TABLE OF CONTENT 1. A project overview………………………………………....3 2. An administration plan……………………...……………...5 3. Gantt chart………………………...………………………..8 4. Identification of potential problems………………………..9 5. Costing of expected time and materials…………………..10 6. A project monitoring tool…………………………………11 7. Brief review of the project………………………………..14
Trang 1Project design and advertising handing out flyers occasion celebrating 30/4 and 1/5
"
The Golden Week"
Green Eden Restaurant
Address: 365 Xuan Dieu Street - Ha Noi
Hotline: (04)37568686 Fax: (04)37568686 Email: Greeneden@infor.com.vn
Website: http://Greeneden.com.vn
Trang 2TABLE OF CONTENT
1 A project overview……… 3
2 An administration plan……… ……… 5
3 Gantt chart……… ……… 8
4 Identification of potential problems……… 9
5 Costing of expected time and materials……… 10
6 A project monitoring tool………11
7 Brief review of the project……… 14
Nguyen Duc Tai
Trang 3Green Eden Restaurant
Project design and advertising handing out flyers occasion celebrating 30/4 and 1/5 " The Golden Week"
I A project overview
As you know, work to promote the image, the brand is critical to the success of your organization, of which there are many different types of advertising to be considered for referral to the client These include the different types of advertising such as, flyers, signs, the internet, on television all brought about certain effect In which the handing out flyers is calculated often the first, with the advantages of shorter design time, low cost, easy access to customers With the business sector of our fast food is no exception, we always want to serve our customers in the best way and the best preferential with
customers We are regularly sent to the customer such preferences, and we want our customers to know that information quickly and clearly
On the occasion of 30/04 and 1/5 we have special programs how customers, celebrated sale promotion "The Golden Week" celebrating 30/4 and 1/5 "The occasion of the 30/4 -1 / 5, 10 – 20% discount when customers come to Green Eden Restaurant", the start time from 7:30 am on 22/4 until 22 pm on 28/4 applies to all customers We have selected designing are flyer advertising the first channel for our restaurant
Create sample brochures, flyers promotions company 30/4-1/5 occasion " Occasion 30/4 -1 / 5, up 10-20% when customers come to Green Eden Restaurant", the start time from 7:30
am on 22/4 until 22 pm on 27/4 applies to all visitors goods
Time: 8am handing out flyers from 20/04 to 25/04 2013
In terms of design flyers, brochures:
Discounts from 10-20% for all visiting and calling fast food in Eden Green Restaurant Ads of the week off of fast food restaurants Green Eden
The food is off the most: Pizza, spaghetti, seaweed rice rolls, Gimped fried…20%
Quantity: 15,000 copies
Management: Group marketing
Trang 4People passing out: 4 people
Human resources: Students Part-time
Cost: 12,000,000
Objective: Ensure flyers to clients is 80%, bringing the latest information about the restaurant's promotions to customers
Nguyen Duc Tai
Trang 5II An administration plan
Green Eden Restaurant (venue VND)
Activity Start End Personnel Performance standards Budget Preparation
-Meeting assign
specific tasks to
each person
-Estimate the
number of
leaflets were
printing and
distribution
processes to
clients
-Prepare
relevant
documents
-Prepare budget
forecasts
15 Apri l 201 3
17 April 2013
Mr Tai
Mr Hoang (maketing)
-Assign specific tasks to each person
-The number of leaflets / leaflets delivered to customers
-Prepare a work plan for the project
-Preparing documents related
-Prepare a budget for the full cost of the project from beginning to end
Implementation
-Designs and to
choose
appropriate
sample flyers for
restaurant
-Given full
information
about the
company's
promotions on
this form
-Print and
photocopy
-Select locations
and handing out
flyers
-Synthesis of the
effectiveness of
the handing out
flyers
18 Apri l 201 3
25 April 2013
Tai, Hoang, Linh, Hung, Tuan, Trang, Hue
-Restaurant name, address, name promotions -Start time promotions -Content about
discounts, promotions for the entire menu of restaurant (Discounts from 10-20% for all visiting and calling fast food restaurant in Eden Green.)
-Cuisines are the most discounts (The food is off the most: Pizza, spaghetti, seaweed rice rolls, Gimped fried…
20%) -15,000 copies
- Human resources:
Students Part-time
-Design flyer 500,00 -Printing and photocopy (15,000) 7,500,000
-Persons distribute flyers 4,000,000
Trang 6-Collect and
synthetic results
-The difficult
problems
encountering
-Solutions to
solve problems
-Analysis
solutions
-Written report
to superiors
-Presented at the
meeting of the
management
24 Apri l 201 3
28 April 2013
-Receive feedback from customers to the
restaurant -Make surveys sent to customers
-Directly monitoring employees leaflets -Analyze and evaluate information
-Made the comment and the results of work -Discuss and offer solutions to remedy omissions
-Written report about the work, these results obtained and omissions -Make statements about the cost of work
-Presented at management meetings
Nguyen Duc Tai
Trang 7Key Stakeholders
1 Nguyen Duc Tai Green Eden
Restaurant -Approved by project flyer
-Appointment of project manager -Set objectives and meet the needs project
-Printing contracting -Inspection and the reception
-Inspection results and reports
Marketing Manager Tel: 0943614999
2 Nguyen Tien Hoang
Nguyen Tương Linh
Green Eden Restaurant
-Design flyers -Make a list of time for work
-Cost estimate for the work
-Find leaflets staff -Set report on the work
Marketing Department Tel:
3 Pham Thi Hue
Nguyen Quynh Trang
Tran Trung Tuan
Nguyen Manh Hung
Employees handing out flyers
-Handing out flyers correct location is required
-Ensuring leaflets be release delivered to customers
-Their enthusiasm and openness at work
Students Part-time
Trang 8III Gantt chart
Nguyen Duc Tai
Trang 9IV. Identification of potential problems
Control
element Potential problems Identification pointers Preventive action
Timelines Unexpected delays
such as equipment breakdown(printers, photocopier
damaged)
When the equipment first breaks down
-To ensure the project will be finished according to the timeline -Ensure equipment is serviced prior to the project
Cost Costs exceed the
permissible level of the company
Changes in market prices lead to wage increases for employees, printing of documents for the project increased
-Provide more money -Find the location print /photo cheap -Used Printer/ copier company
-Decrease The number of employees
Resources Lack of human
resources and equipment to work
-when marketing department employees sick leaves prolonged
- Office equipment damaged
-Looking person in the same room have the ability to replace
-Find someone who can
be trained to take over?
