THỰC HIỆN TÍNH TOÁN MÔ PHỎNG TRÊN PHẦN MỀM PSSE VỚI HỆ THỐNG ĐIỆN 24 NÚT CỦA IEEE. NỘI DUNG CHÍNH PHẦN 3 (Calculation for IEEE 24 Bus System): 1. Overview of the IEEE 24 Bus System. 2. Load Flow Analysis. 3. N-1 Contingency Analysis. 4. Short-Circuit Analysis. 5. PV-QV Analysis. 6. Dynamic Analysis of 3ph and SLG Faults.
Trang 1A Division of Global Power
POWER SYSTEM STABILITY CALCULATION TRAINING Day 1 - Review of the Main Topics Covered in Course A
December 6, 2013 Prepared by: Frida Ceja-Gomez
Trang 2• PV & QV Analysis
Trang 3IEEE 24 BUS SYSTEM REVIEW
System Components
&
Load Flow Simulation
Trang 4Reliability Test System
• Two areas (230kV &
Trang 5• Open the saved case file and
the single line diagram
• Run a power flow simulation;
no errors should be
encountered
encountered
• Identify the main direction of
the power flow on the SLD
Reports to identify overloads
or voltage issues
Trang 7Eliminating the overloads
• All the transforms originally had a rating of 100MVA
• It was necessary to modify the transformers’ ratings as
shown below
• Note that the resistance/reactance values do not need to
be modified since these parameters were input with
respect to the winding MVA base, which was left
unchanged
Trang 8Correcting the voltage issues
we added a fixed shunt capacitor of 75 MVAR at
bus 3
10, 11 and 14, we placed a fixed shunt capacitor
Trang 9Swing bus reactive power
• To correct this problem, it was necessary to
increase the scheduled voltage at nearby PV buses
increase the scheduled voltage at nearby PV buses
to encourage other machines to increase their reactive power output
• Specifically, we modified the scheduled voltage at
bus 23 to 1.03pu
Trang 10IEEE 24 – N-1 CONTINGENCY
ANALYSIS
Trang 11Preparing the input files for the DFAX file
below, which the whole system as well a
subsystem for each area
Trang 12Preparing the input files for the DFAX file
• overloads on all branches
• the buses for each subsystem having a
• the buses for each subsystem having a
voltage below 0.9pu or above 1.1pu
Trang 13Preparing the input files for the DFAX file
each of the branches in the system, one at a
time
Trang 14Creating the DFAX file
build the distribution factor data file
Trang 15Creating the DFAX file
the distribution factor file
bus
Trang 18AC Contingency Analysis Report
Trang 19AC Contingency Analysis Results
overloads?
Trang 20AC Contingency Analysis Results
major overloads?
prevent excessive overloads?
power compensation to keep the
voltage within acceptable limits? If so,
where?
Trang 21Remedial Action Schemes
upgrade lines, it is necessary to
develop operational measures to
protect lines and other equipment from
protect lines and other equipment from
high overloads
you implement for the safe operation of
this system?
Trang 22IEEE 24 – SHORT-CIRCUIT
ANALYSIS
Trang 23Negative and Zero Sequence Parameters
there was no input data for the zero
sequence parameters
the negative and zero sequence
parameters are not available?
Trang 24Negative and Zero Sequence Parameters
• Negative-sequence impedance is equal to
positive-sequence impedance for all equipment
• Zero-sequence impedance of generators is equal to ¼
of positive-sequence impedance
of positive-sequence impedance
• Zero-sequence impedance of transformer is equal to
positive-sequence impedance
• Zero-sequence impedance of lines is equal to three
times the positive-sequence impedance (B0 = ½ B1)
Trang 25Automatic Sequencing Fault Calculation in
PSS®E
• Go to the Misc menu,
and select Change
Program Settings
• Change the
short-• Change the
magnitude and angle
Trang 26Automatic Sequencing Fault Calculation in
PSS®E
and select the ASCC
option
• Set the pre-fault
conditions as the linear
power flow
three-phase and
line-to-ground faults
Fault current summary
Trang 27Automatic Sequencing Fault Calculation in
Trang 28IEEE 24 – VOLTAGE STABILITY eBook for You
Trang 30to study the loss
of each one of the
transformers
Trang 31• Set the initial
• Set the initial
Trang 33PV Analysis Results
• In Course A, we had
plotted the voltage
at Bus 14 for each
contingency
• What is the point of
• What is the point of
voltage collapse for
Trang 34for each case?
