Summary of Major Issues raised through Draft Plan consultation & how addressed in Proposed Submission VALP 83... A Draft Housing and Economic Development Needs Assessment HEDNA and Housi
Trang 1Vale of Aylesbury Local Plan
Submission (Regulation 22) Consultation Statement
January 2018
Trang 2Contents
1 Purpose of the document
Regulations The Vale of Aylesbury Local Plan Stages in preparing the VALP Statement of Community Involvement Sustainability Appraisal
Evidence Base
3
2 Scope of The Plan - 2014 (Regulation 18) 10
3 Issues and Options – 2015 (Regulation 18) 14
4 Draft Plan – 2016 (Non-Statutory) 18
5 Proposed Submission Plan – 2017 (Regulation 19) 29
B Deposit Point Location and Opening Hours 87
C List of Specific, General and Other Consultees 88
Tables
1 Stages of engagement in the production of the Vale of
Aylesbury Local Plan
5
2 Summary of representations received from Duty to
Co-operate Bodies at Reg 19
54
4. Specific SCI requirements for each consultation stage 76
5 Summary of Major Issues raised through Draft Plan
consultation & how addressed in Proposed Submission VALP
83
Trang 31 Purpose of the document
1.1 This version of the consultation statement sets out how the Council has involved residents and key stakeholders in preparing the Vale of Aylesbury Local Plan For each consultation stage it describes the background to the work, the various periods of consultation that have been held, along with who was invited to make representations and how This is then followed by a summary of the main issues that were raised at each stage and how they have been addressed It should be read alongside the Duty to Cooperate Statement of
Compliance which also explains how we have engaged actively and constructively with duty
to co-operate bodies, including neighbouring authorities, about strategic issues and the outcomes achieved
Regulations
1.2 This Consultation Statement describes how the Council has undertaken community
participation and stakeholder involvement in the production of the Local Plan to date, setting out how such efforts have shaped the Plan and the main issues raised during each consultation It is produced to respond to and therefore fulfil the requirements set out in the Town and Country Planning (Local Planning) (England) Regulations 2012, and specifically Regulation 19 and Regulation 22(1) part (c) This requires the submission to the Secretary of State of a statement setting out:
● which bodies and persons the local planning authority invited to make representations under Regulation 18;
● how those bodies and persons were invited to make representations under Regulation 18;
● a summary of the main issues raised by the representations made pursuant to
Regulation 18;
● how any representations made pursuant to Regulation 18 have been taken into
account;
● if representations were made pursuant to Regulation 20, the number of
representations made and a summary of the main issues raised in those
representations; and
● if no representations were made in Regulation 20, that no such representations were made
The Vale of Aylesbury Local Plan
1.3 This consultation statement accompanies the Submission Vale of Aylesbury Local Plan (VALP) in accordance with Regulation 22 (1) (c) The VALP is the emerging Local Plan for the district and will, once adopted, replace the 2004 Aylesbury Vale District Local Plan (AVDLP) saved policies The VALP sets out a clear strategic direction for the district, whilst enabling neighbourhood planning to come forward should communities so wish The VALP also contains:
1 Housing and jobs numbers for the Local Plan period, which is through to 2033
Trang 42 Strategic vision, objectives and strategic policies – including for Aylesbury Garden Town
3 Development Management Policies – including design policies, affordable housing, housing mix, employment, infrastructure delivery, green belt policy/criteria for
assessing proposals within, tourism, gypsy and travellers, change of use, renewable energy and climate change
4 Site Allocations for housing, employment, retail, gypsy and traveller sites and green infrastructure
5 Locally valued landscape designations and a reviewed green belt boundary
6 A reviewed Aylesbury town centre boundary and retail frontages
7 Detailed Infrastructure to be set out in policies and proposals in an Infrastructure
Delivery Plan
1.4 The VALP has been prepared in accordance with the National Planning Policy Framework (NPPF) and National Planning Policy Guidance Consultation has been taken within the context of Paragraph 155 of the NPPF which states:
“Early and meaningful engagement and collaboration with neighbourhoods, local
organisations and businesses is essential A wide section of the community should be proactively engaged, so that Local Plans, as far as possible, reflect a collective vision and a set of agreed priorities for the sustainable development of the area, including those
contained in any neighbourhood plans that have been made.”
