Individual programme management has improved, but there has been no progress on techniques for assessing the impact of a portfolio of programmes and their alignment with agency strategie
Trang 1in the US federal government
A report from the Economist Intelligence Unit
Sponsored by Oracle
Trang 2Preface 3
Contents
Trang 3Creating value in the public sector: Intelligent project selection in the US federal government is an Economist
Intelligence Unit research report, sponsored by Oracle The fi ndings and views expressed in the report
do not necessarily refl ect the views of the sponsor The author was Brian Robinson Mike Kenny was responsible for the design
April 2011
Trang 4Executive summary
US federal agencies have been under pressure for years to improve the way they select and prioritise the programmes they manage, with successive administrations and Congress beating the effi ciency drum Government budgets threaten deep cuts, and that pressure will increase Most agencies are not where they need to be to meet these demands Individual programme management has improved, but there has been no progress on techniques for assessing the impact of a portfolio of programmes and their alignment with agency strategies and goals Evaluation practices have not kept pace, and programmes have fallen through the cracks Ineffective programmes continue to run seemingly under their own momentum, with scant justifi cation of their effi cacy
New requirements will ratchet the pressure even higher The Obama administration’s Accountable Government Initiative will require agencies to identify their worst-performing projects, and weed out the least critical A Government Accountability Offi ce (GAO) report released in March detailed overlaps and duplications in hundreds of government programmes Congress will undoubtedly use these fi ndings
to cut billions of dollars from agency spending Meanwhile, in line with the enactment of the revamped Government Performance and Results Act (GPRA) in 2010, agencies now have to link their programme evaluation and selection more closely to annual performance plans and strategy goals
The government is not a monolith, and each agency has its own culture and unique set of stakeholders
No one template can provide an answer for all government agencies, but there are common approaches that can improve the performance of most programmes:
l Take a holistic approach to programme evaluation New programmes cannot be considered without
knowing how they fi t with existing ones, how they will operate and what they will cost This portfolio-based approach provides the best way to gain a holistic view of agency needs
l Build a feedback loop into the evaluation process Agencies will need the ability to redefi ne their
planning continually, instead of only at the beginning of each budget cycle, in order to adjust the mix
of programmes in their portfolio more quickly to changes imposed by overall demands on agencies and subsequent changes in strategies
l Make sure there is a clear prioritisation of programmes Know which programmes are vital to
maintain the agency’s mission and which are less so Build this into the agency’s operating plan so that budgets can be reallocated across the portfolio of programmes as needed to make sure the needs
of those with the highest priorities are met
l Assume the worst, and plan accordingly While the budgets for certain individual programmes may
rise, most agency budgets overall will drop substantially over the next few years Planning for that eventuality will require a robust process for evaluating programmes across the enterprise, and how they link with agency strategies and goals
Trang 5These are not the best of times for government With a federal budget defi cit projected to be US$1.6trn
by the end of fi scal year 2011 (the federal government fi scal year runs from October 1st to September 30th), the administration of Barack Obama has called for a fi ve-year freeze on government spending, while Republicans in Congress have pushed for deep cuts What is certain is that most agencies will have to
do their work with fewer resources
In addition to these cuts, there will be an even sharper focus on how agencies select and implement programmes At the beginning of March the Government Accountability Offi ce (GAO), the investigative arm of Congress, released the fi rst of a series of congressionally mandated annual reports identifying which federal programmes, agency offi ces and initiatives have duplicative goals or activities.1 If Congress acts on these fi ndings, it could cut billions of dollars from agency budgets
The report found 34 areas of government where the objectives overlapped, provided similar services
to the same sectors of the population, or where missions were fragmented across multiple agencies
or programmes It also identifi ed 47 areas where costs could be reduced, or extra revenue could be
obtained (see box Improving the US food safety system) Overall, the GAO’s fi ndings spanned hundreds of
programmes, and touched nearly all the major federal departments and agencies
At the same time, agencies are also under pressure from the Obama administration “to make government work better, faster and more effi ciently”, by scrutinising more carefully which programmes to implement, and then providing a better evaluation of the effectiveness of these programmes
One goal of the president’s Accountable Government Initiative, clearly, is to identify the lowest-priority and worst-performing government programmes All agencies have to take a hard look at their spending in order to weed out the initiatives that are the least critical to their missions—in turn shifting the focus to how they evaluate programmes
Just before he left his post as director of the Offi ce of Management and Budget (OMB) at the end of July 2010, Peter Orszag sent a memo to federal agency heads pointing out that rigorous programme evaluations can be key to determining whether they are achieving their purpose at the lowest cost
“Some programmes have persisted year after year without adequate evidence that they work,” he wrote (The OMB is part of the Executive Offi ce of the President, and its core mission is to help a wide range of executive departments and agencies across the federal government to implement the commitments and priorities of the president.)
