Investment decisions and the cost of capital tài liệu, giáo án, bài giảng , luận văn, luận án, đồ án, bài tập lớn về tất...
Trang 1MANAGERIAL ECONOMICS
An Analysis of Business Issues
Howard Davies and Pun-Lee Lam
Trang 3Capital and Capital Budgeting
Capital:
is the stock of assets that will generate a
flow of income in the future.
Capital budgeting:
is the planning process for allocating all
expenditures that will have an expected
Trang 44 Investments for complying with government or
insurance-company safety or environmental
Trang 5Question for Discussion:
What are the factors you would consider when making a choice among different investment
projects?
1.
2.
3.
Question for Discussion:
What are the factors you would consider when making a choice among different investment
projects?
1.
2.
3.
Trang 6Simple Technique for Appraisal of
Investment
Simple Technique for Appraisal of
Investment
Payback-period criterion:
Payback period is the amount of time
sufficient to cover the initial cost of an
investment
But it ignores any returns accrue after the
pay-back period; ignores the pattern of
returns; ignores the time value (time cost)
of money.
Payback-period criterion:
Payback period is the amount of time
sufficient to cover the initial cost of an
investment
But it ignores any returns accrue after the
pay-back period; ignores the pattern of
returns; ignores the time value (time cost)
of money.
Trang 7Initial investment: $10 million
Payback-period?
If cash flow : $4 million per year
Payback-period?
Trang 8On the other hand, the process of discounting
or capitalization is to turn a future stream of
services or income into its equivalent present value When an expected future sum is turned into its equivalent present value, we say that it
is discounted or capitalized.
On the other hand, the process of discounting
or capitalization is to turn a future stream of
services or income into its equivalent present value When an expected future sum is turned into its equivalent present value, we say that it
is discounted or capitalized.
Trang 9The present value of a single future amount
In general, present value (PV) refers to the value
now of payments to be received in the future (I) The present value of I after n year at r is:
PV=
I (1+r) n
Trang 10Suppose we try to find the present value of a
single future amount of $121, to be received
after two years Since goods available in the
future are worth less than the same goods
available now, the future amount of $121 is
worth less than $121 at present Given the
market rate of interest of 10%, its present
value is: $121
(1+0.1) 2 = $100
This means that the future amount of $121 (to
be received after two years) is equivalent to a
value of $100 at present.
Trang 11Simple Technique for Appraisal of
Investment
Simple Technique for Appraisal of
Investment
Net-present-value technique:
Net present value (NPV) is the difference
between the present value of a future cash
flow and the initial cost of the investment
project; a firm should adopt a project if the expected NPV is positive.
Net-present-value technique:
Net present value (NPV) is the difference
between the present value of a future cash
flow and the initial cost of the investment
project; a firm should adopt a project if the expected NPV is positive.
Trang 12NPV = -P + I 0 + I 1
(1+r)
I 2 (1+r) 2 + … + + (1+r) I n n
NPV = -P + I
r
where:
P: =capital cost, accruing in full at the
beginning of the project
I 1,2,…n =net cash flows arising from the project
in years 1 to n
or
Trang 13Simple Technique for Appraisal of
Investment
Simple Technique for Appraisal of
Investment
Internal-rate-of-return method:
Internal rate of return (IRR) is the rate of
return that will equate the present value of
a multi-year cash flow with the cost of
investing in a project
Internal-rate-of-return method:
Internal rate of return (IRR) is the rate of
return that will equate the present value of
a multi-year cash flow with the cost of
investing in a project
Trang 14P, n and the expected future cash returns (I) are known, we try to find IRR.
If the IRR is greater than the market rate of
interest r, it implies that the present value of the capital good (PV) is greater than its purchase
price (P) and the firm should invest Conversely,
if IRR is smaller than r, it implies that PV is
smaller than P and the firm should not invest.
P, n and the expected future cash returns (I) are known, we try to find IRR.
If the IRR is greater than the market rate of
interest r, it implies that the present value of the capital good (PV) is greater than its purchase
price (P) and the firm should invest Conversely,
if IRR is smaller than r, it implies that PV is
smaller than P and the firm should not invest.
