Extensions of Time, Delay Analysis and Prolongation Where are we? Where are we going? Extensions of Time, Delay Analysis and Prolongation Where are we? Where are we going? SCOTT ADAMS, SCOTT ADAMS CON[.]
Trang 1Extensions of Time, Delay Analysis
and Prolongation:
Where are we? Where are we going?
SCOTT ADAMS, SCOTT ADAMS CONSULTANTS LTD., UNIT A5, 17/F MAI LUEN INDUSTRIAL BUILDING, 23-31 KUNG YIP STREET,
KWAI CHUNG, HONG KONG TEL: 2512 1708
Trang 2• Programmes and Project Management
• SCL Delay and Disruption Protocol Rider 1
(Delay Analysis Techniques)
• Recent Cases on Delay and EOT
• Prolongation Costs - Costain v Charles
Haswell
• Liquidated Damages: A New Test for
Penalties
Trang 3Programmes & Project Management :
• A programme is a project management tool …
• … and nothing more
• Not devised for political, or tactical purpose
• “The programme … is not contractual in the
same sense as the specification, since neither
the contractor or the employer are bound by it The programme is what it is – a document
indicating the intent of the contractor at the
time he furnishes it …” (Max Abrahamson)
Trang 4Programmes & Project Management :
• Vivergo Fuels v Redhall Eng’r’g Solutions [2013]
• Contractor’s employment terminated for not
keeping programme up to date
• [374]: “In summary therefore the need for the revised
programme was not some mere unimportant obligation Rather it went to an important aspect of the project, the time of completion and on a Project such as the present that was relevant not only as a matter of management of Redhall's works but the entire Project It was not made less important by the existence of the Rev 3 Programme, the draft Rev 4 Programmes in December 2010 and January
2011 or the look-ahead programmes.”
Trang 5Programmes & Project Management :
1 Devise a sound, logical programme (and method
statement)
2 Work to the programme until it becomes
impossible for any reason;
3 Record the reason as fully as possible;
4 Update/Revise the programme to account for the
reason (show any delay honestly and fearlessly);
5 Repeat steps 2-4 in respect of each change which
occurs
Trang 6Programmes & Project Management :
1 Should lead to an incrementally updated / revised
programme, showing all delays as they unfold
2 Backed up with detailed records of what changes
have occurred, and why
3 … reading like the chapters of a book
4 And then no need for any further/new substantive
analysis of the delays.
5 So why does this never happen …?
Trang 7Programmes & Project Management :
1 Contractors often do not have the time/resources to
devise a logical, sound and resource-loaded
programme and/or keep such a programme up to date with all changes;
2 All parties have an aversion to having their delays
shown on a programme
3 GCC Clause 50(4): (After EOT award) “… the
Contractor shall revise the programme referred to in Clause 16 accordingly.”
4 Programme incorrectly regarded as ‘binding’
5 PROGRAMME OFTEN NOT WORKED TO!
Trang 8SCL Delay Protocol: Rider 1 (2015)
1 Original SCL Delay Protocol 2002 (Reprint 2004):
2 Widely quoted (although not so widely adhered to)
3 “Delay and disruption issues that ought to be
managed within the contract all too often become
disputes that have to be decided by third parties The number of such cases could be substantially reduced
by the introduction of a transparent and unified
approach to the understanding of programmed
works, their expression in records, and identifying
delay and disruption.”
Trang 9SCL Delay Protocol: Rider 1 (2015)
1 Original SCL Delay Protocol 2002 (Reprint 2004);
2 “The Protocol recommends that, in deciding
entitlement to EOT, the judge or arbitrator should so far as is practicable put himself in the position of the
CA at the time the Employer Risk Event occurred.”
3 [3.2.11] “The methodology described in this section is
known as ‘time-impact analysis’ The Protocol
recommends that this method be used wherever
circumstances permit, both for prospective and
retrospective delay analysis.”
Trang 10SCL Delay Protocol: Rider 1 (2015)
1 “ [A] key difference introduced by Rider 1 to the
Protocol is the removal of a preference for a
particular delay analysis where that analysis is carried out at a time distant from the delay event or its
effect.”
2 [Other main difference] “… the contemporaneous
submission and assessment of EOT claims is elevated
to a core principle.”
3 ‘Time-Impact’ analysis still recommended during the
course of the project (Guidance Section 3)
Trang 11SCL Delay Protocol: Rider 1 (2015)
1 “ 4.1: This part of the Protocol addresses the
consideration of EOT applications after completion of the works, or considerably after the occurrence of
the delay event or its impact In those circumstances, the prospective analysis of delay referred to in
Guidance Section 3 may no longer be relevant or
appropriate.” [My emphasis]
2 But why not? And how long is ‘considerably after’,
and what difference does it make compared to (say)
‘just after’?