Government has done a good job in recent years with such things as performance measurement and
Introduction
1 Government
Accountability Office,
Opportunities to Reduce
Potential Duplication in
Government Programs, Save
Tax Dollars, and Enhance
Revenue, March 1st 2011.
Trang 6individual programme management, according to Jon Desenberg, policy director for The Performance Institute, a think tank based in Washington, DC Nevertheless, offi cials “haven’t taken that to the next level, especially with things such as portfolio management”, he says
Although government is doing a much more effective job on managing individual programmes, what
is missing in many agencies is the link to a broader strategic outlook, and a better way to prioritise programmes to fi t with that outlook
Improving the US food safety system
One of the most important areas where the federal government adds
value for American citizens is in overseeing the safety of the nation’s
food system It is even more important now given that a much greater
portion of the US food supply is imported, as raw and unprocessed
foods become more popular, and with the growth of sections of the
population that are susceptible to food-borne illnesses
This is the reason that the Government Accountability Offi ce (GAO)
chose the issue as an example of wayward government efforts in its
March 2011 report on Opportunities to Reduce Potential Duplication
in Government Programs, Save Tax Dollars, and Enhance Revenue The
fragmented nature of federal food oversight programmes has caused
inconsistent oversight, ineffective co-ordination and ineffi cient use
of resources, according to the GAO
“Without a government-wide performance plan for food safety,
decision-makers do not have a comprehensive picture of the federal
government’s performance on this cross-cutting issue,” it noted
Responsibility for food safety lies primarily with the Food and Drug
Administration (FDA) and the Food Safety and Inspection Service
(FSIS) of the US Department of Agriculture (USDA) Together, these
two agencies operate a US$2.5bn food safety budget, but a total of 15 federal agencies together administer at least 30 food-related laws This can lead to some bizarre situations For example, the FDA is responsible for the safety and proper labelling of eggshells at the farms where the eggs are produced, whereas the FSIS is responsible for the safety of eggs processed into egg products Meanwhile, other USDA agencies are responsible for setting quality and grade standards for eggs, and for ensuring the health of young chicks supplied to egg farms
Meanwhile, it is unclear who is responsible for actually testing eggs for such things as salmonella In 2010 there was nationwide recall of 500 million eggs because of salmonella contamination
As early as 2004, the GAO reported that integrating food safety oversight could create economies of scale, and made a more concentrated effort to protect the food supply In 2007 it made its
fi rst call for a mission-based, government-wide performance plan focused on results
Although the GAO does not expect reducing fragmentation in food safety oversight to result in signifi cant cost savings, new costs could be avoided This might be an important point going forward, however, since both the FDA and USDA budgets are under pressure in Congress because of the ongoing fi scal crisis
Trang 7Some agencies have become practiced at evaluating proposals for the programmes they want to implement A January 2011 report by the GAO2 found that agencies with the most mature evaluation processes have a consistent approach, from initial consultation with a variety of stakeholders and feedback from senior offi cials to a formal review and approval process
This approach also fi ts well with the ability to take an enterprise-wide look at agency programmes, to see how that portfolio matches up with the longer-term strategic goals By identifying how programmes relate to each other and to those goals, agencies can decide on the optimal mix of programmes needed to meet those strategic targets, and what resources need to be shifted among them to make sure the entire portfolio of programmes is appropriately balanced
The problem with all but the smallest agencies is the diversity of stakeholders whose input has to be considered in any programme discussions At the National Aeronautics and Space Administration (NASA), for example, there are fi ve major lines of business, each of which has several themes that may need their own programmes
The senior leadership at the agency keeps on top of things with reviews of the programme portfolios of each business line “roughly quarterly,” says Dr Michael Hawes, associate administrator in NASA’s Offi ce
of Independent Program & Cost Evaluation Then, at the beginning of each year’s budget cycle, a broader portfolio review is done for the entire agency to see how programmes are developing and which might need adjustment
The National Oceanographic & Atmospheric Administration (NOAA) also provides programmes for several lines of business It uses two key documents – a strategic plan and a business unit implementation plan – to guide its programme evaluation and selection Previously, it used a two-step planning process: the fi rst step was based on the perfect scenario in which all the requirements could be met with no constraints assumed, while the second step added the constraints Now it follows a planning process that includes fi scal constraints from the beginning
Based on the budgets enacted by Congress, the executive team now has a much clearer idea of what
is possible in terms of its overall portfolio of programmes “Before, it was very diffi cult to track decisions over time in terms of the implementation of strategies,” says Paul Doremus, director of strategic planning
in NOAA’s Offi ce of Program Planning and Integration “Now we have a much tighter linkage between strategic intent and what we can actually resource.”