- Repairing or replacing equipment as needed Quality -Marketing
department employees do not complete the task
-Schedule submit handing out flyers delayed Are more than half day compared with plan
-Tabulating clearly assign tasks to each member
-Monitoring and support staff handing out flyers
Trang 10V. Costing of expected time and materials
staff
Per hour VND
No.
hours
Total VND Section A: Preparation
Meeting assign specific tasks to
each person
2 0 3 0
Estimate the number of leaflets
were printing and distribution
processes to clients
2 0 1 0
Prepare relevant documents 1 0 6 0 Prepare budget forecasts 1 0 2
0
Sections B: Implementation
Designs and to choose appropriate
sample flyers for restaurant 1 100,000 5 500,000 Given full information about the
company's promotions on this form
1 0 4 0
Print and photocopy 1 24 7,500,000 Select locations and handing out
flyers
4 50,000 20 4,000,000
Synthesis of the effectiveness of the
handing out flyers
2 0 12 0
12,000,000
Section C: Completion
Collect and synthetic results 3 0 24 0 The difficult problems
encountering
3 0 8 0
Solutions to solve problems 2 0 4 0 Analysis solutions 2 0 4 0 Written report to superiors 1 0 2 0 Presented at the meeting of the
management
1 0 1 0
0
Nguyen Duc Tai
Nguyen Tien Hoang Page 10
Trang 11VI A project monitoring tool
Nguyen Duc Tai
Nguyen Tien Hoang Page 11
"
T h
e
G o
l d e
n
W e
e k
"
c e l
e b r
a t
i n g
3 0 /
4
a n d
1 /
5
"The G
olden W
r e p a r
a t
i o n
Preparation
Trang 12Nguyen Duc Tai
Nguyen Tien Hoang Page 12
"
T h
e
G o
l d e
n
W e
e k
"
c e l
e b r
a t
i n g
3 0 /
4
a n d
1 /
5
"The G
olden W
r e p a r
a t
i o n
Preparation
Trang 13Green Eden Restaurant
Address: 365 Xuan Dieu Street - Ha Noi
Hotline: (04)37568686 Fax: (04)37568686 Email: Greeneden@infor.com.vn
Website: http://Greeneden.com.vn
Implementation surveys with external customers of the handing out flyers
Green Eden Restaurant with the brand promotion is very essential, we are serious about bringing to beautiful pictures and the fastest delivered to customers We were construction a staff of advertising handing out flyers very professional, friendly and always smiling to the customer So have objective perspective about our work, we are looking forward customers have contributions, feedback so that we can better serve Thank you for valued customers
Valued customers know our restaurants through any form of advertising? (One tick)
Flyers Posters The internet
Valued customers felt are bothered by person handing out flyers? (One tick)
Yes No
Promotional information of restaurants provided adequate and correct? (One tick)
Adequate Incomplete Flawed
Information about the promotions of the restaurant will be sent to by flyers Valued customers have wanted to receive them? (One tick)
Yes No
Thank you for coming to Green Eden Restaurant
Trang 14Green Eden Restaurant
Address: 365 Xuan Dieu Street - Ha Noi
Hotline: (04)37568686 Fax: (04)37568686 Email: Greeneden@infor.com.vn
Website: http://Greeneden.com.vn
Internal customers
In addition interest in the work with clients to advertise, we also have the interest and help each other in the work The design personnel and our handing out flyers are always
supported by restaurants To ensure best quality for brand promotion, we have better support about funding, salary and bonuses for employees In addition we have also
interested in meeting and dining held among members We always have the comments box income for the employees
We have also regularly survey forms to capture the needs and desires of employees
You feel the work environment of the company like? (One tick)
Very good
Good
Usual
Not good
Do you feel satisfied with salary and bonus? (One tick)
Satisfied
Not satisfied
Do you want long-term commitment to your work? (One tick)
Yes
No
If you have any comments or need anything You make contribute directly with the management or mailboxes comments Thank you
Nguyen Duc Tai
Nguyen Tien Hoang Page 14
Trang 15VII Brief review of the project
Project Summary: Project design and advertising handing out flyers occasion celebrating 30/4 and 1/5 "The Golden Week"
In the 2 weeks, the team has designed, printed and issued 15,000 flyers to customers, and collects a lot of positive effects for the restaurant We have launched a lot of questions for customers to come to us We have made a summary of the effect of job
Regarding the opinion of external customers:
82% the flyers already delivered to customers
70% of customers come to the restaurant known handing out flyers of restaurant
1200 customer views felt joy at with flyers in total arrivals in 1500 asked
Many customers upset by person handing out flyers annoy
Opinions of customers inside:
Employees’ conscious does not work well
Moving vehicles difficulties
Costs make increases flyers
Lack of working equipment
Lack of cost
Solutions:
Monitoring and support staff handing out flyers
Enhance interpersonal skills for employees
Prompted with the employees work attitude not good
Repairing or replacing equipment as needed
Provide more money
Used Printer / Copier Company