“THERMAL CONTROL PLAN FOR WIND TURBINE FOUNDATIONS” Mr Quoc Tuan TRINH Deputy Manager, Technical Dept FECON (+84) 904 487 486 tuantq1@fecon com vn Hanoi, 31st July 2021 VIETNAM CONCRETE ASSOCIATIO[.]
Trang 1“THERMAL CONTROL PLAN FOR WIND
Trang 21 Introduction
2 Main concerns of Mass Concrete
3 Thermal Control Plan
4 Application to Wind Turbine Foundations
5 Conclusions
Trang 3HCM cityMyanmar
YANGOON, MYANMAR
• FECON Rainbow Co.,
• FECON Trung Chinh JSC
Founded in 2004, FECON has become one of the most
prestigious contractor in Foundation and Underground.
FROM THE START POINT
+800 COMPLETED PROJECTS
FECON is striving to become a leading EPC
in Infrastructure and Industrial ConstructionTOWARD THE VISION 2025
Trang 4Worker
Trang 6RENEWABLE ENERGY INFRASTRUCTURE
• CONSTRUCTION
• INVESTMENT
Trang 8Onshore Wind Power Plant Near-shore Wind Power Plant
Offshore Wind Power Plant (in development)
FECON - B.O.P CONTRACTOR (ENGINEERING AND CONSTRUCTION)
1 ONSHORE WF THAI HOA – BINH THUAN –90 MW
2 ONSHORE WF BT QUANG BINH –250 MW
3 ONSHORE WF LAC HOA & HOA DONG – SOC TRANG –60 MW
4 ONSHORE WF QUOC VINH – SOC TRANG –30 MW
5 NEARSHORE V1-3 – TRA VINH –50 MW
TOTAL OF 112 WIND TURBINE FOUNDATIONS - 480 MW
FECON’S EXPERIENCES IN WIND ENERGY (period 2020-2021)
8
Note: BOP = Balance of Plant
Trang 9• Vietnam: least dimension > 2m
• Japan / Korea: least dimension > 0.8-1.0 m
• ACI: any concrete volume with dimensions large enough to require that measures to be taken …
WTG Foundations must all be treated as mass concrete!
9
WIND TURBINE FOUNDATIONS – MASS CONCRETE STRUCTURE ?
• Bigger and bigger wind turbine
generators (WTG) are being used
• Huge overturning moment is applied
to the Foundation
Foundations are made bigger, heavier
to withstand the increasing loads
A typical shallow WTG Foundation
Trang 101 Introduction
2 Main concerns of Mass Concrete
3 Thermal Control Plan
4 Application to Wind Turbine Foundations
5 Conclusions
Trang 112 Main concerns of Mass Concrete
11
Temperature Difference
(can result in thermal cracking)
Maximum Temperature
(can reduce strength & durability)
ACI 207.1R states that the only characteristic that distinguishes mass
concrete from other concrete work is thermal behavior that may
cause a loss of structural integrity and monolithic action.
Trang 12 Temperature Difference
• Hydration process leads to the temperature rise in
mass concrete
• Low ambient temperature induces temperature
gradient between the exterior concrete & interior concrete
• The interior concrete tends to expand
• The exterior concrete tends to shrink and resist
interior concrete to expand, causing thermal stress
If thermal Stress > Tensile Strength
→ Thermal Cracking occurs
Free surfaces need to be insulated!
Selecting correct Insulation & Choosing correct
removal time is crucial for Mass Concreting
2 Main concerns of Mass Concrete
Temperature difference → Strain
Trang 13 Temperature Difference (Cont.)
• Not enough Insulation → Big ΔT → Thermal
Cracking
• Sufficient insulation but Early Removal can
cause Thermal shock → Thermal Cracking
2 Main concerns of Mass Concrete
Insufficient insulation
Early formwork removal
Trang 14 Temperature Difference (Cont.)
Required Temperature Difference
• TCVN:ΔT ≤ 20⁰C, gradient T ≤ 50⁰C /m
• ACI:ΔT ≤ 20⁰C (35 ⁰ F)
2 Main concerns of Mass Concrete
FECON’s practices for Insulation
• 5 (cm) of Styrofoam is generally sufficient
• Styrofoam inside the Formwork to enable early formwork removal
• Insulation removal time:
+ 07 days if cooling system is used + 21 days if no cooling system is used
Trang 15 Maximum Temperature
DELAYED ETTRINGITE FORMATION (DEF)
Ettringite is one the the first new crystal that forms instantly
when water is added to Porland cement Ettringite formed at early
ages is often refered to as ‘Primary Ettringite’ It is a necessary and
beneficial component:
C3A + CSH2 + H2O → Ettringite (C6AS3H32)
C3S + H2O → C3S2H3 (glue) + CH
C2S + H2O → C3S2H3 (glue) + CH
Ettringite + C3A + H2O → Monosulfates (3C4ASH18)
C4AF + H2O → Hydrogarnets
However,
Concrete cured at excessively high temperature, i.e > 70 ⁰C,
may develop (DEF) because ettringite decomposes – or does not
form at high temperature
Later it forms / reforms after the concrete has hardened and
may cause expansion & micro-cracking
2 Main concerns of Mass Concrete
Mechanism of micro-cracking in the paste and aggregate interface due to DEF
DEF leads to a decrease of mechanical performance and durability of the structure !