1.5 Aside from demonstrating compliance with the aforementioned Regulations this statement also highlights how AVDC has met the requirements of paragraph 155 of the NPPF and the Statement of Community Involvement (SCI) (November 2013 update)
Stages in preparing the VALP
1.6 The specific stages in the plan preparation are set out below in Table 1
Trang 5Table 1: Stages of engagement in the production of the Vale of Aylesbury Local Plan 1
2 April – 28 May 2014 An 8-week Scoping (Regulation 18)
Consultation was undertaken asking respondents to tell us if the
proposed scope for the plan was correct, and if anything should not
be included or was missing Around 250 responses were received at
this stage Forums for communities, stakeholders and developers
were held in late 2014 to share initial findings of the evidence A
‘Call For Sites’ was commenced inviting the submission of sites that
would be considered in the technical evidence to inform the VALP
site allocations and overall growth capacity
8
From 23 October- 4 December 2015, we published a VALP Issues and
Options document with a draft evidence base for comment A Draft
Housing and Economic Development Needs Assessment (HEDNA)
and Housing and Economic Land Availability Assessment (HELAA)
evidence studies were published, along with other evidence to
support the VALP Issues and Options As part of this, exhibitions
were held at key larger settlements in the district The total number
of respondents was 771, providing 4,480 individual responses to the
questions A summary report of the issues raised is available at:
On 7 July- 5 September 2016 we published the next stage of the plan,
the VALP Draft Plan, for 8 weeks consultation, including Policy Map
Insets with a suite of supporting documents This stage of the plan
included a developed preferred spatial strategy, fully written policies
and proposed allocations This engagement was accompanied by a
series of exhibitions and a report of comments received has been
published Please see:
http://www.aylesburyvaledc.gov.uk/vale-aylesbury-local-plan-draft-plan More than 1,600 responses,
comprising over 5,000 comments, were received After this time,
various evidence documents to inform the next stage of plan making
were commissioned or finalised and published when completed
8
During 2017, further evidence to inform the VALP Proposed
Submission stage was completed to inform the Proposed Submission
Plan including a Sustainability Appraisal, Habitats Regulation
6
1
Please note that as well as the stages outlined in table 1.0 there was also regular and on going dialogue
with key stakeholders including adjoining authorities (please see the Duty to Cooperate Statement of
Compliance (November 2017) for more information)
Trang 6Assessment, transport, viability, landscape, open space/sports,
cumulative impact assessment for Aylesbury and an updated
Housing and Employment Land Availability Assessment The VALP
Proposed Submission was agreed by full Council on 18 October 2017
The plan was published for a final period of public comment prior to
being submitted to Government for independent examination This
took place over a six week period, from 2 November 2017 until 14
December 2017
988 responses, comprising 2441 comments, were received On the
penultimate day of the Regulation 19 consultation, it became
apparent that an earlier draft version of the Plan could be accessed
online through the Council’s website This was the case even though
the main VALP consultation page – to which the vast majority of
respondents referred – contained the links to the most up to date
draft The responses which referred to the older draft were
identified, 6 in total, and carefully reviewed The Council’s view was
that none of these 6 consultees had been prejudiced by referring to a
previous draft However, in an abundance of caution these 6
consultees were notified and given an extended deadline of 15
January 2018 to submit any amended or further representations on
the changed elements of the Plan which were minor in nature
Further checking during the processing of representations at the
start of 2018 identified a further three responses which referred to
the older draft of the Plan As before, consideration was given to
whether these consultees had been prejudiced as a result of this but
the Council concluded that this was not the case Nonetheless, the
three respondents in question were contacted and given an
extended deadline (13 working days as with the previous group) to
submit amended or further representations on the changed
elements of the Plan
TOTAL WEEKS CONSULTA TION
28
1.7 The above table shows how we have fully complied with the requirements in the
Regulations in terms of consulting on the content of the emerging VALP Views collected in
response to our 2013 consultation on the withdrawn Vale of Aylesbury Plan (VAP) were
also fed into the VALP options consultation October-December 2015 Since the formal
commencement of work on the VALP, a comprehensive evidence base has been developed
upon which policies and proposals within the emerging VALP have been founded and there
has also been extensive engagement with local communities and stakeholders at various
key stages
1.8 Throughout the preparation of the VALP, the Council considers it has succeeded in
