KHÓA ĐÀO TẠO TÍNH TOÁN ỔN ĐỊNH VÀ HƯỚNG DẪN SỬ DỤNG PHẦN MỀM PSSE CHO KỸ SƯ HỆ THỐNG ĐIỆN (Mô phỏng và tính toán hệ thống điện Việt Nam trên Phần mềm PSSE):• Overview of the Vietnamese Power System. • Load Flow Analysis. • N1 Contingency Analysis. • ShortCircuit Analysis. • PV QV Analysis.
Trang 1POWER SYSTEM STABILITY CALCULATION TRAINING Day 4 - Overview of the Vietnamese Power System
November 21, 2012 Prepared by: Frida Ceja-Gomez
Trang 2OUTLINE
• Overview of the Vietnamese Power System
• N-1 Contingency Analysis
• Short-Circuit Analysis
Trang 3THE VIETNAMESE POWER
THE VIETNAMESE POWER
SYSTEM
Overview of the Vietnamese Power System
&
Load Flow Analysis
Trang 4Saved Case File and Slider File
4 THE VIETNAMESE POWER SYSTEM
Saved Case File and Slider File
Today’s exercises will require the following
• Today’s exercises will require the following
files:
September_2013_max.sav
Trang 6Region Totals North
6 THE VIETNAMESE POWER SYSTEMRegion Totals - North
• Generate a zone based
report including all the zones
belonging to the North
belonging to the North
region
Trang 7• Generate a zone based report including all the
zones belonging to the South region
• How is this region different from the North
region?
Trang 8Region Totals Central
8 THE VIETNAMESE POWER SYSTEMRegion Totals - Central
• Generate a zone based report including all the
zones belonging to the South region
Trang 9• Generate an inter-area flow report for the links p
with China, Laos and Cambodia
• Is power imported from or exported to these Is power imported from or exported to these
countries?
Trang 10Running the Load Flow Simulation
10 LOAD FLOW ANALYSISRunning the Load Flow Simulation
• Run the power flow simulation p
• Verify the Progress window Are there any problems?
Trang 11• Does the diagram range checking flag any problems? g g g g y p
Trang 12Limit Checking Reports
12 LOAD FLOW ANALYSISLimit Checking Reports
• Verify if there are any branch overloads y y
• At what voltage level are the overloads more severe?
Trang 13Pl i R li bilit C it i
Planning Reliability Criteria
• The table below shows the current voltage
reliability criteria used in Vietnam
Trang 14Limit Checking Reports
14 LOAD FLOW ANALYSISLimit Checking Reports
• Verify if there are any voltage violations at the 500kV y y g
level
Trang 15• Verify if there are any voltage violations at the 220kV y y g
level
Trang 16Limit Checking Reports
16 LOAD FLOW ANALYSISLimit Checking Reports
• Verify if there are any voltage violations at the 110kV y y g
level
Trang 1818 N-1 CONTINGENCY ANALYSIS
Preparing the input files for the DFAX file
• Create a subsystem file as shown below
Trang 19Preparing the input files for the DFAX file
• Create a monitoring file
voltage below 0.9pu or above 1.1pu g p p
Trang 2020 N-1 CONTINGENCY ANALYSIS
Preparing the input files for the DFAX file
• Finally, write a contingency file to trip each of
the branches in the high voltage transmission
t system
Trang 21Creating the DFAX file
• Go to AC contingency solution (ACCC) and build
the distribution factor data file
Trang 22Creating the DFAX file
22 N-1 CONTINGENCY ANALYSIS
Creating the DFAX file
• Verify the output bar for any problems with the
distribution factor file
• Note that several contingencies create islands
Trang 25a report of the
non-converged cases eBook for You
Trang 2626 N-1 CONTINGENCY ANALYSIS
AC Contingency Analysis Reports
• How many contingencies caused non-convergence?
• Would this be resolved by increasing the iteration limit? y g
Trang 27AC Contingency Analysis Reports
• Increase the iteration limit and solve again
• Were any contingencies removed? y g
Trang 2828 N-1 CONTINGENCY ANALYSIS
Contingencies causing non-convergence
• For the loss of line from Bus 52002 to Bus 52062, we could build ,
an SLD to analyze the situation
Trang 29Contingencies causing non-convergence
• Note that switching this line off creates an island
• This issue would be resolved by adding a parallel
circuit
Trang 30Contingencies causing non convergence
30 N-1 CONTINGENCY ANALYSIS
Contingencies causing non-convergence
• When losing any of the lines with a blue arrow, all the power is going from bus
30102 to 19262 through the remaining line in service (red)
• This line has enough capacity to transfer the required amount of power, which
indicates that the non-convergence is caused by a voltage problem
Trang 31• This problem can be corrected by adding a fixed shunt capacitor of 80MVAR at
Trang 33AC C ti A l i R lt
AC Contingency Analysis Results
Make sure that the non transformer % units
• Make sure that the non-transformer % units
are in MVA (Misc, options menu)
Trang 34AC C ti A l i R lt
34 N-1 CONTINGENCY ANALYSIS
AC Contingency Analysis Results
• How many contingencies cause severe line
overloads?
