This design for Camden Lock Village Phase 1 comprises a major new building along the Regents Canal at Chalk Farm Road: The canal building. This building comprises a new, 21st century re imagining of the street and canal levels, together with apartments on the upper levels
Trang 1Camden Lock Village Canal Building
Stage C report
25 October 2006
Trang 2Camden Lock Village - Canal Building
25 October 2006
Dear David and Piers,
We are delighted to present our stage C report for the Camden Lock Village Canal Building The illustrated scheme has been developed and co-ordinated with your other appointed design team, together with yourselves, and represents what was shown to Camden earlier this month We believe the design is in a robust condition to move forward to the next stages
Trang 3This design for Camden Lock Village Phase 1
comprises a major new building along the Regent’s Canal at Chalk Farm Road: The Canal Building
This building comprises a new, 21st century
re-imagining of the existing successful markets at
the street and canal levels, together with
apartments on the upper levels.
The building opens up the currently impenetrable site Public routes and spaces alongside the canal are created, together with a new route adjacent to the railway arches, which are themselves re-
modelled and restored.
Public terraces at the intermediate levels offer
new access for dining and relaxation These are
linked via a grand public ramp, enabling all the
floors to be reached seamlessly.
This design offers an exciting and important new development in the regeneration of Camden.
Trang 4Site location within Camden Town Centre 10
The site: relationship to the town centre 12
Development within Regent’s Canal conservation area 16
Optimization of areas: June to September 2006 40
Chalk Farm Road public roof terrace 84
Trang 501
Trang 6Brief History of the site
This is a triangular site, bounded on the northwest by the
railway, to the southwest by Chalk Farm Road and to the
south by the Canal.
There are currently nine buildings along the Chalk Farm Road
boundary, numbers 1- 9 Number 7-8 is a public house
currently called the Camden Rock Café, but previously, and
for the majority of its life, known as the Carnarvon Castle
This row of properties was previously known as Frances
Terrace, and the map regression suggests that they were
built in 1841 The road was renamed and renumbered in 1863,
with no 2 Frances Terrace becoming 7-8 Chalk Farm Road.
The 1870-3 OS map indicates the presence of a pub on this
site and the rate books and census returns for the 1860s
indicate that this was called the Pickford Arms By 1874 it had
changed its name to the Carnarvon Castle and drainage
records dated 1874 from LB Camden suggest that this was a
new building by an unnamed architect on the same site
Drainage records for the remaining terrace of houses to the
right of the Carnarvon Castle indicate that these have been
extensively rebuilt and that substantial alterations have
been made to plan form, use and finishes.
The only other building(s) on the site is a clearly marked canal
facility which existed as early as 1834, and can clearly be seen
in the very centre of the study area in each of the maps, until
the present-day OS map 2006 Aerial photography shows the
site at present to be a car park and there appears to be no
standing remains of this element of the site’s history.
1870-73 OS Map, showing the existence of the buildings on Chalk Farm Road (including the Carnarvon Castle Pub) The red line indicates part of the Phase 1 proposed development
1834 Parish Map of St Pancras - area near canal has not been developed
Site history
Trang 7Kentish Town
Chalk Farm Road
Camden High Street
Mornington Crescent
Kentish Town
Hampstead / the North
Chalk Farm Road Kentish
Camden High Street
West End
The site: relationship to the town centre
The site is located at the heart of the existing markets and borders on the North edge of Camden’s shopping centre.
Therefore it is important that the design does not destroy the character
of the markets, but fosters them and celebrates its unique characteristics.
The site is easily accessible by public transport.
Trang 810 11
14
13
12 15
16
17 18
1 Residential Development
2 The Roundhouse
3 Stables Market, Buildings A & B
4 Henson’s Mixed Use Scheme
5 Camden Lock Middle Market
6 35 Oval Road
Completed developmentCurrently being implementedPotential development site
17 Stables Market, Building C
18 Stables Market, Building D
Within the conservation area some of the old industrial sites have become available for development:
the completed sites are shown in green, those currently being implemented in magenta and potential sites are shown in yellow.
to King’s Cross
Improvements to Silver Link Line
- doubling capacity
Metropolitan Walks and green chain
Camden Road Station
Cross river tram terminus
NORTH LITTLE VENICE
hampstead road lock
Camden Town
Angel
city road lock
city road basin
wenlock basin REGENT’S PARK
bottle bridge tunnel cumberland arm
maida hill tunnel
RIVER THAMES
DLR
kentish town lock hawley lock
saint pancras basin saint pancras lock
kingsland basin
islington tunnel
limehouse tide lock commercial road lock salmon’s lane lock johnson’s lock
limehouse basin
sturt’s lock
old ford lock
mile end lock VICTORIA PARK
PADDINGTON BASIN
acton’s lock
The Regent’s Canal
Camden Road Station is within a 5
minute walk from the site
Improvements to the Silver Link Line
will double its capacity.