Trang 12SCL Delay Protocol: Rider 1 (2015)
1 “ 4.3: The choice of delay analysis to be deployed
should be determined by reference to the following criteria:
• The relevant conditions of contract;
• The value of the project or dispute [proportionality]
• The nature, extent and quality of available records
• The forum in which the assessment is made”
Trang 13SCL Delay Protocol: Rider 1 (2015)
1 “ 4.3: The choice of delay analysis to be deployed
should be determined by reference to the following criteria:
• The relevant conditions of contract;
2 My view: only this criteria matters; if requisite records,
programming etc have not been kept, then it should only go to make execution of the delay analysis (or
prosecution of the claim) more difficult
Trang 14SCL Delay Protocol: Rider 1 (2015)
1 But – beyond the seven bullet points - the Rider does
not clarify what types of factors would lead to
narrowing the choice down to any particular method
2 The disadvantages of each method are mentioned,
but only in a few words
3 Arguably, in cases where records have not been
kept, the Rider could permit lazy or inferior delay
analyses to succeed under the guise of “common
sense”
Trang 15“As-Planned Impacted”
1 Take the initial programme (‘as-planned’)
2 Impact (add) claimed delays to it (as extra activities)
3 The overall delay = the claimed EOT
Trang 16“As-Planned Impacted”
1 Very simple and easy to present and understand
(and cheap!!)
2 But criticised because it does not take account of
progress made at the time of delay events, or
acceleration, or resequencing
3 Results tend to ‘favour’ delays to activities which are
on the initial critical path
4 Rarely accepted by judicial tribunals because of the
problems in (2)
Trang 17“As-Built Collapsed”
1 Take the as-built programme
2 Subtract claimed delays from it, and collapse it
3 The overall delay ‘but for’ = the claimed EOT
Trang 18“As-Built Collapsed”
1 Very simple and easy to present and understand
(maybe not so cheap if ABP takes time to construct)
2 Has the aura of ‘reality’, because it is based on
as-built programmes (but, note, result is theoretical)
3 But criticised because it does not take account of
acceleration, or resequencing Also introducing logic links into an as-built programme can be a very
subjective task
4 Results tend to ‘favour’ delays to activities which are
on the last critical path (longest path)
Trang 19Dynamic Methods: (TIA; Windows)
1 See the “Gold Star Slide” – these methods are based
on contemporaneous or re-constructed updates
2 Because progress and changes in sequence are
accounted for, they are generally considered the
best (most accurate) methods
3 But HUGE volumes of data, and (often) indigestible
massive critical path networks involved Also takes a long time and much $$$$$ … I speculate this is why the Rider is allowing choice of easier methods
4 Lots of opportunity to manipulate the analysis
Trang 20SCL Delay Protocol: Rider 1 (2015)
Trang 21Recent Cases
1 Walter Lilly v MacKay [2012]
2 Cleveland Bridge v Severfield-Rowan [2012]
3 Discussion of actual v prospective delay
4 Adyard Abu Dhabi v SD Marine Services [2011]
5 Discussion on status of EOT Protocol Fig 9 (“Fairness
vs Criticality”)
Trang 22Recent Cases
1 Walter Lilly v MacKay [2012]
2 [362] “Whilst the Architect prior to the actual
Practical Completion can grant a prospective extension of time, which is effectively a best
assessment of what the likely future delay will be
as a result of the Relevant Events in question, a court or arbitrator has the advantage when
reviewing what extensions were due of knowing what actually happened.” [my emphasis]
Trang 23Actual vs Prospective Delay
Trang 24Recent Cases
1 Cleveland Bridge v Severfield [2012]
2 [98]: “In all these delay cases, it is necessary to
show that the claiming party was actually delayed
by the factors of which it complains; it simply does not follow as a matter of logic, let alone practice,
on a construction or fabrication project, that,
simply because a variation is issued or that
information is provided later than programmed or that free issue materials are issued later in the
programme than envisaged originally, the
claimant is delayed.”
Trang 25Recent Cases
1 Cleveland Bridge v Severfield [2012]
2 [98]: “If the real cause of the delay is, say,
overwork or disorganisation within the claimant,
the fact that there have been variations, late
instructions or information or late issue of materials
is simply coincidental.”
Trang 26Recent Cases
1 Adyard Abu Dhabi v SD Marine Services [2011]
2 Delays after prevailing Date for Completion
3 [262]: [SD Marine’s delay expert] gave a helpful example of the
extreme consequences in practical terms of this approach:
"Assuming (as is in fact appropriate in the present case) that the
Contractor is many months in delay by reason of its own default The Employer decides a week before the (original unextended) contract completion date that he wishes a wall to be painted blue instead of the contractually specified red At the time of the instruction,
because of the Contractor's delays, the wall is not even built yet The paint will take 5 weeks to procure, but will still arrive before the
completion of the wall and the date upon which the Contractor
would require the paint in line with his delayed progress
Trang 27Recent Cases
1 Adyard Abu Dhabi v SD Marine Services [2011]
Mr Swan's analysis would appear to entitle the Contractor to 4 weeks' extension of time (by adding 5 weeks to the date of impact, and
comparing with the original contract completion date) However, I
would suggest that common sense tells the observer that such an
extension was neither fair nor reasonable, where the employer's
actions have not actually delayed the progress of the Contractor by
a single day."