Trang 162 Main concerns of Mass Concrete
Maximum Temperature (Cont.)
Required T max for Wind Farm
• Tmax ≤ 70 ⁰C (SGRE, VESTAS, GE …)
FECON’s practices for Thermal Control
• Many factors to be considered
• Many measures that range from simple to complex
• Depending on actual site conditions, one or
multiple measures can be applied
Proposed T max for Wind Farm
• Tmax ≤ 80 ⁰C
Trang 171 Introduction
2 Main concerns of Mass Concrete
3 Thermal Control Plan
4 Application to Wind Turbine Foundations
5 Conclusions
Trang 18To reduce thermal stresses and control cracking, the general measures should be:
Material Selection: cementitious material content control
Pre-cooling and / or Post-cooling of concrete
Construction Management: concrete handling, construction
scheduling and construction procedure
3 Thermal Control Plan
→ Depending on the actual site conditions, one or multiple solutions shall be applied!
References:
• ACI 301-20 “Specifications for Concrete Construction”
• ACI 207.1R-05 “Guide to Mass Concrete”, 207.2R-07 “Report on Thermal and Volume Change Effects on Cracking of Mass Concrete”
• ACI 224R-01 “Control of Cracking of Concrete Structures”
Trang 19Material Selection: cementitious material content control
Mix design with lower heat hydration:
• GGBF
• Fly Ash
• Low-Heat Hydration Cement
3 Thermal Control Plan
Lower peak temperature when pozzolans are introduced in the mix design
Trang 20Pre-cooling and / or Post-cooling of concrete
3 Thermal Control Plan
• Shelters
• Spray coarse aggregates
• Chiller / Ice for mix water
• Liquid Nitrogen (not feasible)
Each 6 ⁰C lowering of the placing temperature will result in a lowering by about 3 ⁰C of the peak temperature (ACI)
Above pre-cooling measures can reduce the placing temperature by 5-10 ⁰C
Applied in most of Fecon’s Wind Projects
as they are relatively simple & not costly
Trang 21Pre-cooling and / or Post-cooling of concrete
• Remove internal heat after concrete has been placed
• Reduce maximum temperature
• Reduce cooling time
• Specified peak temperature is 70 ⁰C
• Demand of quick construction of hardstand
3 Thermal Control Plan
Trang 22Construction Management: concrete handling, construction
scheduling and construction procedure
Lift 1 Lift 2
• Cast during night time
(one of the simplest measure)
• Coordination of construction schedules with seasonal changes
(try to avoid summer time or hot weathers)
• Cast the structure in multiple lifts
3 Thermal Control Plan
Trang 231 Introduction
2 Main concerns of Mass Concrete
3 Thermal Control Plan
4 Application to Wind Turbine Foundations
5 Conclusions
Trang 244 Application to Wind Turbine Foundations
Assessment of Inputs
Thermal Control Plan
Trial & Error
Full-scale Mockup
Implementation
Repeat if NOT OK
• What is the mix design ?
• Cast in one time or multiple times ?
• Using pre-cooling or not ?
• Using cooling pipe or not ?
• What is the curing method ?
• Method Statement, Working Drawings, ITP … for Mass Concrete, where Tmax and ΔT are predicted
Foundation dimensions
Weather
Onshore or Offshore
Concrete provider Project
Specifications Project
Schedule
Output
Output
Water / Ice availability
If OK
Trang 254 Application to Wind Turbine Foundations
Assessment of Inputs
Thermal Control Plan
Trial & Error
Full-scale Mockup
Implementation
Repeat if NOT OK
Foundation dimensions
Weather
Onshore or Offshore
Concrete provider Project
Specifications Project
Schedule
Output
Output
Water / Ice availability
If OK
Hot
No water
Onshore D=26m, T = 3.6m
T max < 80 ⁰C
Not tight
Mix design not optimized
PROJECT A
Example 1
Trang 264 Application to Wind Turbine Foundations
Assessment of Inputs
Thermal Control Plan
Trial & Error
Full-scale Mockup
Implementation
Repeat if NOT OK
Foundation dimensions
Weather
Onshore or Offshore
Concrete provider Project
Specifications Project
Schedule
Try #1
Output
Water / Ice availability
If OK
Hot
No water
Onshore D=26m, T = 3.6m
T max < 80 ⁰C
Not tight
Mix design not optimized
• Mix design: OPC
• Cast: one time
• Pre-cooling: placing temp ≤ 30 ⁰C
• Cooling pipe: No
• Curing compound: Antisol type E
PROJECT A
Example 1
Trang 274 Application to Wind Turbine Foundations
Assessment of Inputs
Thermal Control Plan
Trial & Error
Full-scale Mockup
Implementation
Foundation dimensions
Weather
Onshore or Offshore
Concrete provider Project