With the Metropolitan Walk running
along the canal there lies a great
opportunity in developing the site as
part of the green chain.
Links to public transport
Trang 9Camden LockMiddle Market Chalk
Farm Road
Kentish
Town Road
Stables Market
Clarence Way Estate
Hawle
y Road Playground
and Community Centre
Phase 1Phase 2
The site and its environs
Shown in red is the boundary of Phase 1, comprising of the Torbay street development to the North of the railway arches and the Canal building along the Regent’s Canal.
The Regent’s Canal conservation area
Development within the Regent’s Canal conservation area
Suffolk Wharf & 32-36 Jamestown Rd Gilbeys Warehouse
Camden Lock Middle Market Gilbeys Warehouse
Trang 10Low density underdeveloped site
The site is currently underdeveloped
because of its historical use The
primary activity is the Canal market as
well as the shops within the Victorian
terraces along Chalk Farm Road
Currently the potential of the site is
restricted due to the lack of access and
routes into the site.
Currently no public access to the canal
is provided from Chalk Farm Road.
The market is accessed through a steeply sloping claustrophobic tunnel.
The original facade of the terrace is affected by a significant amount of additions.
Chalk Farm Road frontage
Trang 11There is no direct access from Chalk Farm Road down to
the canal side.
An iron fence separates the Canal market from the
quayside As a result the canal side is deserted in sharp
contrast to Camden Lock Middle Market, just the other
side of Chalk Farm Road.
•
•
Visualisation of arches adjacent to buildings A + B
Currently the railway arches to the North of the site are largely hidden and their potential unfulfilled.
no access to and no relationship with canal
C
halk F
armo ad
Canal sit e
animated, strong relationship with canal
Trang 12Within Camden’s UDP the scheme
responds to the Regent’s Canal area
of special character, the conservation
area.
The Parliament Hill - Palace of
Westminster view cone wider context
clips the western edges of the site
Camden’s UDP has designated the site
for mixed use residential and retail
development.
Key UDP designations
wider context
Trang 1302
Trang 14Maximise views outwards to the surroundings.
by the canal.
• Increase permeability across the site, create new public routes
•
MTV studios
Ambitions
Trang 15to Camden Rd Station
Link to Metropolitan Walk
The masterplan generates clearly definable plots and creates a network
of public routes through the site extending westwards towards Stables Market, eastwards towards Camden Road station and northwards towards a re-modelled Hawley Road garden and the established Metropolitan Walk.
On the Canal Market site a new building fronts the canal and Chalk Farm Road
It acts as a gateway into the heart of the development.
Hawley Rd Garden
Trang 16Development of the
Canal Building:
April - September 2006
03
Trang 17First floor: Retail restaurants and terrace
Second floor: restaurants and terrace
Third floor: restaurants and residential
April 2006
The curved form of the building draws people in and through to the site beyond
At first floor a public dining terrace fronts onto Chalk Farm Road Within the building a series of ramps connects the various levels, offering ease of movement and mitigating the requirement for stairs and escalators.
Trang 18A ramp creates a clear pedestrian
connection between Chalk Farm Road
and the quay.
Trang 19The public roof terrace on second floor with various types of
restaurants and small food units will form a destination
point
Different options were investigated to optimise the size of
enclosed area in relation to open spaces
Trang 20Although the floor plates are staggered
to follow the ramped circulation system the structural grid is designed
to allow a variety of possible retail layouts
180: Camden: Canal Building
Schedule of areas 05.07.2006
Floor Anchor R1 indoor R1 outdoor R2 indoor R2 outdoor R3 indoor R3 outdoor Footcourt
indoor
Footcourt outdoor
Staff Rooms Core/plant
Second - - - 1,440 640 5,870 1,600 3,230 4,270 - 1,350
First - 4,020 1,400 1,440 800 - - - 1,450
Upper Ground Floor 2,570 - - - 1,500
Lower Ground Floor 2,140 - - - 2,800
Basement 1 28,560 - - - 1,690
Basement 2 8,790 1,200 1,300 - 1,760 - - - 1,560 9,155
Total 42,060 5,220 1,400 4,180 1,440 7,630 1,600 3,230 4,270 1,560 17,945
Kitchen area 30% of indoor restaurant area
The client is advised to seek specialist advice with regard to the measurement of areas.
