Tài liệu tiếng Anh thương mại quản lý Chapter 15 Methods of compensation
Trang 1Chapter 15
Methods of Compensation
Trang 2Key Concepts
• Contract cost risk appraisal
agreements
Trang 3Key Concepts
» Firm fixed price contracts
» Fixed price with economic adjustment contracts
» Fixed price redetermination contracts
» Incentive arrangements
» Cost plus incentive fee arrangements
» Cost plus fixed fee arrangements
» Cost plus award fee
» Cost without fee
» Cost sharing
» Time and materials
» Letter contracts and letters of intent
Trang 4Introduction to Compensation Agreements
determines:
assumed by the supplier
supplier
the compensation arrangements
Trang 5Example 1: Low Level of Uncertainty
Trang 6Example 2: High Level of Uncertainty
Trang 7Example 2: Continued
• Most sellers are unwilling to large risks
at $1,100,000 due to this additional uncertainty
• In this case, the seller studies the
distribution of likely cost outcomes and
concludes that, 9 times out of 10, the
actual cost will be $1,400,000 or less
• Based on the risk aversion, the seller may demand a firm fixed price of $1,540,000
this cost)
contract
Trang 11Contract Cost Risk Appraisal
– Type and complexity of the item or service
– Stability of design specifications or statement of work
– Availability of historical pricing data
– Prior production experience
» Anticipate material and labor cost increases
– Forward pricing is common
» Anticipate possible schedule slippages
Trang 12General Types of Contract Compensation
Cost
Type
Contracts Incentive Contracts
Trang 13Firm Fixed Price Contracts
• A firm fixed price (FFP) contract is an
agreement to pay a specified price when
the items (services) specified by the
contract have been delivered (completed) and accepted
Trang 14When to Use FFP
• Specifications are well defined
• Cost risk is low
• Schedule risk is low
• Technical risk is low
Trang 15Firm Fixed Price Contract Example
Figure 19-3
Trang 16Reasons Why Firm Fixed Price Contracts Do Not
Always Remained Fixed
relief if:
– Assumes other suppliers are not available
sound supply management practices
Trang 17Fixed Price and Economic Price Adjustment Contracts (FPEPA)
• (FPEPA) contracts are used to recognize
economic contingencies, such as unstable labor or market conditions
• FPEPA is an FFP contract that includes
economic price adjustment clauses
Trang 18Rules for Selecting Indexes for Price Adjustment
actual price change of the item being indexed
Trang 19Fixed Price Redetermination Contracts (FPR)
• A FFP is set for an initial contract period
occurs at a stated time during the contract
» Occurs at a stated time during the contract
» Used where a fair and reasonable price can be developed for initial periods but not subsequent periods
• FPR retroactive
» Occurs at the end of the contract
» Used when uncertainty exists as in the prospective, but the amount of the contract is small and/or the
performance period is short
Trang 20Incentive Arrangements
• Used to motivate the supplier to:
• Contract price will usually be higher
• Ceiling price is usually fixed during
negotiations
• Cost responsibility is shared
Trang 21Elements of a Simplified Incentive Contract
• Target cost
the most likely outcome
• Target profit
• Allocating costs above or below target
met
reflects the sharing of the cost responsibility
Trang 22Fixed Price Incentive Fee Example
Trang 23Cost Plus Incentive Fee Arrangements
the cost plus fixed fee arrangement
• Under a CPIF arrangement, an incentive
applies over part of the range of cost
outcomes
• The fee structure resembles a cost plus
fixed fee contract at both the low-cost and high-cost ends of the range
Trang 24Cost Plus Incentive Fee Example
• Sharing below target (customer/supplier) = 75/25
• Sharing above target (cust./supplier) =
Trang 25CPIF Contract Example Continued
Trang 26Cost Plus Incentive Fee Arrangements
• Cost savings = target cost - final cost
• Supplier’s share of cost savings = cost
savings × supplier share
• Computed fee = savings fee + target fee
• Final price = final cost + maximum fee
Trang 27Cost Plus Incentive Fee Example
Trang 28Cost-type Arrangements
» Research and development increases technical risk
» Project completion is in doubt
» Product specifications are incomplete
» High-dollar, highly uncertain procurements are involved
» Cost reimbursement
» Cost plus fixed fee
» Cost plus award fee
» Cost without fee
» Cost sharing
» Time and materials
Trang 29Cost Plus Fixed Fee Arrangements (CPFF)
• Buying firm pays a fixed fee and all costs beyond fee
• Fee is for specified scope of work
• Supplier has no incentive to control costs
• Characterized by low supplier profit
• A total liability limit is usually established
Optimistic Most likely Pessimistic
Final cost $800 $1,000 $1,200 Fixed fee 50 50
50
CPFF Example
(not in text)
Trang 30Cost Plus Award Fee (CPAF)
• The award fee is a pool of money
established by the buyer to reward the
supplier in meeting the buyer’s stated
needs
• Receipt of the fee is based on the buying
firm’s subjective evaluation
• CPAF works as a flexible tool
Trang 31Cost Without Fee
• Used primarily by nonprofit institutions
• Used for research work without the
objective of making a profit
• Institutions recover all overhead costs
• In recent years, high-technology firms
have increased their use of this contract
type
Trang 32Cost Sharing
• In some situations, a firm doing research
under a cost type of contract stands to
benefit if the product developed can be
used in its own product line
the seller agree on what they consider to
be a fair basis to share the costs (most
often it is 50-50)
• The electronics industry has found this
type of contract especially useful
Trang 33Considerations When Selecting Contract Types
» Which may require additional resources to meet deadlines
Trang 34Concluding Remarks
methods presented will significantly
reduce expenditures when cost risk is
present
a reasonable allocation of the cost risk
motivation to the supplier to assure
effective performance
Trang 35END