Cast-in-place concrete is selected to be used in this project. Vertical transport equipment:Required height of tower crane:Hyc=hct + hat + hck + ht = 33+1+1.5+1.5=37mWhere:hct: height o
Trang 1DEPARTMENT OF CONSTRUCTION TECHNOLOGY AND MANAGEMENT
MINI - PROJECT CONSTRUCTION ORGANIZATION
Content: Design Construction Schedule and Site Logistics
Supervisor: Pham Nguyen Van Phuong
Hanoi, 2021
Trang 21 Introduction to the building
- Structure of the building is monolithic reinforced concrete structure The building has 9storeys and 12 spans All the geometric data of the building is illustrated in the below table
- Construction and site conditions of the building:
Geological properties: soil grade II with high strength of soil There’s no need toreinforce foundation pit
The level of water table is by far greater than the level of foundation pit
Trang 3Reinf.Ratio µ% 1
Trang 63 Foundation structure
Trang 8*) At axis B&D:
+
+
Thus, choose:
Trang 9*) At axis C:
+
+
Thus, choose:
Trang 11- Heat proofing :12+n/3=12+4/3=13.33Choose : 15 cm
- 2 layers of traditional terra-cotta floortile ( ceramic tile)
6 Wall
Trang 12- Plaster 40% of external wall area ; 50% of internal wall area.
- Paint 6% of external wall area ; 1% of internal wall area
- Doors ( and windows) take 60% of external wall area ; 10% of internal wall area
- Power, water factor 0,32 working hour per 1m of floor. : 2
7 Construction plan and location of building
a) Construction plan
Figure 10: Construction plan
Figure 11: Building location on construction plan
X1 =10+5n=10+5x4= 30 (m)
X2 =15+n/2=15+4/2= 17 (m)
Trang 18Table 226: Labour resource for formwork dismantlement of each partition
Floor Segment Component
Area 100m 2 Quantity Total 100(m2)
Total per element
Quota workday /m3 Workday Total per element
Trang 25Use tower crane as vertical transport equipment.
Because the length of the building is quite great, hence, tower crane with large radius will bearranged
Cast-in-place concrete is selected to be used in this project
Vertical transport equipment:
Required height of tower crane:
Hyc=hct + hat + hck + ht = 33+1+1.5+1.5=37(m)
Where:
hct: height of building
hat: safety distance
hck: height of structure components
ht: height of hanging kits
Working range of tower crane:
Where:
L=43.42m: the length of the building
Trang 26: width of scaffold
: safety distance
b=1m : distance from centre of tower crane to the edge of tower crane
Select tower cranebase on the following requirements:
- Maximum operating radius: R =31.43 (m)yc
Hoisting height: H=37 (m)
Trang 27(ZoomLion’s product catalouge) with following parameters:
- Load capacity: Q=2.8(T)
- Maximum operating radius: R=35 (m)
- Hoisting height: H=40.8 (m)
- Speed:
o Hoisting speed: 48 m/min
o Lowering speed: 48 m/min
o Trolleying speed: 30-60 m/min
o Slewing speed: 0-0.72 r/min
Trang 29 Cycle of tower crane: 1
i t
E is simultaneous gesture factor E=0.8
t1=10(s): time for hanging the bucket on the lifting hook
: slewing time to pouring position
: time for trolley get to pouring position
: time for lowering the bucket to constructing position
t 6 = 120s: pouring concrete time.
: time for lifting bucket to former position
: time for trolley come back to the start point
Trang 30
- Productivity of tower crane per working shift (for concrete transporting only)
N=Q x n x k x k x Tck tt tg Legend: +) t =0.8 x 408.175=326.54(s) : time period of a cycleck
+) n =3600/326.54= 11.02: number of cycle in an hourck
+) k =0.8 : weighting factortt
+) k =0.9 : factor considering time-used of cranetg
+) T=8 (h): duration of a working shift
So the selected tower crane ensures productivity
6 Choose a concrete mixer
- Using commercial concrete
C ROOF CONSTRUCTION
1 List of tasks
1 Pouring waterproof concrete layer 50mm
2 Pouring heat resistant concrete layer 150mm
Trang 314 Paving the ceramic tiles
Figure 25: Cross-section of roof layers
2 Calculation of work volume
Table 27: Work volume of roof construction
No Name of tasks
Dimensions(m)
Unit VolumeLengt
3 Brick wall (110mm thick) 122.56 0.11 1.1 m³ 14.83
2 Heat resistant concrete m³ 116.32 AF.32310 1.66 193.09
3 Brick wall (110mm thick) m³ 14.83 AE.81310 1.72 25.51