All areas are indicative only and should not be relied upon The areas given relate to the likely areas of the building at the current state of the design.
Any decisions to be made on the basis of these predictions, whether as to project viability, pre-letting, lease agreements or the like, should include due allowance for the increases and decreases inherent in the design development and building
processes.
Kitchen areas are located in the second
basement, with dumb waiters servicing
the finishing kitchens on the restaurant
levels
Trang 21residential would bring the total gross
area of the building from 189 000 sq ft
to 205 000 sq ft (incl 30 000 sq ft
residential)
Optimization of areas: June to September 2006
Planning meeting scheme Chalk Farm Rd view
Current scheme Chalk Farm Rd view
Extra floor schemeChalk Farm Rd view
Planning meeting scheme Camden Bridge view
Current scheme Camden Bridge view
Extra floor schemeCamden Bridge view
Planning meeting scheme Stables Market view
Current scheme Stables Market view
Extra floor schemeStables Market view
Base Scheme - Camden Bridge view
Chalk Farm Rd view Canal bridge view
Massing study development
Trang 22Retail Retail Retail within
arches
Anchor Store
Anchor Store
Anchor Store Retail Restaurant
Duplex Appartment
Two additional floors along the back and one along the
canal frontage
Increase of enclosed area on second floor by reducing
the size of canal facing terrace.
•
•
July 2006 September 2006
Development of sections
July 2006 September 2006
Trang 24Usage options analysis
04
Trang 25Option 1
Floors 2, 3, 4, 5 are residential Floors B2, B1, LG, UG, and 1 are mainly retail and restaurant
Option 2
Floors 3, 4, 5 are hotel Floors B2, B1, LG, UG, 1 and 2 are mainly retail and restaurant
Option 3
Floors 2, 3, 4, 5 are hotel Floors B2, B1, LG, UG, and 1 are mainly retail and restaurant
The client is advised to seek specialist advice with regard to the measurement of areas.
All areas are indicative only and should not be relied upon The areas given relate to the likely areas of the building at the current state of the design.
Any decisions to be made on the basis of these predictions, whether as to project viability, pre-letting, lease agreements or the like, should include due allowance for the increases and
On August 9th, 2006, Make, Davis Langdon and CBRE were at
the request of the client developing a study involving various
options to the upper floors 2, 3, 4 and 5 of the Canal Building
and specifically the valuation and cost model refers to which
of these performs the best.
This chapter details the findings of the study It has been
produced in collaboration with the appointed design team
and should be read in conjunction with Davis Langdon’s cost
and area schedule
The following options have formed the basis for this study:
Base scheme
Scheme as signed off in mid July.
Option 1
Floors 2, 3, 4 and 5 are residential
Floors B2, B1, LG, UG and 1 are mainly retail and
restaurant (for this option the sloping floors and ramps
stop on level 1)
Option 2
Floors 3, 4 and 5 are hotel
Floors B2, B1, LG, UG, 1 and 2 are mainly retail and
restaurant, though there will be a hotel presence at the
front on UG and a hotel-related restaurant and bar on
first and second.
