Phần 2 KHÓA ĐÀO TẠO TÍNH TOÁN ỔN ĐỊNH VÀ ỨNG DỤNG TRÊN PHẦN MỀM PSSE CHO KỸ SƯ HỆ THỐNG ĐIỆN (Nghiên cứu và ứng dụng trên Phần mềm PSSE của Siemens PTI): • PSS®E Basic Operation. • Load Flow Analysis. • Contingency Analysis. • ShortCircuit Analysis.
Trang 1A Division of Global Power
POWER SYSTEM STABILITY CALCULATION TRAINING
D 1 I t d ti t PSS®E Day 1 - Introduction to PSS®E
July 4, 2013 Prepared by: Mohamed El Chehaly
Trang 2OUTLINE OUTLINE
• PSS®E 33: Basic Operation
• Load Flow Analysis
Trang 3PSS®E 33: BASIC OPERATION eBook for You
Trang 4PSS®E Functional Description
PSS®E Functional Description
Power flow and related network analysis
functions
Balanced and unbalanced fault analysis
Dynamic simulation
Trang 5Input Data Files
Input Data Files
Power Flow Raw Data Files (.raw)
Dynamics Data Files (.dyr) y ( y )
Saved Case (.sav) and Snapshot (.snp):
binary files
Subsystem Description Data (.sub)
Contingency Description Data (.con)
Sequence Data Files (.seq)
Trang 6Output Files
Output Files
Distribution Factor Data (.dfx)
AC Contingency Solution Output (.acc) g y p ( )
PV Solution Output (.pv)
QV Solution Output (.qv) Q So ut o Output ( q )
Channel Output (.out)
Slider Diagram (.sld)
Trang 7Automation Files
Automation Files
Response File or IDEV File (.idv)
IPLAN Source Program (.ipl)
IPLAN Executable Program (.irf)
Python Program (.py)
Trang 8Key Elements of the Interface
Key Elements of the Interface
Toolbars Tree View
Trang 9Key Elements of the Interface
Key Elements of the Interface
Tree View
in a hierarchical list
displayed in expandable/collapsible folders
Spreadsheet View
Importing a sav file or a raw file populates the
spreadsheet with network data
Tabs allow specification of the various data
categories
Trang 10Key Elements of the Interface
Key Elements of the Interface
Output View
Alerts and warning also appear in red text in the
Command Line Interface (CLI)
Trang 12Branch Tab
Branch Tab
Branch Data (pu) ID
Trang 13Load Tab
Load Tab
ID Bus Number
Load Data
Trang 14Plant Tab
Plant Tab
Bus Number
Remote Bus Scheduled Voltage
Trang 15Machine Tab
Machine Tab
ID Bus Number
Trang 16Two Winding Tab
Two Winding Tab
Trang 17Two Winding Tab
Two Winding Tab
Base Type
Transformer Data
Thermal Rating
Magnetizing Admittance
Transformer Data
g
Trang 18Fixed Shunt Tab
Fixed Shunt Tab
ID Bus Number
Fixed Shunt Data
Trang 19Switched Shunt Tab
Switched Shunt Tab
Bus Number
Control Mode
Voltage Limits Reactive Power Limits
Trang 20Switched Shunt Tab
Switched Shunt Tab
Number of Step for Block i
Initial Value
Number of Step for Block i Admittance Increment for Each Step in Block i
Trang 21Exercises
1 Go to the “Bus” tab Find bus 3008:
a) What is the name of this bus and its rated
voltage?
Name: CATDOGRated Voltage: 230 kV
b) Based on the code number, what type of bus is
this?
Rated Voltage: 230 kV
Code number: 1 Load Bus
Trang 22Exercises
2 Go to the “Branch” tab Find the branch
that connects bus 201 to bus 207:
a) What are the name of the buses and the rated
voltage of the branch?
Bus Names: HYDRO and DUPONT
b) What is the rated resistance and reactance of
Bus Names: HYDRO and DUPONT Rated Voltage: 500 kV
b) What is the rated resistance and reactance of
this branch (p.u.)?
Trang 23b) What is the power factor of this load?
Trang 24Exercises
4 Go to the “Machine” tab Find generator
connected to bus 402:
a) What are the maximum and minimum reactive
power ratings of this generator?
Qmax = 610 MVAr
b) What is the power loading of the machine in %?
Qmax = 610 MVArQmin = -110 MVAr
b) What is the power loading of the machine in %?
Loading in MVA = √(3212 + 142.32492) = 351.14 MVA
Loading in % = 351.14 / 610 = 58%
Trang 25Exercises
5 Go to the “Switched Shunt” tab Find
switched shunt connected to bus 154:
a) What is the number of shunt elements
connected?
Sum of all blocks = 13
b) What is the maximum reactive power produced?
Sum of all blocks = 13
b) What is the maximum reactive power produced?
