Ứng dụng Ổn định quá độ trên Phần mềm PSSE.NỘI DUNG CHÍNH PHẦN 12 (Application of transient Stability): • Introduction to the test system. • Load flow analysis. • Dynamic simulation setup. • Dynamic simulation setup. • Running a dynamic simulation. • Plotting dynamic simulation outputs.
Trang 1A Division of Global Power
POWER SYSTEM STABILITY CALCULATION TRAINING
D 5 A li ti f T i t St bilit Day 5 - Application of Transient Stability
July 10, 2013 Prepared by: Frida Ceja-Gomez
Trang 2OUTLINE OUTLINE
• Simulation 1: Bus fault – All other elements in service
• Simulation 2: Bus fault – Initial system with elements out of
service
• Simulation 3: Line fault – All elements in service
Trang 3EXAMPLE 1 - INTRODUCTION
EXAMPLE 1 - INTRODUCTION
TO THE TEST SYSTEM
Trang 4Input files
Input files
The files required to perform today’s
exercise are the following:
Trang 5Example 1 Single line diagram
Example 1 – Single line diagram
Trang 6Example 1 Test system information
Example 1 – Test system information
Trang 7Example 1 Test system area based report
Example 1 – Test system area-based report
• Go to the Power Flow menu, Reports, Area / owner / zone totals
• Select Report on Areas, All areas, Loads/induction machines connected to
area buses, and click on Go
• We can see the total generation, load, reactive compensation, losses and
exports of each area
Trang 8Example 1 Inter area flow report
Example 1 – Inter-area flow report
• Go to the Power Flow menu, Reports, Area / zone based reports
• Select Inter area / zone flow, choose output for all areas and click on Go
• We can see the total generation, load, reactive compensation, losses and
exports of each area
Trang 9EXAMPLE 1 – LOAD FLOW
EXAMPLE 1 – LOAD FLOW
ANALYSIS
Trang 10Example 1 – Load Flow Analysis
Example 1 Load Flow Analysis
Performing a quick load flow analysis will allow us to become
familiar with the system y
files
Trang 11Identify any problems in this base case
• Two buses suffer from low voltage
What is the cause of this low voltage?
• There is a transformer with a loading There is a transformer with a loading exceeding 100%
Why is this overload present?
Trang 12eBook for You
Trang 14Converting Loads and Generators
Converting Loads and Generators
it depends on V 2
Trang 15Converting Loads and Generators
Converting Loads and Generators
• Check the output bar to see if the p
conversion was successful
Trang 16Order network for matrix operations
Order network for matrix operations
Solution
matrix operations (re orders
matrix operations (re-orders
the buses for sparsity)
Trang 17Factorize admittance matrix
Factorize admittance matrix
Go to Power Flow menu Solution
• Go to Power Flow menu, Solution
• Select: Factorize admittance matrix
Trang 18Solving power flow for switching studies
Solving power flow for switching studies
Trang 19Saving the converted saved case file
Saving the converted saved case file
ready to be used in
transient stability
simulations
different name (under the (
File menu, Save…)
case file cannot be used for
steady state power flow
analysis
Trang 20Opening the dynamics data file
Opening the dynamics data file
• Two options:
• Dynamics data file – The program assumes it
is the first dynamics file you open
• Add dynamics data file - The program adds
Trang 21Opening the dynamics data file
Opening the dynamics data file
• The window below will appear
• The window below will appear
• The starting indices will be discussed in more
detail later so for the moment just select OK
detail later, so for the moment just select OK.