Option 3
Floors 2, 3, 4 and 5 are hotel
Floors B2, B1, LG, UG and 1 are mainly retail and
restaurant, though there will be a hotel presence at the
front on UG and a hotel-related restaurant and bar on
Trang 26Indicative Rental Value psf
Indicative Yield
Completed Value psf Comments
Option 1& 2 Retail (2nd floor) 10 units £15.00-25.00 5.00% £275- £450
View based on traditional national multiple retailer, as opposed to market trader model Reduction of demand at upper levels
Degree of concern over saturation of retail accommodation in Camden
Option 1& 2 Restaurant Space (2nd Floor) 3 units £20.00-40.00 5.50% £300 - £500
Option 1 Residential (3rd floor - 5th
Lower value units to the rear; higher value overlook the lock Best local comparables include Star Wharf, Camden & Angel Wharf in Islington Estimate shows premium over these levels and assumes exclusively rivate units
Option 1A Residential (2nd floor) £500 - £700 Units with railway viaduct discounted
Option 3 Hotel (2nd floor) Total 85 - 110 rooms across
Based on £100,000 - £120,000 per room Quantum of available rooms would not appeal to a major luxury hotel brand Likely users wold be independent theme hotel or budget operator
Option 2 & 3 Hotel (3rd - 5th floors) Total 85 - 110 rooms across
Camden Lock Village, ‘Canal Building’ Upper Floor Scheme Options – Fire Safety Design Summary
The information below summarises the respective fire safety strategies which would be used to meet Building Regulation requirements depending on the use of the upper floors of the Canal Building:
leading directly to outside These routes would be separated from the non-residential accommodation by protected lobbies
Protected escape stairs and fire-fighting shafts to ground level leading directly to outside These routes would be separated from the non-residential accommodation by protected lobbies
Protected escape stairs and fire-fighting shafts to ground level leading directly to outside
evacuate upon fire alarm activation within the specific apartment
Further evacuation of other spaces would be possible, if necessary, following instructions from the attending Fire Service via a “full evacuation” control in the fire control centre
Simultaneous evacuation of the hotel upon fire alarm activation within the hotel
Further evacuation of other spaces would be possible,
if necessary, following instructions from the attending Fire Service via a “full evacuation” control in the fire control centre
Simultaneous evacuation of the entire building
Type LD3 fire alarm system The installed detectors will relay information to the landlord fire alarm panel indicating activation and mains failure of a particular unit Landlord-based detection will
be provided in the common areas of the residential building elements.
Category L2 fire alarm system designed, installed and maintained in accordance with BS 5839 part 1:2002 including a PAVA system (voice alarm)
Category L2 fire alarm system designed, installed and maintained
in accordance with BS 5839 part 1:2002 including a PAVA system (voice alarm)
No requirement for compartment floors or walls unless:
1 The building exceeds 30m in height > need compartment floors
2 a retail unit exceeds 4000m2 (assumed sprinkler protected)
on any single floor > need compartment walls
Following Section 20 guidance, smoke clearance would be needed
on every above-ground level, via either openable windows or by mechanical smoke extract system If natural ventilation is adopted each floor will need to be fitted with manually openable windows, totalling 2.5% of the floor area Any mechanical smoke extract system should be designed to achieve 6 air changes per hour
guidance, complying with BS 5306 part 2 or BSEN 12845
proposed, together with significant quantities of glazed façade
Trang 27Simone Gauss make SimoneGauss@makearchitects.com
Make Architects have requested that NDY provide a brief review of the principal services that are likely to
be applicable to levels 3, 4 and 5 if they are:-
a) Residential units
b) Hotel Accommodation The current design philosophy for the Canal Building assumes that the upper floors will be residential units The design philosophy would be as follows:-
is not included, but this will be considered as part of the overall review in order to achieve the 10%
renewable requirement
The heating pipework to each residential unit would be sized to satisfy heating and hot water service requirements Each residential unit would be individually metered to allow the landlord to recover energy usage costs
With a centralised heating plant solution, it is not anticipated that gas pipework would be provided to residential units, with electricity being used for cooking purposes
An alternative to this centralised solution could be localised gas fired boilers to each residential unit
These localised boilers would require individual gas supplies and these installations would provide the heat source for local hot water systems as well as local heating Individual metering of each residential unit gas supply would be required
Should cooling be required to residential units, this could be achieved by centralised chiller plant serving water–cooled fan coil units or by a ground source (geothermal) system from which water would be distributed to residential units to provide a heat sink for localised room cooling units Individual meters would be required to each residential unit connection This system could permit room units to provide
NORMAN DISNEY & YOUNG
3.00 Fire Services
The current fire strategy does not require fire protection services to the residential accommodation
An analogue addressable fire detection system would be provided in corridors, stairwells etc, however, supplemented by “domestic” detectors in residential units
4.00 Public Health Services
A centralised boosted cold water system shall provide potable cold water to each residential unit These supplies would each be sub-metered
Within each residential unit, cold water would be distributed to sanitary fixtures Hot water shall be derived from local calorifiers served by the primary heating system
5.00 Lift Services