• Make sure that the non-transformer % units are in
MVA (Misc options menu)
Trang 35Id tif i l d
Identifying overload causes
• Note that Note that
Trang 36O l d S l ti
36 N-1 CONTINGENCY ANALYSIS
Overload Solutions
What would you
• What would you
recommend to deal
with this overload?
• What type of RAS
would you propose? y p p
Trang 37V lt Vi l ti
Voltage Violations
• Some examples of contingencies causing Some examples of contingencies causing
voltage violations are shown below
Trang 38V lt Vi l ti
38 N-1 CONTINGENCY ANALYSIS
Voltage Violations
• Which contingencies caused severe
• Which contingencies caused severe
voltage violations?
• At what voltage level are voltage violations
• At what voltage level are voltage violations
more numerous?
I th lt t bilit ti ill
• In the voltage stability section, we will eBook for You
Trang 39VIETNAM SYSTEM –
SHORT-CIRCUIT ANALYSIS
Trang 40Automatic Sequencing Fault Calculation in
Trang 41• Go to the Fault menu and
select the ASCC option
• Set the pre-fault
conditions as linear
fl d li k power flow and click
Apply
• Choose to analyze
three-phase and line-to-ground
faults
• Select the output as Fault Select the output as Fault
current summary table
• Select only the 500kV
buses
Trang 43• Repeat the process but…
• Set the pre-fault
conditions as FLAT
• Be sure to unselect this
option
• Select the output as Fault Select the output as Fault
current summary table
• Select only the 500kV
buses
Trang 45Sh t Ci it A l i R lt
Short-Circuit Analysis Results
• Are there any buses with a fault level
exceeding the breaker capabilities?
• Do the results vary with different
pre-fault conditions? If so, why?
• Now perform the short-circuit analysis
for the 220kV b ses
Trang 46Sh t Ci it A l i R lt 220kV
46 SHORT-CIRCUIT ANALYSIS
Short-Circuit Analysis Results – 220kV
• Are there any buses with very high fault levels?
• What about the example shown below?
Trang 47split the bus?
Trang 48VIETNAM SYSTEM – VOLTAGE
VIETNAM SYSTEM – VOLTAGE
Trang 50PV Distribution
50 PV ANALYSIS
PV Distribution
Factor File Input
Create a subsystem file that
Create a subsystem file that
has the following
subsystems
Trang 51Factor File Input
Write the monitoring file Write the monitoring file
as shown to the left
Write the contingency file
as shown to the right
Trang 52and create the
and create the
Trang 53eBook for You
Trang 54Transfer Dispatch Methods Subsystem
54 PV ANALYSIS
Transfer Dispatch Methods - Subsystem
Trang 5656 PV ANALYSIS
PV Analysis Results
• If you go back to the report for non-converged
• If you go back to the report for non-converged
contingency, you will see that the list includes
contingency 2
• Check the progress window to see what
prevented the last transfer increase for the base
case
during the last increase for contingency 1
Trang 59• We will pay special attention to the contingency single 58 (loss of
line 19262-30102)
Trang 62• What can you
tell from the
curve for the eBook for You
Trang 63• What can you
tell from the
curve for the
contingency
case?
Trang 6464 QV ANALYSIS
QV Analysis Results
• Why did we see such low voltages for
this outage during contingency
l i ? analysis?
Trang 65QUESTIONS?
Trang 66WE CARE embodies SNC-Lavalin’s key corporate values and beliefs It y p
is the cornerstone of everything we do as a company Health and
safety, employees, the environment, communities and quality:
these values all influence the decisions we make every day And importantly, they guide us in how we serve our clients and therefore
affect how we are perceived by our external partners WE CARE is
integral to the way we perform on a daily basis It is both a responsibility
d f ti f ti d id b idi h i t t and a source of satisfaction and pride by providing such important standards to all we do.
WE CARE about the health and safety of our employees, of those who work under our care, and of the
people our projects serve.
WE CARE about our employees, their personal growth, career development and general well-being.
WE CARE about the communities where we live and work and their sustainable development, and we commit to fulfilling our
responsibilities as a global citizen.