3 Division of construction segment
Trang 32Table 29: Work volume of each partition
Partitio
Dimensions
Unit AmountArea
(m2)Height(m)
1
Waterproof concrete 202.79 0.05 m³ 10.14
Heat resistant concrete 202.79 0.15 m³ 30.42
Brick wall (110mm thick) 4.50 1.1 m³ 4.95
2
Heat resistant concrete 207.3 0.15 m³ 31.10
Brick wall (110mm thick) 2.51 1.1 m³ 2.76
3
Waterproof concrete 193.32 0.05 m³ 9.67
Heat resistant concrete 193.32 0.15 m³ 29.00
Brick wall (110mm thick) 2.38 1.1 m³ 2.62
4
Waterproof concrete 173.81 0.05 m³ 8.69
Heat resistant concrete 173.81 0.15 m³ 26.07
Brick wall (110mm thick) 2.14 1.1 m³ 2.35
Trang 331 Heat resistant concrete m³ 30.42 AF.32310 1.66 50.50Brick wall (110mm thick) m³ 4.95 AE.81310 1.72 8.51
2
Waterproof concrete m³ 10.37 AF.32310 1.66 17.21Heat resistant concrete m³ 31.10 AF.32310 1.66 51.63Brick wall (110mm thick) m³ 2.76 AE.81310 1.72 4.75
3
Waterproof concrete m³ 9.67 AF.32310 1.66 16.05Heat resistant concrete m³ 29.00 AF.32310 1.66 48.14Brick wall (110mm thick) m³ 2.62 AE.81310 1.72 4.51
Heat resistant concrete m³ 26.07 AF.32310 1.66 26.68Brick wall (110mm thick) m³ 2.35 AE.81310 1.72 4.04
D FINISHING WORK
1 Work breakdown structure
1 Constructing inside wall-110
Trang 343 Installing MEP system
4 Plastering inside wall-110
5 Painting inside wall-110
6 Installing door and window
7 Plastering outside wall
8 Painting outside
2 Calculation of work volume
a) Brick wall and installation of doors and windows
- Brick wall run along all axes: 220mm for exterior wall and110mm for interior wall.
- Doors and windows take: 60% of external wall and 10% of internal wall
Table 231: Volume of 110mm-thick internal wall and area of internal doors
Trang 35110-Internal wall: 50% plastered and 220-external wall: 40% plastered
Table 253: Area of plastering for 110- internal wall
Floo
Dimensions (m)
Area of Area ofbrickwall plasterHeight Lengt
h(m²) (m²)
Trang 36c) Inside painting and outside painting
- Inside building is painted 2 layers: first is base layer and second is cover layer 1% of internal wall is painted
- Outside building is painted 2 layers: first is base layer and second is cover layer 6% of external wall is painted
Table 275: Area of inside painting
Floo
Area of Area ofbrick painting
Trang 37Height Lengt
h(m²) (m²)
Trang 38d) Mechanical, electricity and pipe installation
MEP task consumes 0.32 working hour per 1m of floor Base on the area of floor, labour2resource can be determined
Table 297: Labour resource for MEP
Element Dimension (m) Quantity Number
Areafloor Norm hoursMan Man-dayLength Widtth per floor of floor (m²) (hour)
3 Calculation of labour resource
Table 308: Labour resource for finishing tasks ( 9 floors)
day
Man-1 Building 110-wall m³ 867.33 AE.81310 1.72 1491.81
3
Plasterin
5 Doors & windows m² 2905.21 AH.32111 0.25 726.30
4 Choose hoist
- Mass of wall built in 1 shift is: =(867.33+297.56)/(9x4)=32.36 m3
-According to basic construction norms, 1m3 of walls need 550 bricks, 0.3m3 of mortar.1m3 has a weight of 2T
-Total weight is Q = 32.36x2 = 64.72 T/shift1
- The volume of plastering in 1 shift is =3944.19/(9x4)=109.56 m2
-According to the basic construction norm, 1m2 of plaster requires 0.02m3 of mortar,1m3 has a weight of 2T
-Total weight is Q = 109.56 x 0.02 x 2 = 4.38 T/ca2
-Total weight to lift is Q = Q1+Q2= 64.72+4.38=69.1 T/shift
Trang 39+ Lifting load: 0.5 T
+ Design lifting speed: 7 m/s
+ Maximum lifting height: 50 m
+ Machine weight: 5.7 billion
+ Capacity of the hoist is calculated by the formula: N = q x n x k x k1 2
Where:
+ k1 = 0.8 coefficient of using the hoist
+ k2 = 0.8 time utilization factor
+ q = 0.5 (T)
+ n = 3600 / Tck with Tck = t + t + t + t1 2 3 4
+ t : loading and unloading time , t = 3 minutes = 180 s1 1
+ t : lifting and lowering time, t = 2x24/7= 7 s2 2
*) Hoist transporting people
In addition, to serve traffic to high floors, we also use a PGX (800-16) passenger hoist
5.Choose Mortar Mixer
The volume of mortar for each segment of each work is calculated as the table below:
Trang 40Table 319: Schedule calculation for one floor
Trang 421 Determine the specific location of the planned work on the ground.