The current proposal incorporates lifts that are allied to the cores serving residential accommodation
In the event that the upper floors provide hotel accommodation, the design philosophy would be as follows:-
1.00 Mechanical Services
Hotel rooms will almost certainly need cooling as well as heating and the centralised plant shall be procured accordingly Heating/cooling from room units would be provided Primary plant could be centralised boilers and chillers or ground source plant; the final solution be reviewed in consideration of GLA requirements The greater centralised HWS requirement would enhance the viability of CHP plant Supporting areas such as kitchens, toilets, staff accommodation etc would all require heating/cooling and ventilation The kitchens will require a gas supply These provisions will increase plant requirements above those of a residential scheme
2.00 Electrical Services
The hotel accommodation could be served from a dedicated HV meter and dedicated sub-station (dependant upon load) with sub-main distribution, generally as for the residential scheme The associated loads are likely to be higher to accommodate air conditioning and ancillary area requirements
Alternatively, a landlord sub-station could be provided, as for the residential scheme, which would satisfy all “non-anchor” loads
Supplementary systems such as telephony systems, music system (possibly), centralised TV/radio systems, access control systems etc would be in addition to te basics provisions required by the residential scheme
3.00 Fire Services
A full analogue addressable detection system would be provided throughout., including within accomaodation
Trang 28Sprinkler protection may be required by Insurers
4.00 Public Health Services
The cold water system would be similar to the residential solution without the need for sub-metering
Hot water would be provided from a centralised boiler and storage unit with flow and return distribution to each room
In respect of foul and waste pipework, suspended drawings within rooms would be possible which may reduce quality of stacks
Additional hot and cold water storage and distribution services including drainage provisions etc would be required to serve the ancillary accommodation (eg kitchens, communal toilets etc)
Architect’s Statement The current scheme contains two elements which would need further detailed analysis, if any of the options were pursued.
Primarily the current design allows for the ramps, the major part of the circulation They go to level 2, where they arrive at
a grand terrace.
If either residential or a hotel occupied level 2 in place of the current retail and restaurant use, the ramps would no longer need to go to this level, so would terminate at level 1 In addition they would no longer terminate at a terrace.
The existence of a terrace at level 2 is questionable if the accommodation is either residential or a hotel at this floor, and therefore it is probable that this part of the design would be removed.
Bettridge, Turner & Partners
A hotel normally requires access for a variety of vehicles for
a number of purposes If there is no car parking customers and a hotel operator would at least expect there to be a pick
up and drop off point for taxies and private vehicles at or close to the hotels main entrance In addition to this we have been advised by Court Catering that hotels generate a significant demand for servicing with vehicles associated with food deliveries and laundry operations requiring access
at frequent intervals throughout the day The number of deliveries is difficult to determine at this stage, although CC have advised that 20 deliveries per day by small and medium sized vans would not be unusual and could be a conservative estimate This is in addition to customers being picked up and dropped off.
Although it is not clear where precisely the hotel entrance would be at ground floor level, we are assuming that it would
be positioned towards the western (Chalk Farm Road) end of the Hawley Lock building With the scheme design as it stands it is proposed that access for some small delivery vehicles would be gained from Chalk Farm Road, with the majority of deliveries taking place at the eastern end of the
site via Torbay Street There are no arrangements in the design at present to allow any cars or taxis to enter the site
It may be possible for a pick up/off point to be located at the end of Torbay Street, but this does run the risk of this area being congested and some vehicles movements being restricted/blocked from time to time It should be noted that this area will have to accommodate HGV movements
associated with a delivery bay, refuse collections and most
of the deliveries for the whole scheme, including the hotel, i.
e there will be a considerable amount of activity in a very small area Hotel customers being dropped of and collected here would have to carry or have their luggage portered a significant distance to the Hotel entrance, which is not desirable In addition having customer access to the hotel in
an area where deliveries and refuse collections take place may not be attractive to a potential operator There could be one solution to this problem, but this would impact on a design for phase 2 of the development This solution would involve maintaining Haven Street, the existing site access as
a route for traffic which could allow a pick up/drop of point for hotel customers to be located closer to its entrance and away from the sites servicing area However this will clearly impact on the design of a scheme at phase 2.
I apologize if this summary appears a little pessimistic but a traditional hotel operation does usually require a customer entrance with highway access at or very close to its This does appear to be difficult to achieve given the constraints
of the Hawley Lock site However if the client wishes to take matters further we can look in more detail at the access options outlined above as part of your overall assessment into the feasibility of a hotel
Consultant’s Statements
Trang 29to be presented to Camden’s planning officials.