front-loading consultation as far as possible by continuously engaging with local communities,
businesses and stakeholders An example of this is the ‘Call For Sites’ which continues to
provide the opportunity to submit sites for consideration in the next stage of plan making
Trang 7There is also ongoing engagement with key stakeholders including Buckinghamshire County Council on evidence base documents and neighbouring councils (see Duty to Co-operate Statement of Compliance)
Statement of Community Involvement (SCI)
1.9 The 2013 adopted Statement of Community Involvement (SCI) contains information on how the Council will consult on the different aspects of planning in planning policy and development management terms This is in accordance with the legal requirements set out
in the Planning Acts2 and Regulations3 The purpose of the SCI is to show how and when community engagement will take place for planning and development The SCI identifies the key groups that the Council consults with, the underlying intention being to engage with anyone who has an interest in the future of the District as a place to live, work or visit
1.10 The Town and Country Planning (Local Planning) (England) (Regulations 2012) prescribe a series of ‘Specific and General Consultation Bodies’ that the Council has to consult with during each consultation stage Below are the groups of specific and general consultation bodies Appendix C outlines the specific organisations and other bodies that the Council considers to have an interest in the preparation of planning documents within Aylesbury Vale
Specific Consultees
● National, regional and local government
● Parish and town councils
● Statutory bodies and groups e.g the environment agency and English Heritage
● Emergency services
● Adjoining planning authorities
● Utility companies e.g Water and electric companies
● National Health Service bodies
● Internal council groups including members and officers
General Consultees
● National organisations e.g the National Trust
● Local organisations and societies e.g residents associations
● Businesses and economic groups e.g Bucks Thames Valley Local Enterprise Partnership
● Environmental groups e.g Bucks & Oxon Wildlife Trust
● ‘Hard to reach’ groups
Other Consultees
● Individuals
● Housebuilders / Agents / Landowners / Housing Associations
● Schools / youth groups e.g Aylesbury Youth Action
1.11 The Council maintains a database of these specific and general consultation bodies
together with local organisations and individuals that have expressed an interest in being consulted on or kept informed of the development of planning policy The database is live and continuously updated The database includes all those listed as specific and general consultation bodies and others including those listed in Appendix C
2
Those referred to are the Town and Country Planning (Local Planning) (England) Regulations 2012;
Planning and Compulsory Purchase Act 2004; Town and Country Planning Act 1990; and
The Town and Country Planning (Development Management Procedure) (England) Order 2010
3
Neighbourhood Planning (General) Regulations 2012.
Trang 81.12 The SCI was adopted in 2013 and sets out methods of consultation for formal consultation stages including:
● Circulating material by email or letter
● Making information available on the website
1.13 This submission consultation statement sets out how the Council have met the
requirements of the adopted SCI for the preparation of the VALP For more detail on each
of the requirements of the SCI and how these have been addressed is shown in Table 2 1.14 As well as consultation on the VALP policy document, there has also been consultation on
the evidence base and supporting documents Specifically there has been consultation on the Sustainability Appraisal (SA) and on going dialogue with key stakeholders as part of the Duty to Cooperate
Sustainability Appraisal (SA)
1.15 The SA is an iterative process and there have been various stages throughout the
preparation of the plan The iterations of SA are listed below All stages, and the key
findings, are summarised in the final SA Report which is published alongside the Proposed
Submission VALP
Sustainability Appraisal Date Completed/
Consultation Held
Information that was appraised
SA Scoping Report September 2015
Published for consultation with VALP Issues and Options, October
2015
Baseline information for Aylesbury Vale This Scoping Report has been prepared as the first stage of the SA process in order to inform the environmental assessment of the plan This report was published for consultation with the
consultation bodies as required by Regulation 12 (5) of the UK SEA Regulations 2004
Reasonable Alternatives
SA Report
October 2015
Published for consultation with VALP Issues and Options, October
2015
This report assesses the reasonable alternatives stage of plan-making, also known as ‘options’ AVDC has considered a range of different sites and policies for development within the Vale of Aylesbury This SA Report document represents a
SA of the reasonable alternatives for strategic spatial sites identified by AVDC
Assessment of
Reasonable Alternatives
July 2016
Published for consultation with VALP Draft Plan July 2016