2 Arranging cranes, machinery and equipment for construction
3 Design of the traffic system on the construction site
4 Design warehouse for materials and components
5 Design temporary houses on the construction site
6 Design of electricity and water supply networks
7 Design the system of occupational safety and environmental sanitation
3 CONSTRUCTION ORGANIZATION FOR MAIN TASKS:
3.1 Locate and plan layout on site:
-Based on given data, the construction site layout is presented below:
Trang 43Y1 = 34 (m) Y = 70 (m)2
Trang 45Use fixed-tower crane There are regulations while using tower crane such as:
- The standing of the crane must be the most beneficial in terms of working, convenient in hoisting, mounting or transmaterials, components, etc., with a large reach covering the entire project
- The standing of the crane must ensure the safety of the crane, the construction site and the workers, and facilitate theand dismantling of the crane
- Economical: make full use of the crane power, have a reasonable service radius, high productivity
3.3 Traffic road calculation
Construction site traffic system includes temporary road system, built for construction work The temporary road system inc
- Off-site road: is the road connecting the construction site with the existing public road network
- On-site road: is the network of roads within the construction site, also known as internal roads
When designing the construction site road, it must comply with the current regulations of the Ministry of Transport and otheregulations of the state At the same time, when designing the construction road network plan, it is necessary to follow the gprinciples as follows:
- Maximize the use of existing local roads and combine the use of permanent roads to be built, under the project's plannpre-constructing a part of these roads, to serve the construction
- Based on the diagrams and flow of goods transportation to rationally design the road network, ensure convenient trans
of materials, equipment, etc., and reduce the number of loading and unloading times to the maximum
- To ensure safety and increase transportation productivity, it is advisable to design a one-way street when possible
- Under normal conditions, with a 1-lane road, the parameters of the road width are taken as follows:
- Road width: b = 3,75 (m)
- Side road width: c = 2.1,25 = 2,5 (m)
- Road-bed width: B = b + c = 6,25 (m)
Trang 46- The curved radius of the line where the angle is taken is R = 15(m)
- Road slope: i = 3%
- Road material
- Thoroughly level the ground, then spread a layer of sand 15-20(cm) thick, carefully compact the rocks about 20-30(cm
of the rocks and spread 4x6 rocks
4 TEMPORARY HOUSE
4.1 Number of labours and staffs
- There are 5 main groups of labour on site:
A: main labours
B: supporting labours at supporting plant
C: technical staffs/engineers
D: office staffs
3 Pebbles for drainage
4 Densely compacted sand
1 Clay layer
2 Mixed material layer
Trang 47- Based on the schedule diagram, the average number of type A labour is:
4.2 Temporary house area
- Accommodation for labours (minimum 4m2/labour):
Trang 48- Temporary canteen for labours (50m /100 labours):
5 MATERIAL STORAGE AREA
The plan of storage is storing construction material enough for constructing one storey The mortar used for constructingand plastering is mark 75 cement-sand mortar The selected cement and sand are PC30 cement and fine black sand.a) Determine the amount of materials to be stocked (Qdtr): depends on the following factors:
- Time to receive materials and transport to the construction site is t = 1 day.1
- Time of loading and unloading is t = 1 day.2
- Time for testing and classifying materials is t = 1 day.3
- The time between receipts was t = 4 day.4
- The reserve period is t = 5 days.5
T== 12 days
Trang 49The amount of reserve material is determined by the formula: Q = qi.TWhere:
- Q : is the amount of material stored.idtr
- q : is the maximum amount of materials consumed daily.i
- T : number of days of reserve, we take T = 6 (days)
Sand, brick, stone take T = t1 + t5 = 6 daysdt
- Reinforcement work: 3.57 T (segment 2 floors 1)
-Concrete work: 39.81 m (segment 2 floors 1)3
- Formwork work: 762 m (segment 2 floors 1)2
We have: the norm of 1m of concrete grade 250 has a grade of3 + 0.415 T of cement
Trang 50Use mortar grade 75, norm 1 m3:
- Use mortar grade 75, norm 1 m3:
Trang 51Fine sand: 1.7 * 1,05 = 1.785 (m )3
-Formwork task:
+Formwork: 762 m => 22.86 m2 3
+Including shores: 1.4x22.86=32.004
-Volume of material used in a shift:.
Stored volume of materials:
No Material Unit Volume /1 day T ( day )dt Volume
Trang 52- Storage area F is the area that directly used to store material:
(m )2Where:
d: Quantity of material can be stored per m2
Qmax: Maximum estimated quatity of material at site storage
- Storage area S, including acess for loading, unloading, fire safety, etc.:
S=αFWhere: α: Utilization factor
α =1.5-1.7: for general storehouses
α =1.4-1.6: for warehouse
α =1.2-1.3: for storage yards storing structure members, component, etc
α =1.1-1.2: for storage yards storing piles of material like sand, brick, etc
No Material Unit Stored
volumeType of storage
Volume material/m² α
F(m²)Select
S (m²)
Trang 53Total(kW)