0m), Contractor use bracingsystem inside steel piles cofferdam
Dimension, sheet pile cofferdam lay out, scope of application spreadsheet for all kinds of pier cap onTypical Bridge is shown in the attached drawing in section 10.1.1
Dimension, sheet pile cofferdam lay out, scope of application spreadsheet for all kinds of pier cap onSpecial Bridge is shown in drawing DLM-IMP-GPV-WVO-JOO-10003-B and DLM-IMP-GNS-WVO-JOO-10018-B (attached in section 10.1.2)
Spreadsheet for pier cap in the most unfavourable when constructing pier cap with cofferdam withoutwales & struts inside, will be submitted separately
Spreadsheet for pier cap in the most unfavourable when constructing pier cap with cofferdam and wales &struts inside, will be submitted separately
Trang 19Organic silt, firm/Bụi lẫn hữu cơ, dẻo mềm
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,firm/Sét dẻo thấp dẻo mềm
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Organic silt: soft/Sét dẻo thấp dẻo chảy,
Lean clay,firm/Sét dẻo thấp dẻo mềm
Organic silt, firm/Bụi lẫn hữu cơ, dẻo mềm
Layer 3/Lớp 3
Lean clay with some organic,firm /Sét dẻo thấp, đôi chỗ lẫn ít hữu cơ dẻo mềm
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Layer 2/Lớp 2
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/ Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Trang 20Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/ Đất lấp
Layer 2/Lớp 2
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean Clay, Stiff-very stiff/Sét dẻo thấp nửa cứng
Layer 3/Lớp 3
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Organic silt:
soft-firm/Sét dẻo thấp dẻo chảy, mềm
Lean clay,firm/Sét dẻo thấp dẻo mềm
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Organic silt, firm/Bụi lẫn hữu cơ,dẻo mềm
Organic silt, Stiff/cát lẫn bụi, xốp- rất xốp
Organic silt, firm/Bụi lẫn hữu cơ,dẻo mềm
Organic silt: soft- firm/Sét dẻo thấp dẻo chảy, mềm
Cobble,Gravel with sand, very dense/Cuội sỏi, lẫn cát, rất chặt
Organic silt ,firm/Sét dẻo thấp dẻo mềm
Silt sand,medium dense/Cát lẫn bụi,chặt vừa
Organic silt firm/Sét dẻo thấp dẻo mềm
Organic silt ,firm/Sét dẻo thấp dẻo mềm
Silt sand,medium dense/Cát lẫn bụi,chặt vừa
Trang 21Reference to
Special bridge/Cầu đặc biệt
Organic silt, firm/Bụi lẫn hữu cơ, dẻo mềm
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Silt sand, medium dense/Cát lẫn bụi,chặt vừa
Silt sand, medium dense/Cát lẫn bụi,chặt vừa
Organic silt, firm/Bụi lẫn hữu
cơ, dẻo mềm
Organic silt, firm/Bụi lẫn hữu
cơ, dẻo mềm
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay, firm /Sét dẻo thấp dẻo mềm
Organic silt, firm/Bụi lẫn hữu
cơ, dẻo mềm
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Organic silt: soft- firm/Sét dẻo chảy, dẻo mềm
Organic silt, firm/Bụi lẫn hữu
cơ, dẻo mềm
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Made ground/
Đất lấp
Made ground/
Đất lấp
Layer 3/Lớp 3
Organic silt:
soft/Sét dẻo thấp dẻo chảy
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay, firm /Sét dẻo thấp dẻo mềm