This report concentrates on the high level assessment of reasonable alternatives being considered as part of the planned consultation on the local plan This document does not constitute
an Environmental Report in line with the SEA Directive, it is a record of assessments of
Trang 9reasonable alternatives (options) for housing and mixed-use housing and employment sites in Aylesbury Vale (Aylesbury)
Proposed Submission November 2017
This report is the VALP SA Report In line with the Regulations, a report (known as the SA Report) must be published for consultation alongside the draft plan that essentially ‘identifies, describes and evaluates’ the likely significant effects of
implementing ‘the plan, and reasonable alternatives’ The report has been taken into account, alongside consultation responses, when finalising the plan
https://www.aylesburyvaledc.gov.uk/sustainability-appraisal-sa
Evidence Base
1.16 As well as consultation on the VALP document, there has also been consultation on the
evidence base and supporting documents Specifically there has been consultation with technical experts on the following:
● HELAA: through steering group (versions 1, 2) and Buckinghamshire County Council
● HEDNA: consulted all adjoining districts and districts in the housing market area;
● The SFRA and Water Cycle Strategy: consulted Buckinghamshire County Council, the
Environment Agency, Anglian Water, Thames Water and Bedford Group of Internal
Drainage Boards
● The Habitat Regulations Assessment: consulted Natural England
● The SA scoping report: consulted the Environment Agency, Natural England and
Historic England
● Countywide Traffic Modelling reports in 2017 for Aylesbury and Buckingham jointly
prepared with Buckinghamshire County Council (the Highways Authority): consulted
Aylesbury Vale Advantage and Buckingham Town Council
● Aylesbury and Buckingham transport strategies: consulted with AVDC and
Buckinghamshire County Council
● County-wide Green Belt Review: prepared with other Buckinghamshire district councils and consulted BCC
● Bucks Gypsy and Travellers and Travelling Showpeople Accommodation Assessment: prepared with other Buckinghamshire district councils
● Infrastructure Delivery Plan: consulted with Buckinghamshire County Council, Clinical Commissioning Group, utility companies, water companies, power networks, Local
Enterprise Partnerships
1.17 As well as the consultation stages outlined in this document, there has been on-going
dialogue between a number of stakeholders as part of the Duty to Cooperate Further
detail about this is contained within the Duty to Cooperate Statement of Compliance
Trang 102 Scope of the Plan -2014 (Regulation 18)
Public engagement on Scope of the Plan, 2014
2.1 The consultation ran from 2 April until 28 May 2014 This was a first part of meeting
the Regulation 18 requirements on engaging on a local plan The emphasis was to mark the commencement of preparing a new plan and get frontloaded input from
communities and stakeholders before evidence was collected and issues and options generated
2.2 There were four questions asked in this consultation:
Are all of the policy topic areas listed in the consultation document appropriate for inclusion? (if not, please say why and where else they should be covered)
Is there anything missing from the list that should be included within VALP? (please specify)
Do you have any specific suggestions about what the strategy or policies should contain? (please provide as much detail as possible)
Do you have any other comments?
2.3 In addition a ‘Call For Sites’ pro forma (form) was published inviting sites to be
submitted
2.4 These particular questions were asked in order to help the Council identify the key
issues in relation to plan making, and develop options, growth ranges, what kinds of development should be provided for in the plan, what infrastructure is needed and any other matters
2.5 The following documents were produced to support the public consultation:
• Scoping Consultation (Regulation 18) - Consultation Document
• Scoping Consultation (Regulation 18) - Comments Form
• Call for Sites – Consultation Document and Sites Pro forma
Bodies and persons invited to make representations
2.6 Appendix C , the consultation list, includes the general and specific bodies who were
consulted at this stage Individuals have not been listed
How bodies and persons were invited to make representations
2.7 A consultation document and comment form was published and distributed with a letter
to individuals and stakeholders already on the Council’s database of people who had previously commented during the plan making process or who had expressed an interest
in the VALP The consultation material was also made available on our website, at council offices, libraries and area offices, in conformity with the SCI
Trang 112.8 The following methods were available at the is stage of consulting on the plan
Comments could be submitted in a number of ways:
• Electronically via Survey Monkey: https://www.surveymonkey.com/s/VALP-Scoping
• Emailed to: VALPconsult@aylesburyvaledc.gov.uk
• Posted to: Planning Policy, AVDC, The Gateway, Gatehouse Road, Aylesbury, Bucks, HP19 8FF, DX 4130 Aylesbury 1
2.9 Other methods of publicity were:
● VALP Newsletter – 31 March 2014