Identifying the right projects
2 Government
Accountability Office,
Program Evaluation:
Experienced Agencies
Follow a Similar Model
for Prioritizing Research,
January 2011.
Trang 8No decision to begin a new programme is taken in isolation by any government agency Most of them have legacy programmes that need to be funded and resourced, so knowing the matrix of programmes in an agency is key to the decision-making process Good portfolio management is an essential step to better programme selection and prioritisation Without it, agencies have no holistic view
of their strategy and mission, and how each programme (existing or proposed) fi ts into “the big picture” The Offi ce of Environmental Management in the Department of Energy (DOE), for example, is
responsible for cleaning up the radioactive sites in the United States and around the world that are
a legacy of the cold war arms race Programmatically, it is one of the most complex endeavours in government
The clean-up is already 20 years old and has many years still to go Each of the clean-up sites sets up its own baseline needs, but because of the schedules for clean-up and movement of nuclear waste around the country, there is a certain interdependency of needs All of that information feeds into a database that is used by executives at the Offi ce of Environmental Management headquarters to prioritise which programmes to fund based on maximising compliance and clean-up “We think we have a good planning basis,” says Merle Sykes, the Offi ce of Environmental Management’s chief business offi cer (see case study
Nuclear clean-up—planning for the long term) “We know what our costs are on a continuing basis, so we
feel pretty confi dent in that.”
NASA has a similar long-term outlook, if not the same kind of interdependency The Science Mission Directorate alone has around 50 satellites operating in space, many of them with multi-decade lifetimes Each of them has a cost that has to be factored into deliberations about which programmes to continue funding, and which programmes to begin funding
The portfolio reviews undertaken by the agency’s senior leadership give them a good understanding of how each programme is performing, and the level of its operational constraints “We need that to assess the kind of fi xed operating space we have, and what the challenges are in the development of ongoing projects,” says Dr Hawes “Then we can consider what room we have for new missions.”
He believes that strengthening this kind of portfolio approach to gain the most holistic view is important Frequently, attention is driven towards the more unusual and visible projects However, considering the portfolio as a whole allows the agency to factor the broader risks into the budget, to understand the common drivers of cost and to plan for growth
That holistic view is also critical to the way NOAA operates It has “major mission goals” in the
Balancing project portfolios
Trang 9areas of weather, climate, oceans and coasts, says Mr Doremus, with line offi ces responsible for the implementation of those goals, “while acknowledging that the implementation requires capabilities from across the organisation.”
So, when it comes to planning at NOAA and ensuring that this portfolio view is available, each of those lines of business also has to be able to show what the interdependencies are across the organisation, and with external partners
“Each of the objectives in the strategic plan identify the capabilities that are required across the organization as well as, sometimes, what’s needed from the outside,” says Mr Doremus “Those are built into a logic model that shows us how the components work together over time, so we can integrate complementary programmes and avoid redundancies.”