This option was chosen because:
CBRE’s study shows that residential has the highest capital and rental values for Camden Lock.
Options 2 & 3 require a highly engineered solution for the fire safety strategy to work - this will result in a significant increase in cost.
For options 2 & 3 more area is needed for plant rooms due to additional sprinkler requirement and smoke ventilation of upper floors.
The evacuation strategy for hotel use will require more area for means of escape.
Hotel floors require air-conditioning what will increase costs and required plant room area
Any type of hotel requires an area for pick-up and drop-off, difficult to accommodate on Chalk Farm Road.
Servicing for a hotel will increase areas for delivery and refuse significantly Additional volume of delivery traffic would have a negative impact on access routes and neighbouring developments.
The ratio between required ‘support areas’ (catering, servicing) and area available for hotel rooms is unfavourable.
The scheme was presented to Camden on 26 September 2006 and was warmly received It is in a robust state to take to public consultation and forward to planning This scheme is illustrated on the following section.
The major implication of providing a hotel on the upper
floors of the building is that the hotel would be evacuated
simultaneously in the event of a fire within the hotel (the
other areas of the building would only be evacuated
following instructions from the attending fire service).
This would mean that the required minimum storey exit and
stair widths from the hotel levels would wider than the
minimum requirements for a residential apartment scheme
(where only the fire-affected apartment would be evacuated,
not all of the apartments)
Other implications that a hotel will have on the scheme
include:
- A fire detection and alarm system installed to a L2 standard
and provided with voice alarm, would be required in the hotel;
- The corridors serving the hotel bedrooms would need to be
constructed to achieve at least 30 minutes fire resistance
Section 20 would require that smoke ventilation is provided
from each level of the hotel building However, if an ‘open
balcony’ approach is used to design the corridors then the
smoke ventilation would not be required.
- Section 20 would also require sprinklers to be installed in
the building, however It is planned to justify against this
requirement with statutory authorities The installation of
sprinklers would be considered as a design risk item.
Court Catering
Camden Lock Village
Catering / Hotel Operation
The comments enclosed are consistent with either option 2
or option 3 as regards the possible hotel facility.
Delivery
First indications from the outline scheme would lead us to
believe that there will be logistic issues as far as the number
of deliveries and refuse collections are concerned with just
the restaurant scheme If there is a hotel as well this will only
increase the problem with additional deliveries throughout the day of linen, housekeeping products as well as any additional catering requirements.
Hotel Catering There would also appear to be no clear definition as to the catering facilities within the hotel Where is breakfast to be served and will there also be a room service facility? Is there
to be an in-house restaurant or are guests to use the other restaurants in the complex?
Storage This does not appear to be adequately catered for
Consideration should be given to the following likely additional storage requirements:-
Refuse General Equipment Store Beverages Mini Bar Store
Dry Goods Dirty and Clean Linen Staff
Consideration must also be given to staff welfare facilities.
Staff Restaurant Male & Female changing rooms & showers Staff Toilets
Offices Hotel operation will require additional office space for the following functions:-
Food and Beverage operations Chef’s Office
Human resources
• General
• Is there to be a main hotel bar
• Are there going to be meeting/function rooms
• What standard of operation is the hotel? 3 or 4 star.
These are just some initial thoughts which can be expanded upon as the project develops but let me know if you require any further information.
Trang 30Design drawings
05
Trang 31Staff Staff
Plant
Plant
Plant Market
Servicing
Plant Plant
Plant Plant
Trang 32Market Market
Lower ground floor
Upper ground floor
Retail
Market
Market
Market Market
Market
Trang 33Public resi terrace
Apartments
Apartments Apartments
Apartments
Apartments
Apartments
Apartments
Trang 34Circulation in retail floors
Circulation in residential floors
Access from Chalk Farm Road
Access from canal side
3 private residential entrances
Short-cuts via escalators
Access from ‘Mews’
Destination point on second floor terrace
Circulation diagrams
Trang 35Long section Cross section
Trang 36Camden Lock Village Canal Building - Stage C report 25 October 2006 Page 70
Trang 37Camden Lock Village Canal Building - Stage C report 25 October 2006 Page 72
Trang 38Living spaces are fully glazed whilst intimate ‘slot windows’
in the bedrooms provide privacy.
The brass cladding responds to the tone and character of local materials like the brick railway viaduct.
Cladding study
Trang 39Camden Lock Village Canal Building - Stage C report 25 October 2006 Page 76
Trang 4006