MOVABLE SCAFFOLDING SYSTEM MSS Moving Scaffolding SystemSpan length 15 80 m Usual Total Length 500 m several kms Usual cycle time span 6 10 days

23 334 0
Tài liệu đã được kiểm tra trùng lặp

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 23
Dung lượng 4,83 MB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

TRANSVERSE TRUSSLAUNCHING WAGON PIER SUPPORT FORMWORK TENSION BARS... Overhead MSS - A typical construction cycleAfter concreting, curing and tensioning of cables, the Main Girder and th

Trang 1

MOVABLE SCAFFOLDING SYSTEM

MSS - Moving Scaffolding System

Usual Total Length 500m – several km’s Usual cycle time / span 6 – 10 days

Trang 2

Our strong technical support team can offer services at various levels:

The Movable Scaffolding System - MSS:

Complete or partial delivery

• design, know-how & construction engineering

Consultancy & supervision

• experienced supervision and consultation during fabrication,

assembly & operation

• design, know-how & construction engineering

• Feasibility studies

Trang 3

MSS - Moving Scaffolding System

The MSS was first designed in close co-operation with Norwegian contractors in the 1970's

The system has since then been developed and successfully used in various major bridge projects in Scandinavia and world wide.

The design of our advanced equipment has been improved and optimized over the years, based on our wealth of experience from over 100 projects The system is light weight, easy to assemble, practical in design,

supported by internationally known hydraulic and cranage systems, and most importantly, efficient in operation

Strukturas supplies two types of MSS:

Overhead MSS

• Underslung MSS

Trang 4

Overhead MSS

Trang 5

The development of our cost-effective system over the years, stems from the need to reduce the high costs of construction manpower in Norway Today, our MSS for cast-in-situ bridges can offer many cost-saving advantages to your bridge construction projects, through:

Overhead MSS for the construction of

Cast in-Situ Bridges

Trang 6

Overhead MSS

The MSS can also easily be adapted to any bridge cross section (single box, double box, double T, etc.) and span configuration This flexibility provides the contractor the opportunity to re-use the equipment from one project to another

Trang 7

TRANSVERSE TRUSS

LAUNCHING WAGON

PIER SUPPORT

FORMWORK TENSION BARS

Trang 8

Overhead MSS - A typical construction cycle

After concreting, curing and tensioning of

cables, the Main Girder and the Transverse

Trusses are lowered by the main jacks at

the rear and front Pier Supports

Trang 9

After concreting, curing and tensioning of

cables, the Main Girder and the Transverse

Trusses are lowered by the main jacks at

the rear and front Pier Supports

The Main Girder is now resting on the

launching wagon The Formwork is

disconnected from the Tension Bars

Overhead MSS - A typical construction cycle

Trang 10

After concreting, curing and tensioning of

cables, the Main Girder and the Transverse

Trusses are lowered by the main jacks at

the rear and front Pier Supports

The Main Girder is now resting on the

launching wagon The Formwork is

disconnected from the Tension Bars

The Formwork is now lowered and the

MSS is in the launching position

Overhead MSS - A typical construction cycle

Trang 11

After concreting, curing and tensioning of

cables, the Main Girder and the Transverse

Trusses are lowered by the main jacks at

the rear and front Pier Supports

The Main Girder is now resting on the

launching wagon The Formwork is

disconnected from the Tension Bars

The Formwork is now lowered and the

MSS is in the launching position

Overhead MSS - A typical construction cycle

Trang 12

After concreting, curing and tensioning of

cables, the Main Girder and the Transverse

Trusses are lowered by the main jacks at

the rear and front Pier Supports

The Main Girder is now resting on the

launching wagon The Formwork is

disconnected from the Tension Bars

The Formwork is now lowered and the

MSS is in the launching position

Overhead MSS - A typical construction cycle

Trang 13

The MSS is ready for launching The

launching operation to the next concreting

position is to be carried out

NOTE

The first span is usually 0,8 x max span The following

pours will cantilever by 1/5 of the span lengths.

Overhead MSS - A typical construction cycle

Trang 14

The MSS is ready for launching The

launching operation to the next concreting

position is to be carried out

Overhead MSS - A typical construction cycle

Trang 15

Overhead MSS - A typical construction cycle

Trang 16

and the MSS is now ready to be raised into

the concreting position

In the next position, the Formwork is

assembled and rigged into place

A Rear Support is rigged in place, and will

provide the lifting of the Main Girder by

means of the two rear hydraulic main jacks

The Suspension Bars are adjusted,

However, no Pier Support will be available

at the rear end of the Main Girder this time

Overhead MSS - A typical construction cycle

Trang 18

The MSS is now ready to be lifted into the

concreting position

Overhead MSS - A typical construction cycle

Trang 19

Overhead MSS - Rio Major, Portugal

Trang 20

Overhead MSS - Rio Major, Portugal

Trang 21

Overhead MSS - Grandola, Portugal

Trang 22

Overhead MSS – Bid 374, Taiwan, R.O.C.

Trang 23

Overhead MSS – Bid 374, Taiwan, R.O.C.