● Use of the Council’s website – website changes 26 March 2014, 1 April 2014
● Weekly ‘Bulletin’ sent to all parish and town councils – weekly throughout 2014
● Press release (2) - 7 April 2014 and 24 May 2014
Summary of the main issues identified
2.10 A detailed summary of the issues raised by organisations was made available at
https://www.aylesburyvaledc.gov.uk/vale-aylesbury-local-plan-scoping-consultation
2.11 The following are some of the main points raised:
Where specific site allocations have not been included in the Plan it will be
necessary to provide a basis for Neighbourhood Plans and development management decisions
The Spatial Strategy should be supported by a transport / traffic modelling
assessment that takes into account development in neighbouring areas
A number of authorities may not be able to accommodate all of their identified housing needs and may be looking to Aylesbury Vale to accommodate some additional growth Recognising that Aylesbury Vale forms part of a wider Housing Market Area that is not confined to its own administrative boundary, it is crucial that AVDC seeks to work with neighbouring authorities such as Milton Keynes from the outset, to gain a full understanding of housing needs
Self build opportunities should be included
Would like confirmation that infrastructure including roads, rail, schools and hospitals will be provided early in any development It should follow population by families and business A plan for the plan would be most helpful
There should also be the opportunity at this stage of the process to identify sites that should not be developed: e.g to preserve open space(s) in settlements; to prevent coalescence between settlements; to preserve a locally cherished view or area of ecological value that might not be otherwise designated
There is no reference in the scope to biodiversity, green infrastructure or
landscape issues Planning policies should therefore encourage, as best practice, communication with and consultation of the Buckinghamshire Local Nature Partnership in order to identify and promote coherent ecological networks across Aylesbury Vale Planning policies should therefore set a framework for the clear recording and reporting on measures to be taken for the positive management of networks of biodiversity The spatial strategy is currently limited and needs to be expanded to make specific reference to the influence of key settlements in neighbouring authorities such as Milton Keynes The currently proposed focus of the strategy on Aylesbury and Buckingham would potentially limit the scope to achieve development in other sustainable locations within the district
Trang 12 The VALP should be positively prepared in accordance with the guidance in the NPPF and policies should provide clear guidance as to the level and location of future growth for the area There should be a clear policy outlining how the development on specific sites should come forward to help secure the sustainability aspirations of the Council
2.12 40 responses were received via the Survey Monkey questionnaire, and around 200
responses were received via email and post
2.13 In terms of neighbouring authorities, we received responses from Wycombe District who
sent a fairly high level response stating they were happy with overall scope and need to work with them on the VALP; Bedford Borough provided a similar high level response; Luton gave a more detailed response drawing our attention to what they had done so far and that they would be likely to look to us to help meet growth needs; Central
Bedfordshire Council had no comments but thanked us for consulting them; South Bucks commented that we need to allocate more housing and work together on the Duty to Co-operate
2.14 We had around 150 developer-promoted sites received at the ‘Scope of the Plan’
consultation stage Developer responses and sites promoted are set out at
https://www.aylesburyvaledc.gov.uk/vale-aylesbury-local-plan-call-sites-consultation) but are summarised in the following paragraphs
2.15 A number of large sites were promoted around Milton Keynes including land East of
Whaddon, Salden Chase, land north of Newton Longville (and all around the north of the village) and a site east of Newton Longville, as well as Eaton Leys A large extension called Shenley Park was also promoted at this stage
2.16 At Winslow, a number of sites have been submitted including Verney Road and Land off
Little Horwood Road
2.17 At Buckingham – a large site to the south land adjacent to the industrial estate, Land off
Osier Way, Land between the A421 and Tingewick Road, and south of Tingewick Road 2.18 At Aylesbury – Fleet Marston, Land East of Weedon Hill, Land north of Watermead,
Berryfields East, Land between Stoke Mandeville and Walton Court/Southcourt, and the whole of south-west Aylesbury, Hampden Fields and a separate submission from the Weston Turville golf course, and a smaller site off Broughton Lane We also had the land between A41 and the canal (Aylesbury East) and a further extension of Aylesbury East closer to the A41 roundabout/Aston Clinton
How the issued raised have been addressed
2.19 In terms of how the issues raised have been addressed, this is in essence led to the Council