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Layer 2/Lớp 2
Lean clay,very Stiff /Sét dẻo thấp dẻo cứng
Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Lean Clay, Stiff-very stiff/Sét dẻo thấp nửa cứng
Organic silt firm/Sét dẻo thấp dẻo mềm
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Made ground/
Đất lấp
Trang 234 PERSONNEL ORGANIZATION
4.1PERSONNEL ORGANIZATION FOR MAIN CONTRACTOR
HEAD OFFICE ↑ SITE OFFICE ↓
SITE ENGINEER
QUANTITY SURVEYOR
CONTRACT
M ANAGER (CHOI,JAE-HOON)
PROGRAM M E TEAM CONTRACT TEAM
PLANNING DEPARTM ENT PLANNING M ANAGER DEPUTY PROJECT M ANAGER (CHOI,JAE-HOON)
COST CONTROL
M ANAGER (LEE,CHUNG-HEE)
ADM M ANAGER (KWON,YONG-SHIK)
CASHIER
(DOAN HUU KHOAT)
CLERK (NG T THANH)
CHIEF CIVIL ENGINEER (SƠN TRẦN NGỌC)
SPECIAL BRIDGE CHIEF CIVIL
ENGINEER (T T HUY) ACCOUNTING TEAM
LEAD OF
GEOTECHNICAL
(ĐẠI TRỊNH XUÂN) (TÚ NGUYỄN M INH)
(NG X HAI)
(NG V PHONG)
INTERFACE COODINATE
(HOÀ PHẠM THÁI) (KHIÊM TRẦN ĐĂNG)
CHIEF SURVEYOR (T TRUNG THANH) DESIGN TEAM
(Control Environment)
SAFETY SUPPORTERS
H/S ENGINEER (TOÀN NGUYỄN KHÁNH)
H/S ENGINEER (NGUYỄN VĂN TỚI)
ENVIRONM ENT ENGINEER
SECURITY OFFICE SECURITY GUARDS
(Control Security , health and safety)
FLAGM EN
COST CONTROL TEAM
SITE SECURITY M ANAGER
(Control Traffic, health and safety)
PROJECT M ANAGER (SEO,YOUNG-HWA)
ADM INISTRATION M ANAGER (HEO,SEON-HAENG)
SUPERVISOR
CHIEF ACCOUNTANT (T H ANH)
M ATERIAL PURCHASER
CHIEF OF LABORATORY
QC CHIEF ENGINEER (T M KHANH)
LABORATORY STAFF (TÚ TRẦN ANH)
CONSTRUCTION M ANAGER (OH,SEUNG-JONG) ENV/SUPPORTERS
QA / QC DEPARTM ENT QUALITY ASSURANCE M ANAGER
(G B NGOC)
QUALITY CONTROL TEAM
HEALTH & SAFETY M ANAGER (V V THUY)
(NG NG TRÌNH)
CHIEF STR ENGINEER
(D TUNG)
(HOANG TIEN TRUNG)
ADM INISTRATION DEPARTM ENT
(PHƯƠNG NGÔ GIA)
(T T TINH)
Trang 244.2PERSONNEL ORGANIZATION FOR SUB – CONTRACTOR SPECIAL BRIDGE
Construction Team/
Bộ phận thi công
Mr Trần Hữu ThắngPhone: 0983-899-315
Mechanical Team/
Bộ phận máy thi công
Mr Cao Tiến SơnPhone: 0985-320-691
Tổ thi công đào
Traffic AssuranceTeam/
Tổ Đảm bảo giao thông
Planning,QS Team/
Bộ phận Kế hoạch, khối lượng
Mr Lê Thăng QuânPhone: 01683-636-867
Sheet pile Team/
Tổ cọc ván thép
GIÁM ĐỐC ĐIỀU HÀNH DỰ ÁN
Mr.Lê Lệnh BắcPhone: 0913253582
Trang 254.3PERSONNEL ORGANIZATION FOR SUB – CONTRACTOR TYPICAL BRIDGE
GIÁM ĐỐC ĐIỀU HÀNH DỰ ÁNMr.Nguyễn Tuấn AnhPhone: 0989059379Email: tuananhsd73@gmail.com
PHÓ GIÁM ĐỐC BAN ĐIỀU HÀNHPhụ trách quản lý thi công, ATLĐ, đảm bảo giao
thôngMr: Trần Ngọc QuýPhone: 0979267723Email: ngocquyc14@gmail.com
PHÓ GIÁM ĐỐC BAN ĐIỀU HÀNHPhụ trách kế hoạch, thanh toán, kỹ thuật
Mr: Đào Đức HuynhPhone: 0913060752
BỘ PHẬN KẾ HOẠCH, KHỐI LƯỢNG
Mr Bùi Quang VinhPhone: 0949393492
BỘ PHẬN MÁY THI CÔNG
Mr Đỗ Đường TúPhone: 0974112422
Mr Nguyễn Trung KiênPhone: 0979898568
Mr Lê Văn Tuấn
Phone:0972405191
Mr Nguyễn Sỹ ThườngPhone:016689912487
Mr Nguyễn An QuangPhone:01689615196
Mr Nguyễn Văn ĐôPhone:0918488598
Mr Trần Văn CườngPhone:0972405191
Mr Đàm Quang ChiếnPhone:0984322270
Mr Nguyễn Văn HùngPhone:0936672916