Specifications Project
Schedule
Try #1
Water / Ice availability
If OK
Hot
No water
Onshore D=26m, T = 3.6m
T max < 80 ⁰C
Not tight
Mix design not optimized
• Mix design: OPC
• Cast: one time
• Pre-cooling: placing temp ≤ 30 ⁰C
• Cooling pipe: No
• Curing compound: Antisol type E
Repeat as NOT OK
PROJECT A
Example 1
T max > 80 ⁰C
Trang 284 Application to Wind Turbine Foundations
Assessment of Inputs
Thermal Control Plan
Trial & Error
Full-scale Mockup
Implementation
Repeat if NOT OK
Foundation dimensions
Weather
Onshore or Offshore
Concrete provider Project
Specifications Project
Schedule
Try #2
Output
Water / Ice availability
If OK
Hot
No water
Onshore D=26m, T = 3.6m
T max < 80 ⁰C
Not tight
Mix design not optimized
• Mix: using Fly-ash or GGBF S95
• Cast: one time
• Pre-cooling: placing temp ≤ 30 ⁰ C
• Cooling pipe: No
• Curing compound: Antisol type E
PROJECT A
Example 1
Trang 294 Application to Wind Turbine Foundations
Assessment of Inputs
Thermal Control Plan
Trial & Error
Full-scale Mockup
Implementation
Foundation dimensions
Weather
Onshore or Offshore
Concrete provider Project
Specifications Project
Schedule
Try #2
Water / Ice availability
If OK
Hot
No water
Onshore D=26m, T = 3.6m
T max < 80 ⁰C
Not tight
Mix design not optimized
• Mix: using Fly-ash or GGBF S95
• Cast: one time
• Pre-cooling: placing temp ≤ 30 ⁰ C
• Cooling pipe: No
• Curing compound: Antisol type E
Trang 304 Application to Wind Turbine Foundations
Assessment of Inputs
Thermal Control Plan
Trial & Error
Full-scale Mockup
Implementation
• Method Statement, Working Drawings, ITP … for Mass Concrete, where Tmax and ΔT are predicted
Foundation dimensions
Weather
Onshore or Offshore
Concrete provider Project
Specifications Project
Schedule
Output
Output
Water / Ice availability
If OK
• Mix: using Fly-ash
• Cast: one time
• Pre-cooling: placing temp ≤ 30 ⁰ C
• Cooling pipe: No
• Curing compound: Antisol type E
PROJECT A
Example 1
Trang 314 Application to Wind Turbine Foundations
Tmax = 78-79 ⁰C
Flyash 30% replacement – Evolution of Core Temperature
Full scale Mockup 3.6x3.6x3.6 (m)
Good agreement with prediction!
T max < 80 ⁰C → pass!
Little contingency (peak temp so close to T max )
Recommendation from OE: cast the pedestal later!
Trang 324 Application to Wind Turbine Foundations
Assessment of Inputs
Thermal Control Plan
Trial & Error
Full-scale Mockup
Implementation
• Method Statement, Working Drawings, ITP … for Mass Concrete, where Tmax and ΔT are predicted
Foundation dimensions
Weather
Onshore or Offshore
Concrete provider Project
Specifications Project
Schedule
Output
Output
Water / Ice availability
• Mix: using Fly-ash
• Cast: Slab first, then Pedestal
• Pre-cooling: placing temp ≤ 30 ⁰ C
Trang 334 Application to Wind Turbine Foundations
Construction of the 1 st WTG Foundation:
+ Max lift height: 2.95 (m) (instead of 3.6 m)
Trang 344 Application to Wind Turbine Foundations
PROJECT B
Effectiveness of Cooling Pipes:
w/o cooling pipe
with cooling pipe
Tougher input conditions:
+ Very tight schedule!
+ Max lift height: 3.4 m (pedestal included)
+ Concrete C35/45 MS (cement ~ 400 kg/m 3 )
+ Allowable Tmax = 70 ⁰C
+ Ambient temperature: ~ 33 ⁰C
Thermal Control Plan must combine all available pre-cooling
& post-cooling measures:
+ Pre-cooled concrete
+ 4 layers of cooling pipes, D27 @700
+ Icy circulating water, 17 litters/min
Max temp < 65 ⁰C, foundations can be backfilled after 7 days
Example 2
Trang 351 Introduction
2 Main concerns of Mass Concrete
3 Thermal Control Plan
4 Application to Wind Turbine Foundations
5 Conclusions
Trang 365 Conclusions
Method of controlling mass concrete
temperature range from relatively simple to
complex, and from inexpensive to costly:
To reduce ∆T:
Surface Insulation
To reduce Tmax:
Pre-Cooling of Concrete (spray
aggregates, icy water, shelter etc )
Use lower cement content (mix with
GGBF / Fly-ash) or use Low Generation Cement
Heat- Placing concrete in lifts
Post-Cooling of Concrete (cooling
pipes)
Trang 37 Without proper preparations and correct measures, strength &
durability of the massive concrete structure shall be compromised!
No unique solution for every mass-concrete project
Contractors can use one or multiple measures to optimize the cost
5 Conclusions
Trang 38Mr Quoc-Tuan TRINH
Deputy Manager, Technical Dept FECON
(+84) 904.487.486
tuantq1@fecon.com.vn