Trang 22Opening the dynamics data file
Opening the dynamics data file
for details and
Trang 23Dynamic Solution Parameters
Dynamic Solution Parameters
• Found in the Dynamics y
menu
• Here we can modify the
number of iterations
number of iterations,
the tolerance of the
numerical method, etc
Since we are working
• Since we are working
on a 50Hz system,
change the simulation
steps to half a cycle
Trang 24Dynamic Simulation Options
Dynamic Simulation Options
• Found in the Found in the
relative to the swing
t generator
Trang 25Defining the simulation output
Defining the simulation output
• In the Dynamics menu, In the Dynamics menu,
select Define simulation
Trang 26Defining the simulation output
Defining the simulation output
• The first 6 channels added are to monitor the generator’s angles
• The last 23 channels were added to monitor the voltage at each bus
• Note that PSS®E will not delete channels unless the program is
t t d if t t t t h l 1 i th di l i d
restarted or you specify to start at channel 1 in the dialog window
shown in the previous slide
Trang 27EXAMPLE 1 - RUNNING A
EXAMPLE 1 - RUNNING A
DYNAMIC SIMULATION
Bus fault - All other elements in service
Trang 28Initializing the dynamic simulation
Initializing the dynamic simulation
• On the Dynamics menu,
go to Simulation and
go to Simulation and
select Perform
Simulation
• Press on the button to
• Press on the … button to
select or create the
output file
S t R t t 0 0000
• Set Run to to 0.0000
• Print will display values
on the output bar
• Write will record values
on output file
• Click on Initialize
Trang 29Initializing the dynamic simulation
Initializing the dynamic simulation
initialization
following statement should appear at the bottom of the
output bar: “INITIAL CONDITIONS CHECK O.K.”
Trang 30Running the system before any faults
Running the system before any faults
• It is a good practice to run the g p
simulation for a short
duration (in this case 1
second) before applying a
fault
• This allows the software to do
more iterations in order to
refine the system parameters
refine the system parameters
before the fault
• Also, it will be easier to see
the effect of the fault on the
the effect of the fault on the
plots
• To do this, change the run
time to 1s and click on Run
Trang 31Applying a disturbance
Applying a disturbance
menu
choose the bus at which
the fault is applied
be applied on a line
Simulation, Perform ,
Simulation
more cycles and click on
more cycles and click on
Run
Trang 32Removing the disturbance
Removing the disturbance
• Go back to the Go back to the
select Trip line, click
on the select button
and trip branch from
bus 211 to bus 201
Trang 33Running after disturbance has been cleared
Running after disturbance has been cleared
• Click on OK to trip Click on OK to trip
Trang 34EXAMPLE 1 - PLOTTING THE
EXAMPLE 1 - PLOTTING THE
OUTPUTS
Bus fault - All other elements in service
Trang 35Opening the output file
Opening the output file
• Go to the File menu, click on Open and from the drop-down list on the
bottom right corner choose to look for out files
• Open the output file we created on the previous section and a screen like
the one shown below will appear
Trang 36Viewing the recorded channels
Viewing the recorded channels
• Go to the Plot Tree View, double-click on Channel Files and double-click
on example 1
• A list of the recorded channels will now be visible
Trang 37Plotting the recorded channels
Plotting the recorded channels
• To plot a channel, click on it and drag it from the Plot Tree View to the
Channel Plot page
• Plot properties such as the axes, title, background, etc can be modified by
right-clicking on the plot and selecting the parameter we want to change
• Additionally, one can right click and select show editor From this window
one can modify all the plot properties.
Trang 38Plotting the recorded channels
Plotting the recorded channels
• Click on channel 3 and drag it to the channel plot to view the angle of
machine URBGEN
Trang 39Analyzing the output
Analyzing the output
• Is there a problem with the angle of the machine
at bus 206?
• Can it be said that the angle reaches stability?
• Verify the angles of all the other generators in the
• Verify the angles of all the other generators in the
system? Are they all stable?
Trang 40Viewing the recorded channels
Viewing the recorded channels
• Now let us take a look some of the voltages
Trang 41Analyzing the output
Analyzing the output
• Are the observed voltages stable?
• Verify the voltage at all other buses in the
system? Are they all stable?
Trang 42EXAMPLE 1 - RUNNING A
EXAMPLE 1 - RUNNING A
DYNAMIC SIMULATION 2
Bus fault - Initial system with elements out of service
Trang 43Preparing for a new simulation
Preparing for a new simulation
• In previous simulations, we may have switched In previous simulations, we may have switched
certain elements out of service
• Therefore before performing a new simulation it
• Therefore, before performing a new simulation, it
is important to verify that all the elements are in
service
• Go to the Network data sheet and on the Branch
tab, verify that all branches have a checkmark in
their corresponding In Service column
Trang 44Taking an element out of service
Taking an element out of service
Trang 45Initializing the dynamic simulation
Initializing the dynamic simulation
• On the Dynamics y
menu, go to Simulation
and select Perform
Simulation
• Press on the … button
to select or create the
output file
• Use a different output
file from the one we
used in the previous
exercise
• Click on Initialize
Trang 46Initializing the dynamic simulation
Initializing the dynamic simulation
• Verify the output bar for any errors found during Verify the output bar for any errors found during
initialization
Trang 47Running the system before any faults
Running the system before any faults
• Remember to run the system for about 1 second before Remember to run the system for about 1 second before
applying the fault.
