Electricity of Vietnam EVN- a State-owned enterprise, founded in 1994; - in June of 2006: became Vietnam Electricity, one of the top ten of the biggest enterprises in Vietnam - Productio
Trang 1Luong Van Dai
Director of the Department for Project Appaisal
Vietnam Electricity Group (EVN)
(Presentation at the “HYDRO 2007” in Grenada (Spain))
www.vncold.vn
Trang 2www.vncold.vn
Trang 31 Outlines of Power Sector in Vietnam
2 Power Demand and Power Generation Development Plan
3 Hydropower Potential in Viet Nam
4 Power Plants in Operation and Under Construction commissioned in the period of 2010-2015
5 Orientation of Power Grid Interconnection between Vietnam and Neighbouring Countries
6 Orientation of Capital Mobilization Methods
www.vncold.vn
Trang 4Electricity of Vietnam (EVN)
- a State-owned enterprise, founded in 1994;
- in June of 2006: became Vietnam Electricity, one
of the top ten of the biggest enterprises in Vietnam
- Production and trading of power energy,
- Telecommunications, financing, banking
a Functions and Responsibilities:
www.vncold.vn
Trang 5Operation Model: EVN is operating in the
form of parent and subsidiary, in which parent
company not only directly implement power
production and trading but also financing subsidiary and joint-venture companies, and new fields of
business.
Parent Company – EVN: in charge of strategic decision making and critical orientations of EVN on financing development of power projects,
technologies, sciences and others, and planning
long-term business and production and investment
of EVN and subsidiary companies, and financing subsidiary companies and other enterprises, and
organizing administrative mechanism and
developing human resources of EVN and its
subsidiary companies.
www.vncold.vn
Trang 6b Organizing Structure of EVN
Parent Company – EVN:
Including: Administration of Vietnam Electricity, National Load Dispatching Center,
Power and Civil Project Management Boards, Electricity Information Center, Large Power Plants
Subsidiary Companies
EVN holds 100% of charter
capital of these companies
which operate in the
large-scaled fields of power
production, transmission, trade,
telecommunication and finance
-EVN holds over 50% of charter
capital of these companies
which operate in medium-scaled
fields of power production and
trade, information technology,
mechanics, consultation and
others
Joint-venture Companies
Companies of EVN hold less 50% of charter capital of joint-venture ones which operate in power production, banking, real estate and others
Administrative Units
Including:
Institute of Energy, University of
Electricity and three Electricity Colleges
www.vncold.vn
Trang 719 Thermal and Hydropower Plants
19 Thermal and Hydropower Plants 11 Power
Companies
11 Power Companies
15 Project Management Boards of Generation, Networks, Civil Construction
15 Project Management Boards of Generation, Networks, Civil Construction
4 Electricity Mechanics Companies
4 Electricity Mechanics Companies
4 Power Transmission Companies
4 Power Transmission Companies
4 Power Engineering Consulting Companies
4 Power Engineering Consulting Companies
1 Electricity Telecommunication Company
1 Electricity Telecommunication Company
1 Center for Electricity Information
1 Center for Electricity Information
1 University
of Electricity,
3 College of Electricity
Trang 8c Existing Power Generation and Transmission Networks
By late 2006, Total Capacity of all existing Power Plants in Vietnam is 11717MW,
Diezen, and others
2439,
21%
EVN
external EVN
Rate of Power Supply
- 64/64, provinces
- 100%, districts
- 96%, communes
- 91.5%, household
Power energy produced in 2006: 60.6 bil kwh,
Commercial electricity: 51,5 bil kwh
Average: 600kwh/capita/year www.vncold.vn
Trang 9550
Eo commoercial(kwh/capita/year)
223107
45,6
Ecommercial(Billion kwh)
257124
53,5
EProduced (Billion kwh)
70000
60000-27000
25857-11286
Nlm (MW)
2015 2010
2005 Year
Growth Rate 18-20%
Period 2005-2010, Annual Average Increase, upper 3000MW
Period 2010-2015, Annual Average Increase, some of 7000MW
www.vncold.vn
Trang 101987410211
4198Hydropower
181.000112.000
70.000
60.000-2700011286
25857-Total Nlm (MW)
2025 2020
2015 2010
2005 Year
Percentage of Hydropower in the Whole Power System
* Above-mentioned Capacity of Hydropower is included Pumped Storage Power Plants (4800MW to the year 2025) + power imported from Lao and Cambodia
www.vncold.vn
Trang 11Features of Geography and Meteo-hydrology
Gross area of Vietnam is S = 331.000km 2 , in which 4/5 of this
is mountainous areas and highlands
Vietnam is S-shaped, length of 1630km prolonging from the
North to South Largest width of the North and South is 600km
and 370km, respectively, while it is narrowest in the Central part
of Vietnam, Quang Binh province (Dong Hoi provincial town),
as of 50km
Vietnam is located in the tropical monsoon area, hot and humid,
with large amount of rainfall Average Annual Rainfall is some
of 2,000 mm, in which highest and lowest one is
4,000-5,000mm and 1,000mm, respectively In general, rainy season
lasts from 3 - 5 months but unevenly distributed in term of
spacial aspect.