• Which one seems
to be the worst
contingency?
Trang 38for each case?
• Are there any
unstable
points?
Trang 39IEEE 24 – DYNAMIC ANALYSIS eBook for You
Trang 40Dynamic Analysis Setup
• Prepare the IEEE 24 saved
case file (V32) to use for
dynamic simulations
• Load the dynamics data file
that you created in Course A
• Set the required simulation
option options, as shown to
the right
• Do not forget to define the
output channels; select all
machine angles and bus
voltages
Trang 41Initializing the dynamic simulation
• Go to Perform Dynamic Simulation and initialize
• There should not be any errors as shown below
• Do you recall any problems found in Course A with the
dynamic analysis file we created initially?
Trang 42Line Fault
• Run the
simulation to 1s
• Apply a 3-phase
line fault on the
line from Bus
21 to Bus 22
• Leave the fault
for 5 cycles
• Trip the affected
line and run the
simulation ten
more seconds
Trang 433-Phase Line Fault Results
• What can be said of the machine angles?
Trang 443-Phase Line Fault Results
• What about the bus voltages?
Trang 45• Leave the fault
for 5 cycles and
Trang 463-Phase Line Fault Results
• Match the events in the progress window to the plot
Trang 473-Phase Line Fault Results
• What can be said about the bus voltages?
Trang 48single-line-to-ground fault on the
line shown to the
right
Trang 49Applying a SLG Line Fault
• Choose the In-line fault option (the
model assumes both breakers are
Trang 50Applying a SLG Line Fault
(Note that in this case we assumed that there is no
re-closure of the line and that the line breakers only have
3-pole reclose capability)
Trang 51SLG Line Fault Results
• Do the machine angles reach stability?
Trang 52SLG Line Fault Results
• What about the bus voltages?
Trang 53Single Pole Auto-reclose)
• Initialize a new dynamic
simulation and run to 1s
• Go to the disturbance menu and
apply a branch unbalance
• Again, select the branch from
• Run the simulation for 5 cycles
Trang 54Single Pole Auto-reclose)
menu and select the One phase
open option
• Run the simulation for 24
additional cycles
phase by modifying the line
parameters R, X, B
• To close the open phase, replace
the original R, X and B line
parameters in the converted
saved case file (this also removes
Trang 55Pole Auto-reclose)
• Do the machine angles reach stability?
Trang 56Pole Auto-reclose)
• What about the bus voltages?
Trang 57Single Pole Auto-reclose)
• The steps for this simulation are outlined below:
• Initialize and run simulation to 1 second
• Apply an in-line SLG fault to the line from Bus 11 to Bus 14 (1/5
of the line, closer to Bus 14) and run for 5 cycles
• Open the faulty phase and run for 24 cycles
• Close the open phase (by replacing the original R, X B)
• Apply the in-line fault again and run for 5 cycles
• Trip the line
• Run for 20 additional seconds
Trang 58Pole Auto-reclose)
• Do the machine angles reach stability?
Trang 59Pole Auto-reclose)
• What about the bus voltages?
Trang 60Stability Analysis
different event sequences simulated for SLG
faults?
IEEE 24 test system in general (3-phase,
Trang 61QUESTIONS?
Trang 62partners WE CARE is integral to the way we perform on a daily
basis It is both a responsibility and a source of satisfaction and pride by providing such important standards to all we do.
WE CARE about the health and safety of our employees, of those who work under our care, and
of the people our projects serve.
WE CARE about our employees, their personal growth, career development and general
well-being.
WE CARE about the communities where we live and work and their sustainable development, and we commit to
fulfilling our responsibilities as a global citizen.
WE CARE about the environment and about conducting our business in an environmentally responsible manner.
WE CARE about the quality of our work.