Electricity Regulatory Authority of Vietnam ERAV Electricity Regulatory Authority of Vietnam Contents Section 1 - Vietnam power sector overview Section 2 - Power sector development s
Trang 1Electricity Regulatory Authority of Vietnam
POWER MARKET DEVELOPMENTS
IN VIETNAM
18 October, 2010
Trang 2Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam Contents
Section 1 - Vietnam power sector overview
Section 2 - Power sector development strategies Section 3: Competitiveness and affordability
2
Trang 3Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam 1.1 Existing National Grid
As at 2009
1 Generation Capacity: 18,268 MW Generation: 84,750 GWh Consumption: 74,761 GWh
• Coal and oil thermal: 20.9% 3,812 MW
• Gas turbine (CCGT): 36.9% 6,747 MW
• Diesel and small hydro: 2.6% 461 MW
• Import from China: 3.8% 700 MW
2 Total length of lines:
• 500 kV: 3,410 km 8,814 MVA
• 220 kV: 5,602 km 15,440 MVA
• 110 kV: 12,448 km 21,314 MVA
• 6-35 kV: 135,371 km 39,804 MVA
• LV: 240,424 km
3
Section 1: Power sector overview
Trang 4Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam 1.2 Supply and Demand
4
Consumption growth rate: 14%/year Installed capacity growth rate: 12%/year
21526 23484
26457
30423
35715
40590
46226
51854
58781
66612 74197
17725 19592
22397
25752
30228
34835
39596.2
44860.1
51295.5
58438.2
65880
0 5,000 10,000 15,000 20,000 25,000 30,000
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
Year
0 10000 20000 30000 40000 50000 60000 70000 80000
Import from China Diesel and small hydro
Gas turbine
Oil
Coal
Hydro Electricity sale,
GWh
Capacity, generation and consumption from 1998-2009
Generated, GWh
Section 1: Power sector overview
90000 35,000
74761 84750
2009
Trang 5Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam
Total installed capacity planned to 2020
- Growth rate: 15% (based case), Total capacity/Peak demand:
2010 : 21,400 / 16,000 (MW).
2015 : 55,500 / 29,500 (MW).
2020 : 107,300 / 54,400 (MW).
- Additional generation: 40,000 MW in 2009-2015; 52,000 MW in 2016- 2020
0 20000 40000 60000 80000 100000 120000 140000
2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
MW
Import Small hydro and renewable energy Gas turbine and oil
Coal Hydro and pump storage Pmax
5
1.3 Power Development Plan (Master Plan 6) Section 1: Power sector overview
Trang 6Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam
Current power sector structure: Vertically integrated
EVN is holding company for:
• Generation: equitized (EVN holds majority) or subsidiary power
plants account for 68% of installed capacity
• Scheduling and dispatching: dependent accounting unit
• Transmission: dependent accounting unit
• Distribution: 5 independent accounting companies
6
Power Compani es (5 PCs)
Power Compani es (5 PCs)
National Power Transmiss ion Corporati
on (NPT)
National Power Transmiss ion Corporati
on (NPT)
National Load Dispatch Center (NLDC)
National Load Dispatch Center (NLDC)
BOTs and IPPs (32%)
BOTs and IPPs (32%)
Power plants under EVN (68%)
Power plants under EVN (68%)
Electric Power Trading Company (EPTC)
Electric Power Trading Company (EPTC)
EVN
RETAIL
TRANSMISSION, SCHEDULING AND DISPATCHING
1.4 Industry Structure Section 1: Power sector overview
Trang 7Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam
• Generation not keeping up with rapidly growing demand (~14% per annual).