commissioning further evidence which was required in order to help the development of formal issues and specific options that could be consulted on at a next stage The key areas were:
All Call for Sites submission fed into the first two versions of the HELAA (Housing and Economic Land Availability Assessment)
Trang 13 The Call for Sites process would continue outside the formal consultation period to allow the ongoing submission of new sites and updated information on existing sites
A new HEDNA (Housing and Economic Development Needs Assessment) was
prepared for an agreed Housing Market Area and methodology covering ‘Central Buckinghamshire’ This was Aylesbury Vale, Wycombe and Chiltern districts
A report was commissioned to review the evidence base documents Aylesbury Vale Landscape Character Assessment and Aylesbury Vale Areas of Sensitive Landscapes
to see if having such evidence would comply with the NPPF
Trang 143 Issues and Options - 2015
(Regulation 18)
Stakeholder Forums prior to Public Consultation, 11, 12 November 2015
3.1 The formal public consultation was preceded by stakeholder forums All district members
were invited to an event on 11 November whilst all parish and town councils were invited
to send a representative to an event on 12 November 2015
12 November 2015 Parish Forum - How bodies and persons were invited to make
comments
3.2 An officer presentation shared information on the emerging Housing and Economic
Development Needs Assessment evidence, emerging work on constraints reviews and initial stages of the Housing and Economic Development Land Availability Assessment, development management policies and forward timetable There was then a question and answer session where those attending could raise queries and comments, these were all noted down along with the answers provided Some feedback was also provided after the event to specific questions
3.3 There was also a facilitated table discussion which centred around the draft plan aims and
the draft approach to employment Each table again had roughly 6-8 people in the
discussion and an officer leading who was taking notes on comments made The
discussion at the table and any questions asked were circulated in a feedback note sent out to those who attended
3.4 An email was sent to all parish and town councils on 12 October 2015 notifying and
briefing on the publication of an emerging evidence base for the VALP These were draft reports and comments were invited on their content and factual accuracy alongside the Vale of Aylesbury Local Plan Issues and Options consultation which closed on 4 December
2015 The reports were:
• Draft Housing and Economic Development Land Availability Assessment
• Draft Settlement Hierarchy Assessment for the Vale of Aylesbury Local Plan
• Draft Review of Areas of Attractive Landscape and Local Landscape Areas
3.5 The Issues and Options Consultation, as well as shaping the emerging options for high
level policies about development numbers and distribution, also shaped the vision for how the district will be and the ‘sense of place’ hoped to be achieved through the plan This was an issue raised particularly by parishes at the community view stage (during VALP Strategy, 2011) but also through comments made by technical stakeholders amongst their comments on other issues We have addressed these issues in the overall vision of the plan, which has then informed the strategic objectives and subsequently the VALP policies
in a ‘golden thread’
Trang 15Public Exhibitions – November 2015
3.6 Public exhibitions were held as follows:
3.7 The feedback received at the exhibitions in the form of post-its following discussions with
individual officers has been published at aylesbury-local-plan-%E2%80%93-issues-and-options-consultation
https://www.aylesburyvaledc.gov.uk/vale-3.8 The panels displayed at the exhibitions are available to download at
options-consultation
https://www.aylesburyvaledc.gov.uk/vale-aylesbury-local-plan-%E2%80%93-issues-and-Issues and Options Public Consultation
3.9 This ran from 23 October to 4 December 2015 (6 weeks)
Publicity
3.10 A letter was emailed or posted on 23 October 2015 to all statutory consultees and active
consultees on our mailing list Letters included a web link to the consultation documents and how to respond An emailed letter was used where there was an email address, otherwise a printed and posted paper letter was relied on See Appendix C for who was contacted by emailed letter or posted letter on this public consultation, in accordance with our adopted SCI
3.11 The consultation was also advertised on the Council website for the whole consultation
period
3.12 A press release was issued to the media on 8 October 2015
3.13 A Summary Leaflet and Poster were produced and a display was maintained at the AVDC
Gateway offices from 23 October to 4 December when the consultation ended The leaflet and poster were also used at all exhibitions to advertise on the day of the exhibition
Trang 163.14 The primary consultation documents published as PDF documents on the Council website
were the VALP Issues and Options Consultation Document and Issues and Options
Comment Form
Consultation Questions
3.15 13 questions were asked; some were “yes” or “no” questions with detailed comments;
some were tick box answers from a range of options Some questions stated the