CASE STUDY:
Nuclear clean-up—planning for the long term
The Offi ce of Environmental Management at the Department of Energy
(DOE) is charged with cleaning up the environmental waste produced
by 50 years of nuclear weapons development and energy research It
runs dozens of construction and clean-up projects in multiple states
valued at a total lifecycle cost of over US$200bn Scrutiny on its work
will no doubt intensify in the wake of the Japanese nuclear crisis as
public concern over nuclear projects reawakens
The Department is currently operating under a fi ve-year plan that
runs until fi scal year 2012 (October 2011 to September 2012) A
major strategic goal under the plan is to complete the clean-up of 95
contaminated geographical sites by the end of 2012 There is some
fl exibility for changes to the clean-up schedule, but the DOE is liable
for fi nes, penalties and other regulatory action if it strays too far
Accordingly, precise programme evaluation and planning is vital,
and in fact an increased attention to programme management was
a specifi c feature of the fi ve-year plan Each site operates under its
own funding profi le and determines what it needs for clean-up Such
calculations include assumptions relating to funding that are then
included in the agency’s overall fi nancial statement At the same
time, there is a certain amount of interdependency between sites that
must be taken into account, particularly when it comes to shipping
waste “Obviously, everyone can’t ship on the same day, so we have
to make sure that sequencing makes sense,” says Merle Sykes, chief business offi cer at the Offi ce of Environmental Management “Also, there’s an optimum way to fi ll up [the waste depository], so there’s a certain sequencing there you have to accomplish.”
The focus of the Offi ce of Environmental Management’s planning activities is what Ms Sykes calls an integrated priority list Each site uploads its planned activities into a central database, and that list
is used at headquarters to decide which particular projects might require more money
Factors that affect prioritisation include such things as how to maximise regulatory compliance, how to get the most clean-up done for the money and how to manage resources for disposal It
is a mature process, since the agency has been at this for 20 years already But surprises are still possible For example, the agency had been working on the assumption that it would be funded at the same level as fi scal 2010, but there has been talk of cutting it back to 2008 levels “That would have a substantial impact for us,” Ms Sykes says
“We try to hold back, but as the continuing resolution debate drags
on, that’s sometimes not possible We can talk about lay-offs if we get cut, or about curtailing activities, but it’s not precise.”
The saving grace is the planning and evaluation process that the Offi ce of Environmental Management has put in place, and its years
of experience, particularly with regard to costs Even though this is a
“very, very diffi cult year”, Ms Sykes believes that her organisation is
in a good position to weather it
Trang 10All decisions about government programmes are resource-dependent, so what guidance agencies and programme planners can provide about available resources will ultimately drive the fi nal decision on what programmes to develop and what to do without Sometimes that has to do with people, sometimes it
is the time available in which to implement the programmes Currently, funding is by far the biggest driver The question is how to factor resource constraints into the decision-making process For the current
fi scal year planning, well before the current budget debates began, NOAA told its business units to plan as though resources would not increase at all, based on the fi scal trends that seemed to be developing That turned out to have been good guidance, Mr Doremus says, “if not optimistic”
Other organisations try to get ahead by incorporating fl exibility into their upfront planning The Department of Veterans Affairs (VA), for example, is neck deep in new and ongoing information technology (IT) programmes that are needed to upgrade the services it provides to military veterans To make sure that the overall intent of those programmes is not compromised, IT operations at the VA work according to a prioritised operating plan
Each of the 1,100 programmes in the plan has a certain dollar amount attached to it that is considered the minimum needed to move that programme forward If the VA is faced with a reduced budget, it knows how to reallocate funding in such a way as to keep the maximum number of programmes going while factoring in the relative priorities of each project “Any good, well-disciplined organisation knows what it needs in the way of prioritisation,” says Roger Baker, the VA’s chief information offi cer “In the VA, it’s the operations of its hospitals and clinics, and what goes through the benefi ts offi ce.”
The potential funding gap raises a question mark over everything to do with federal programme evaluations, notes George Grob, a former director of planning and policy at the Department of Health and Human Services, and now president of the Virginia-based Center for Public Program Evaluation “The political process says evaluation has to be a part of the DNA of programmes, but for that you need resources,” he says
“The mindset of Congress now is to cut the budget, so where will the funding come from?”
It is a diffi cult process, acknowledges Mr Hawes of NASA NASA usually has very bipartisan support in Congress, which is a huge advantage when it comes to programme planning “because we don’t swing
as widely as some do with the change in political parties and changes in Congress” But both parties are focused on the fi nancial environment now “and we will not be immune to that in any way”, he says “So
we need to look ahead and at those issues, which will be refl ected in whether or not we can inject new programmes into the portfolio.”
Selecting and managing resources