River network of Vietnam is densely presented in which 2,400
rivers are longer than 10km Almost all rivers in Vietnam flow
into the East Sea.
Gross Run-off Volume is 870 bil m3/year, presented as Annual
Average Discharge as of 37,500 m3/s
www.vncold.vn
Trang 12- Theoretical Potential: about 300 bil kWh (only
accounting for rivers with length of over 10km)
- Technical Potential: about 123 bil kWh, referred
to as Installed Capacity of 31,000 MW
- Technical-Economic Potential is identified as
some of 75-80 bil kWh, equivalent to capacity as
18,000-20,000MW
By the year 2006, Total Capacity of Existing
Hydropower Plants in Vietnam is 4460 MW
which is considered as 18 bil kWh of Average
Annual Energy Production It has been, therefore,
over 20% of technical-economic potential
exploited
www.vncold.vn
Trang 13Power Energy Potential of Medium and Small
Scaled Hydropower Projects lower 30MW.
Total Technical-Economic Potential of Hydropower
Projects ≤ 30MW, some of 300 projects, is in the
range of 2,500-3,000 MW, referred to as 10 bil kWh
of Average Annual Energy Production
Power Energy Potential of Pumped Storage Power
Projects: 10 of Pumped Storage Power Projects, total
capacity of 10,000MW, has been identified viable in
term of Technical-Economic aspect (i.e in Sonla
province: 7 projects, Hoa Bình: 1, Ninh Thuan: 1 and
in Binh Thuan province: 1 project) Pre-feasibility
Report of 2 projects, 1 in Sonla and the other in Ninh
Thuan, has been prepared
www.vncold.vn
Trang 14b- EVN has been conducting construction of projects > 30MW , which total capacity is 6,500MW,
to commission in 2010
At the present, 19 projects invested by EVN are under construction.
In which Sonla hydropower plant, 2,400 MW, is the biggest one in the South East Asian The first and
second units are planned to commission by late 2010 and project completion in late 2012
1 2
3 4
5
9 8 6 7
Huoi
Quang
Son La Ban Chat
Dai Ninh
Srepok3 BuonKuop BuonTuaSah
Song Ba Ha
Kanak Ankhe
Quang Tri
www.vncold.vn
Trang 15320 220 520 2400 342
Installed Capacity (MW)
Nghe An Lai Chau Son La Son La
Tuyen Quang Province
Ban Ve
104 RCC
Ban
Chat
130 CGD
Huoi
Quang
138 RCC
Son La
93 RDF
Tuyen
Quang
Dam Height (m)
Dam type Power Plant
(RCC: Roller-Compacted Concrete; RDF: Rockfill Dam with Facing; ED: Earth Dam; RDC: Rockfill Dam with Center Core Wall, CGD: Concrete Gravity Dam)
www.vncold.vn
Trang 16330 220 210 190 64
Capacity (MW)
Gia Lai Phu Yen
Quang Nam
Quang Nam Quang Tri Province
Se San 4
60 ED
Song
Ba Ha
82 RCC
A Vuong
95 RCC
Song
Tranh 2
75 RDF
Quang
Tri
Dam Height (m) Dam type
Power Plant
Trang 17300 270 240 110 173
Capacity (MW)
Lam Dong Lam Dong Lam Dong Kon Tum Gia Lai Province
Dai Ninh
128 RCC
Dong Nai 4
100 RCC
Dong Nai 3
71 RCC
Pkeikrong
64 RDF
An
Khe-Kanak
Dam Height (m)
Dam type Power Plant
(RCC: Roller-Compacted Concrete; RDF: Rockfill Dam with Facing)
Trang 18220 280 86 33
Capacity (MW)
Daklak Daklak Daklak Binh Thuan Province
Srepok3
30 ED
Buon
Kuop
85 RDC
Buon
TuaSarh
25 ED
Bac
Binh
Dam Height (m)
Dam type Power Plant
(RCC: Roller-Compacted Concrete; RDF: Rockfill Dam with Facing;
ED: Earth Dam; RDC: Rockfill Dam with Center Core Wall)
Trang 19Quang Nam
Song Bung 2 3
Installed Capacity (MW)
Province Project
No.