What are the differences between NPV
technique and IRR method?
Trang 15In most situations, the IRR method will yield
the same results as the NPV method But:
•there may be more than one value for the IRR that
satisfies the NPV equation; if the sign of cash flows
changes more than once in the life of the project,
there may be multiple solutions
•the NPV rule uses actual opportunity cost of capital
as the discount rate; the IRR rule assumes the
shareholders can invest at the IRR
•IRR is expressed in terms of a percentage rate of
In most situations, the IRR method will yield
the same results as the NPV method But:
•there may be more than one value for the IRR that
satisfies the NPV equation; if the sign of cash flows
changes more than once in the life of the project,
there may be multiple solutions
•the NPV rule uses actual opportunity cost of capital
as the discount rate; the IRR rule assumes the
shareholders can invest at the IRR
•IRR is expressed in terms of a percentage rate of
Trang 16A firm will invest only if the expected rate
of return exceeds the cost of capital For a firm under rate-of-return regulation, if the permitted rate of return is set above the
cost of capital (or the required rate of
return), the firm will over-invest;
conversely, if the permitted rate is set
below the cost of capital, the firm will
under-invest.
A firm will invest only if the expected rate
of return exceeds the cost of capital For a firm under rate-of-return regulation, if the permitted rate of return is set above the
cost of capital (or the required rate of
return), the firm will over-invest;
conversely, if the permitted rate is set
below the cost of capital, the firm will
under-invest.
The Cost of Capital
Trang 17Weighted Average Cost of Capital (WACC):
Cost of debt (rd): interest rate paid to creditors net of taxes
Cost of equity (re): rate of return to shareholders in order to induce them to invest in the firm
WACC : rd × + re D × E
Trang 18•there are no taxes
•the capital market is efficient and competitive
•there are no transaction costs
•there are no costs associated with bankruptcy
•shareholders can borrow on the same terms as
corporations
•the cost of debt is constant, whatever the level of
Trang 19•If they were not the same, investors could improve
their position by “arbitrage”, selling the shares of one and buying shares in the other, which would alter the relative prices of shars until the WACCs become equal
Trang 20The Cost of Equity Capital
The Cost of Equity Capital
1 Dividend valuation approach DVA
(or dividend growth/discounted cash flow model ):
Rate of return = Dividend/Price + Expected
growth rate
re = D 1
P 0 + g The DVA relies on the equivalence of the market price of a stock, P 0 , with the present value of the dividends ( or cash flows) expected from the
stock The discount rate in finding the present
value is considered to be the cost of equity capital.
Trang 21There are few assumptions behind the method:
(a) future dividends are expected to grow at a constant rate perpetually;
(b) future dividends can be discounted at a
constant cost of equity capital;
(c) future dividends remain a constant
proportion of earnings over time;
Trang 22D 1 (1 + r) + (1 + r) 2 +
(1 + r) 3
D 1 (1+g) PV= D 1 (1+g)
2
+
Trang 23D 1 (1 + r)
Let A = Let B = (1 + r) (1 + g)
PV = A(1 + B + B 2 + …) (1)
× B on both sides:
PV × B = A(B + B 2 + B 3 + …) (2) (2) - (1):
PV(1 - B) = A
A (1 - B)
= 1
-=
=
(1 + r) (1 + g)
1 - B
Trang 24The Cost of Equity Capital
The Cost of Equity Capital
2 Capital asset pricing model (CAPM):
Cost of equity capital = risk-free rate +
beta (market rate - free rate)
Re = Rf + β (Rm - Rf)
Therefore, if we use the CAPM to estimate a
firm’s cost of equity capital (Re, or the required rate of return), we have to estimate a firm’s beta, the risk-free rate of return, and the market risk
premium (the difference between Rm and Rf).
Trang 25In the CAPM, the measure of market risk is
known as beta (β)
For example, the returns from an asset with a beta
of 0.5 will fluctuate by 5% for each 10%
fluctuation in the market’s returns
It has been shown that the required risk premium for an asset is directly proportional to its beta
Therefore, the holder of an asset with a beta of 0.5 will require a risk premium only half as large as
that offered by the market as a whole