Qmax = 124 MVAr
Trang 26LOAD FLOW ANALYSIS eBook for You
Trang 27Power Flow Solution Calculations
Power Flow Solution Calculations
Basic inputs:
admittance
machine
Trang 28Power Flow Solution Calculations
Power Flow Solution Calculations
Quantities determined:
produced/absorbed by each generator at each PV
bus
the generators at the swing bus
transmission line and transformer
Trang 29Power Flow Solution Methods
Power Flow Solution Methods
Gauss-Seidel
Modified Gauss-Seidel
Full Newton-Raphson
Decoupled Newton-Raphson
Fixed-Slope Decoupled Newton-Raphson
Trang 30Power Flow Solution Calculations
Power Flow Solution Calculations
Gauss-Seidel (SOLV)
‐ Tolerant of data
errors
‐ Indicates areas of
‐ Cannot handle negative series reactance
‐ Initial voltage estimates are poor
‐ Network has
‐ Series capacitors
‐ Very low impedance
‐ Number of
Network has reactive power problem
‐ NR failed to
impedance branches
iterations increase with system size
converge
‐ Data is suspect
Trang 31Power Flow Solution Calculations
Power Flow Solution Calculations
Modified Gauss-Seidel (MSLV)
‐ Same as SOLV
‐ Series capacitors
between Type 1
‐ Convergence is very sensitive to tuning of
‐ Initial voltage estimates are poor
‐ Network has
‐ Very low impedance branches
between Type 1
buses
tuning of acceleration factor
‐ Slight deviation from optimum value
l d
Network has reactive power problem
‐ NR failed to
branches
‐ Series compensation more than 80%
leads to poor convergence
converge
‐ Data is suspect
‐ Series capacitors connected to
generator buses
Trang 32Power Flow Solution Calculations
Power Flow Solution Calculations
Full Newton Raphson (FNSL)
‐ Rapid convergence ‐ Intolerant of data p g ‐ Network is ‐ Overloading has
estimates
conventional and well‐behaved
‐ Network with series capacitors
g produced reactive power problems
mismatches can be
achieved
estimates
‐ No indication of cause of problem when failing to
series capacitors
converge
‐ Problems when reactive limits are restrictive
Trang 33Power Flow Solution Calculations
Power Flow Solution Calculations
Decoupled Newton-Raphson (NSOL)
‐ Same as FNSL ‐ Same as FNSL
‐ Cannot handle network with low
‐ Poor voltage estimate
‐ Network with
‐ Overloading has produced reactive power problems
network with low X/R ratio branches
Network with series capacitors
power problems
‐ Network contains branches with low X/R
Trang 34Power Flow Solution Calculations
Power Flow Solution Calculations
Fixed-Slope Decoupled Newton-Raphson
be allowed if mismatches are
estimate
‐ Network with series capacitors
produced reactive power problems
increased
Trang 35Power Flow Solution Calculations
Power Flow Solution Calculations
Approach in solving a new case
Flat start: all voltages to unity amplitude and
phase angles to zero
number of iterations to achieve convergence
Trang 36Power Flow Solution Calculations
Power Flow Solution Calculations
Approach in solving a new case
Trang 37 Line and transformer loading under N 0
Trang 38Data Check
Data Check
Bus voltage check
Trang 39Data Check
Data Check
Line loading check
Trang 40Exercises
1 Load Flow Calculation:
a) What is the first step in the approach to solve a
new case?
Set as flat start and run FDNS
b) What are the two biggest disadvantages with
Gauss-Seidel?
- Cannot handle series capacitors
- Acceleration factor must be tuned
Trang 41Exercises
2 Bus voltage check :
a) Are there any voltage violation at the 500 kV
Trang 42Exercises
3 Line loading check:
a) Are there any non-transformer branches
overloaded at 230 kV and higher?
No
b) What is the load level of the transformer between
L = 141.2% = 1905.7 MVA
Trang 43CONTINGENCY ANALYSIS eBook for You
Trang 44Approach to Contingency Analysis
Approach to Contingency Analysis
Establish base case scenario
Identify the contingencies for both
steady-state and dynamic analysis
Perform the tests and flag all violations g
Trang 45Deterministic Reliability Tests
Deterministic Reliability Tests
Trang 46Basic Process
Basic Process
Trang 47Creation of the Distribution Factor File
Creation of the Distribution Factor File
Trang 48Creation of the ACCC File
Creation of the ACCC File
Trang 49Report Non Converged Cases
Report Non-Converged Cases
Trang 50Report Violations
Report Violations
Trang 51SHORT-CIRCUIT ANALYSIS eBook for You
Trang 52Assumptions Made by PSS®E
Assumptions Made by PSS®E
When the negative and zero-sequence
When the negative and zero sequence
data is not available:
Negative sequence impedance of transmission g q p
lines and transformers equal to positive sequence
impedance
negative-sequence equal and opposite to the
Trang 53Assumptions Made by PSS®E
Assumptions Made by PSS®E
When the negative and zero-sequence
When the negative and zero sequence
data is not available:
positive-sequence are converted to constant
admittance in the positive-sequence
in the negative-sequence as in the
positive-sequence
Trang 54 System planner can make assumptions:
positive-sequence impedance for all equipment
to ¼ of positive-sequence impedance
to positive-sequence impedance
Zero-sequence impedance of lines is equal to q p q
three times the positive-sequence impedance
Trang 55Setting Up Short Circuit Analysis
Setting-Up Short-Circuit Analysis
Change to Physical and Polar
Trang 56Flat Conditions
Flat Conditions
Flat conditions usually selected:
zero phase angle
Trang 57Flat Conditions
Flat Conditions
Flat conditions usually selected:
shunt elements neglected
angle
neglected
Zero sequence ground ties created by grounded q g y g
transformer windings represented
Trang 58Automatic Sequencing Fault (ASCC)
Automatic Sequencing Fault (ASCC)
Trang 59QUESTIONS?
Trang 60partners WE CARE is integral to the way we perform on a daily
b i It i b th ibilit d f ti f ti d basis It is both a responsibility and a source of satisfaction and pride by providing such important standards to all we do.
WE CARE about the health and safety of our employees, of those who work under our care, and
of the people our projects serve.
WE CAREabout our employees, their personal growth, career development and general
well-WE CARE about our employees, their personal growth, career development and general well
being.
WE CARE about the communities where we live and work and their sustainable development, and we commit to
fulfilling our responsibilities as a global citizen.
fulfilling our responsibilities as a global citizen.
WE CARE about the environment and about conducting our business in an environmentally responsible manner.
WE CARE about the quality of our work.