7 6 5 4
2 1
60 Gia lai
Se San 4a
90 Nghe An
Khe Bo
60
Quang Nam Song Bung 5
145
Quang Nam Song Bung 4
250
Thanh Hoa Trung Son
1200 Lai Chau
3 4
5
9 8 6 7
6
2 3
7
4 5 1
www.vncold.vn
Trang 20d Pumped Storage Power Plants, EVN: These planned projects, total capacity of 4,800MW, will be commissioned in the period 2018-2022.
e- Hydropower Plants, N >30MW: these will be invested by local units in the form of BOT and IPP, and planned commissioning as follows:
- Period 2006 – 2010 : 920MW
- Period 2011 – 2015 : 3100MW
- Period 2016 – 2020 : 1000MW
g- Small-scaled Hydropower Plants:
1,000 MW from small-scaled hydropower projects (i.e projects <30MW) will
be generated in the period 2006- 2010, about 500 MW in 2011-2015 and 1,000 MW in 2016-2020
www.vncold.vn
Trang 21- Interconnecting with Lao:
Immediate projection is that hydropower plants of Lao
such as Nam Mo (100 MW) will be interconnected with
Vietnam via transmission line 220 KV running through A
Vuong HPP to Da Nang city
In Power Development Plan No 6, an amount of
1,000MW will be imported from Lao up to the year 2010
and an increase of 2,000MW beyond 2010 via 2
directions as follows:
+ The first direction: from Central of Lao( Nam Thueon
2, 688MW) to Ha Tinh province
+ The second direction: from the South of Lao( Ban Sok),
Sekaman 1, Se Kong 4, 5 and Nam Kong, total capacity
of up to 1,600MW to Pleiku (Gia Lai)
Due to the delay of proposed development plans of
hydropower projects in Lao, construction of planned
transmission line 500kV will be backward 2010
www.vncold.vn
Trang 22Interconnecting with Cambodia
+ In the period 2008 – 2010: Vietnam will provide
Cambodia with 150-200MW via transmission line
220KV from Cuu Long River Delta (i.e proposed
from transformer station 220KV, Thot Not)
running through Chau Doc and Ta Keo to Phnom Penh
+ In the period 2010 – 2015: proposed
construction of hydropower projects as Lower Se
San 2 (430MW) and Se San 1 & Se San 5
(100MW) will be implemented and transmitted to
the North of Ho Chi Minh city and transformer
station Pleiku, respectively
www.vncold.vn
Trang 23Interconnecting with Van Nam province of
China
+ It is planned that 250 -300 MW will be imported via transmission line 220KV Lao Cai – Yen Bai -Viet Tri in 2006
+ In the middle of 2007, 200MW will be imported
to Ha Giang - Thai Nguyen
+ Possibility of electricity importation 1,500MW in the period of 2006-2018 via transmission line 500KV is considering to connect transformer station 500/220KV Hong He (Hong Ha – Van Nam province) with the one of Soc Son
www.vncold.vn
Trang 24Average Investment Capital for itself EVN in the period of 2006- 2015 is USD 4 billion per year, orientation of capital mobilization methods are as follows:
- Privatization of Power Plants and Power Companies
- Domestic Credit and Bond issue
- International Credit and Diversification of Different Financing Sources
www.vncold.vn