1 [263]: In my judgment Adyard's approach is wrong as a matter of
both principle and authority It is also contrary to common sense,
as the above example illustrates.
Trang 28Recent Cases
1 Adyard Abu Dhabi v SD Marine Services [2011]
2 [291(4)]: “In so far as reliance was also sought to
be placed on Figure 9 of Appendix D of the SCL Protocol, I find that, as put to [Adyard’s delay
expert] in cross examination, it can be read as showing that the introduction of the employer's event on path 2 makes that path critical and
causative of concurrent delay in which case
again it puts forward the orthodox position.”
Trang 29Recent Cases
Trang 30Delay and Disruption in Construction Contracts, 5 th Ed (Pickavance, Burr)
Trang 31Recent Cases
Delay and Disruption in Construction Contracts, 5 th Ed (Pickavance, Burr)
Trang 32Prolongation Costs: Costain v Haswell
1 Costain, main contractor constructing a water
treatment plant (design & build); Haswell its engineer
2 Plant consisted of 10 separate buildings/structures
3 Works were delayed due to design problems with
piling of two of the ten structures; Costain claimed
against Haswell
4 At trial, both delay experts agreed that the piling
delay was on the critical path; but nevertheless, the claim for prolongation costs failed
5 Court held that delays to all 10 buildings needed to
be proved, not just the 2 with critical delays
Trang 33Prolongation Costs: Costain v Haswell
1 Court also held that the piling delays were not
proved in any case, despite the experts’ agreement
as to criticality
2 The Court held that the early piling delays may have
been mitigated or neutralised by later events
3 This appears to be at odds with the results which
would be obtained from a time-impact delay analysis
Trang 34Prolongation Costs: Costain v Haswell
1 Court held that delays to all 10 buildings needed to
be proved, not just the 2 with critical delays
2 [184]: “… the contractor will not recover the general site
overheads of carrying out all the activities on site as a
matter of course unless he can establish that the
delaying event to one activity in fact impacted on all
the other site activities Simply because the delaying
event itself is on the critical path does not mean that in point of fact it impacted on any other site activity save for those immediately following and dependent upon
the activities in question.”
Trang 35Prolongation Costs: Costain v Haswell
2 But prolongation costs
only recoverable for
Trang 36Prolongation Costs: Costain v Haswell
Trang 37Prolongation Costs: Costain v Haswell
1 Contractor might
receive no EOT and thus
be liable for full amount
of LD (Adyard v SD Marine); SCL Protocol Figure 9 apparently does not apply
2 Does this seem
Trang 38Liquidated Damages:
1 Several types of defences may be advance to LDs
2 But LDs provisions are seen as a source of certainty,
simplicity of proof and party agreement and so are not lightly set aside by courts / arbitrators
3 In increasing order of desperation (my opinion), the
main defences to LDs are:
• EOT award Insufficient and/or Practical Completion
achieved earlier than certified
• Time at Large (Peak v McKinney)
• LDs are a penalty (Dunlop v New Garage)
• Void for Uncertainty (Bramall & Ogden)
Trang 39Liquidated Damages:
1 Dunlop Pneumatic Tyre v New Garage (1915)
2 Lord Dunedin: “… the essence of liquidated
damages is a genuine covenanted pre-estimate of damage.”
3 “If the sum is extravagant and unconscionable in
amount in comparison with the greatest loss that
could conceivably be proved to have followed the breach, it will be regarded as a penalty and
unenforceable.”
Trang 40Liquidated Damages:
1 ParkingEye Ltd v Beavis [2015]
2 Parking charge for overstay (lump sum, £85) in a
shopping mall car-park
3 [28]: “A damages clause may properly be justified
by some other consideration than the desire to
recover compensation for a breach.”
4 Thus socio-economic factors may be brought into
consideration
5 ParkingEye argued (successfully) that they had a
legitiate interest in managing the car-park and
influencing the conduct of drivers
Trang 41Liquidated Damages:
1 Therefore, we now seem to have a ‘two-stage’
test:
Is Sum a genuine pre-estimate of
loss?
NOT A PENALTY
Yes
Any Economic factors
Socio-giving rise to legitim’t interest
to charge more?
NOT A PENALTY
Yes
Trang 42Liquidated Damages:
1 Not law in HK (yet) … but persuasive
2 Many construction projects have a socio-economic
justification Will this new test give employers carte
blanche to levy higher LDs?
3 Note that the judgment offered no guidance on
what the level of parking charge would have been in order to ‘outweigh’ the legitimate interest
4 Thus the ‘penalty’ defence to LDs has become
harder and (arguably) even more hazy