• Reasons:
− Required investment in power sector, especially for generation, is far beyond EVN financial resource
− Electricity pricing is not transparent and not reflecting costs; low prices unattractive for investors
− The current vertically integrated structure cannot ensure generation investors confidence in a fair and efficient trading environment, fair and non discriminatory access to the grid, dispatch
− Lack of clear mechanism for PPAs leads to delays and inefficiencies in negotiations and pricing, and lack of clear mechanisms for other
generation investors PPAs to sell to EVN
7
1.5 Challenges Section 1: Power sector overview
Trang 8Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam Contents
Section 1 - Vietnam power sector overview
Section 2 - Power sector development strategies
Section 3: Competitiveness and affordability
8
Trang 9Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam
1 Electricity Law (2005) stipulates:
− Diversification in power sector investments, allowing participation of all economic sectors
− Introduction of power market, step-by-step development of competitive generation, wholesale competitive, and retail competitive markets
2 Power sector administration:
− Ministry of Industry and Trade (MOIT) is the sector’s policy maker
− Electricity Regulatory Authority of Vietnam (ERAV): Established in 10/2005 as an entity under MOIT, to conduct:
Development and regulation of power markets
Economic regulation (electricity pricing)
Monitoring supply/demand balance to promote security, efficiency
and conservation
Licensing and Dispute resolution
ERAV is the first and only infrastructure dedicated economic
regulator in Vietnam
9
2.1 Legal Framework Section 2 - Sector development strategies
Trang 10Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam
Competitive Generation
Market (VCGM)
Competitive Generation
Market (VCGM)
Electricity Wholesale Market Electricity Retail Market
Pilot Operation
Full Operation
Pilot Operation
Full Operation
Pilot Operation
Full Operation
The preparation for the Competitive Power Market (CGM) is now in
progress and conducted by ERAV
2.2 Power Market Development Roadmap Section 2 - Sector development strategies
Trang 11Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam
• A cost-based pool (CBP) design has been selected as providing the best balance between the objectives of:
o attracting investments
o assuring power supplies and retail tariff stability
o increasing competition and transparency in the power market
o the CBP design draws on the experience of EVN’s pilot power market
• A single buyer (part of EVN) purchases all generation
• The CBP comprises a gross pool, with hourly clearing and day-ahead bidding Major features are:
o thermal generators are subject to a bid cap equal to variable costs
o hydro generators are subject to a bid cap in a range around their water value (calculated by the system and market operator, SMO)
o a market-clearing price (system marginal price, SMP) is set on an ex-post basis using an unconstrained schedule
o contracts for differences are used, initially covering up to 90% of expected output, to stabilise prices for generators and customers
11
2.3 VCGM design Section 2 - Sector development strategies
Trang 12Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam 2.4 VCGM structure
Section 2 - Sector development strategies
Trang 13Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam
PARTICIPANTS
NON-PARTICIPANTS
SERVICE PROVIDERS
MDMSP
SMO
TNO
Non-BOT TPPs HPPs
SMHPs
FSR/CSR/
RMR
INDIRECT TRADING GENERATORS DIRECT TRADING GENERATORS
Exports
BOTs Imports
SPPs (<30 MW)
SPPs (<30 MW)
SINGLE BUYER (Electricity Power Trading
Company)
SINGLE BUYER (Electricity Power Trading
Company)
PCs Customers
2.5 VCGM participants Section 2 - Sector development strategies
Trang 14Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam
in the schedule plus a margin, in each daylight hour
o the payment is calculated to cover the fixed costs of a new thermal generator that are not recovered from the energy market
which determine sites, size and fuel for new generators
o ERAV is responsible for advising on updates to the master plan and for approving ranges for generation prices to be negotiated by the single buyer
PPAs covering all output Existing PPAs are not affected by the CGM
2.6 Investment and cost recovery in VCGM Section 2 - Sector development strategies
Trang 15Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam
15
2.7 VCGM implementation plan Section 2 - Sector development strategies
to a number of independent generation companies and none of them owning more than 25% of total generation capacity.
operated
o test the market mechanisms, market rules and procedures
o identify and provide remedies to deficiencies
o test the market infrastructure and market systems prior to implementing the full market
o create an environment for members to learn, practise and develop their skills for participation in the competitive market
VCGM starting late-2011
Trang 16Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam Contents
Section 1 - Vietnam power sector overview Section 2 - Power sector development strategies
Section 3: Competitiveness and affordability
16
Trang 17Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam 3.1 Tariff Reforms
- a uniform national residential tariff, with PCs paying different
bulk supply tariffs (BSTs) according to their costs of service
- maintaining affordability of tariffs for smaller residential
customers through cross-subsidies
- increase in average tariff levels of 8.92% (to 5.5 USc/kWh)
- harmonisation of residential tariffs for customers served by
PCs and by local distribution utilities (LDUs) in rural areas
- revisions to the rising block structure for residential tariffs with
the first block (up to 50 kWh) being charged a tariff set at 60-65% of the average rate
- gradual elimination of cross-subsidies over 5-6 years, by
increasing industrial and commercial tariffs more slowly than residential tariffs
- tariffs are revised annually reflecting changes in the cost
chain elements The proposal for 2010 has been submitted to the Government for review and approval
17
Section 3: Competitiveness and affordability
Trang 18Electricity Regulatory
Authority of Vietnam
ERAV
Electricity Regulatory
Authority of Vietnam 3.2 Market-Based Competitive Pricing
transparency in generation pricing
reforms are planned to increase competitiveness
- industrial and commercial tariffs will become a cap, with PCs being able to negotiate lower tariffs
- the current cross-subsidy for households in the first consumption block will be converted into a rebate on electricity bills
- the national uniform tariff may be limited to residential customers only It will continue to be applied through a differential Bulk Supply Tariff charged from the single buyer to PCs
- the automatic indexation of tariffs to changing costs is being considered
Section 3: Competitiveness and affordability
Trang 19Electricity Regulatory Authority of Vietnam
19
THANK YOU FOR YOUR ATTENTION !!!