change the run time to 1s and click on Run
Trang 48menu, Select bus fault
and choose the bus to
fault
Simulation, Perform
Simulation
4 additional cycles and
click on Run
Trang 49Removing the disturbance
Removing the disturbance
select Trip line, click
on the select button
and trip branch from
bus 211 to bus 201
Trang 50Running after disturbance has been cleared
Running after disturbance has been cleared
• Click on OK to trip Click on OK to trip
Trang 51Verification of the output
Verification of the output
the output bar
Trang 52Output Verification
Output Verification
• Why didn’t the network converge?
• How many machines tripped? How many machines tripped?
• Which machine tripped first? Why?
• What happened after the machine we chose as
reference for the angle tripped?
Trang 53Plotting the recorded channels
Plotting the recorded channels
• Open the output file and plot some of the machine’s angles.
Trang 54Plotting the recorded channels
Plotting the recorded channels
• Now plot some of the bus voltages.
Trang 55Output Analysis
Output Analysis
• What can you tell from the plots?
• Identify the events from the progress report on Identify the events from the progress report on
the plots
• Which buses were the most affected?
• What are the main causes of the instability in the
t k?
network?
• What type of instability can you identify?
Trang 56EXAMPLE 2 - RUNNING A
EXAMPLE 2 - RUNNING A
DYNAMIC SIMULATION 3
Line fault – All other elements in service
Trang 57Preparing for a new simulation
Preparing for a new simulation
Once again let us verify that all the
• Once again, let us verify that all the
elements are in service
• Go to the Network data sheet and on the
Branch tab, verify that all branches have
a checkmark in their corresponding In
Service column
Trang 58Initializing the dynamic simulation
Initializing the dynamic simulation
• On the Dynamics y
menu, go to Simulation
and select Perform
Simulation
• Press on the … button
to select or create the
output file
• Use a different output
file from the one we
used in the previous
exercise
• Click on Initialize
Trang 59Initializing the dynamic simulation
Initializing the dynamic simulation
• Verify the output bar for any errors found during Verify the output bar for any errors found during
initialization
Trang 60Running the system before any faults
Running the system before any faults
• Remember to run the system for about 1 second before Remember to run the system for about 1 second before
applying the fault.
change the run time to 1s and click on Run
Trang 61Select line fault and
choose the line to
fault (bus 152 to bus
Trang 62Removing the disturbance
Removing the disturbance
select Trip line, click
on the select button
and trip the faulted
branch
Trang 63Running after disturbance has been cleared
Running after disturbance has been cleared
• Click on OK to trip Click on OK to trip
Trang 64Plotting the recorded channels
Plotting the recorded channels
• Open the output file and plot some of the machine’s angles.
Trang 65Plotting the recorded channels
Plotting the recorded channels
• Now plot some of the bus voltages.
Trang 66Output Analysis
Output Analysis
• What can you tell from the plots?
• Is the system stable following this disturbance?
• Why doesn’t this fault cause instability issues?
Trang 67Closing the output file
Closing the output file
• Go the Plot Tree View
• Right-click on the output file you wish to close
• Select close
• Note that you can also export the channels to
• Note that you can also export the channels to
Excel
Trang 68QUESTIONS?
Trang 69partners WE CARE is integral to the way we perform on a daily
b i It i b th ibilit d f ti f ti d basis It is both a responsibility and a source of satisfaction and pride by providing such important standards to all we do.
WE CARE about the health and safety of our employees, of those who work under our care, and
of the people our projects serve.
WE CARE about our employees, their personal growth, career development and general
well-WE CARE about our employees, their personal growth, career development and general well
being.
WE CARE about the communities where we live and work and their sustainable development, and we commit to
fulfilling our responsibilities as a global citizen.
fulfilling our responsibilities as a global citizen.
WE CARE about the environment and about conducting our business in an environmentally responsible manner.
WE CARE about the quality of our work.