conclusion from the evidence base but for all questions there was the opportunity to suggest alternatives, for example a different settlement hierarchy to the one in the
published settlement hierarchy evidence paper
Methods of Feedback
3.16 We received feedback by the following methods:
a ‘Survey Monkey’ questionnaire was the Council’s preferred method of
feedback
material sent in writing to AVDC at the Gateway offices
The Response
3.17 The total number of respondents was 771, providing 4,480 individual responses to the
questions There were also a number of new sites promoted to the Council and further information on sites that had already been promoted to the Council
Summary of the main issues identified
3.18 A detailed summary (319 pages) of the issues raised by organisations was made available
at and-options-consultation
https://www.aylesburyvaledc.gov.uk/vale-aylesbury-local-plan-%E2%80%93-issues-3.19 There was also a published summary of responses from neighbouring councils and from
utility companies
https://www.aylesburyvaledc.gov.uk/vale-aylesbury-local-plan-%E2%80%93-issues-and-options-consultation These responses informed the situation for the purposes of the Duty to Co-operate for ongoing engagement and also infrastructure planning
3.20 In terms of the overall issues raised, responses largely focused on the amount of housing
being proposed and the role of unmet need in that figure The main response was that the number should be lower without any unmet need However some responses suggested that any unmet need from the south of the county should not be accommodated in the north of Aylesbury Vale There were a number of comments on the content of the Housing and Economic Development Needs Assessment which were passed on to the Council’s consultants
3.21 There were also a significant number of comments on the implications for growth in the
villages from the Settlement Hierarchy Some considered the Settlement Hierarchy needed
a major revamp, with its assertions outdated and unsophisticated Some respondents considered it inappropriate to define 31 villages of hugely different populations and
Trang 17facilities all as 'large' Eight have populations in excess of 2,000; six have less than 800 There are over 100 villages within rural areas, providing rich heritage that needs
protecting for future generations
3.22 In meeting the Duty to Co-operate it is important that the comments of adjacent
authorities are given particular consideration Aylesbury Vale is a potential location for unmet need from several adjacent Council areas and this formed a significant part of the response at the Issues and Options stage The responses recognised that the figure for unmet need is subject to confirmation from the respective authorities and so following review of those authorities’ constraints and supply, the need figure could change The NPPF states that plans should be based on a strategy which seeks to meet development needs, “including unmet requirements from neighbouring authorities where it is
reasonable to do so and consistent with achieving sustainable development”
3.23 Buckinghamshire County Council made significant comments in response to the Issues and
Options consultation and the responses to the questions are set out in Appendix 3 to the
11 May 2016 VALP Scrutiny Committee Broadly, the County Council considered that the overall strategy should be reconsidered to direct more development away from the smaller settlements to Buckingham and the southern part of Aylesbury Vale, and that Haddenham could be a location for a new settlement The County Council stated it
fundamentally disagreed with a blanket assumption of an expansion of all larger villages and smaller villages; it considered that any village expansion should be on merit and considered on a case by case basis
How the issued raised have been addressed
3.24 The issues raised were reported to the VALP Scrutiny Committees (11 May, November 7
2016) along with information about what was to happen next This included the collation
of further or revised evidence and formulating policy in response to all of the following: new evidence, the representations, views of Members at the intervening meetings, updated events such as new household projections or planning decisions on sites or neighbourhood plan progress
3.25 In terms of how specific issues have been raised:
A new Buckinghamshire HEDNA (Housing and Economic Development Needs
Assessment) was prepared, including South Buckinghamshire District Council and a draft report was published in January 2016 Further reports followed in 2016
The settlement hierarchy was revised in 2016 and a new category ‘Medium Villages’ was created taking in some of those previously classified as ‘Large’
A new settlement option for distributing growth was considered further with a New Settlement Scoping Study commissioned and ultimately published in summer 2016
Further HELAA (Housing and Economic Land Availability Assessment) work took place with a ‘version 3’ report finding capacity at Medium and Smaller villages
It was acknowledged in the consultation for the forthcoming Draft Plan that
infrastructure remained an evidence gap which would be filled once comments on the Draft Plan had been received
Trang 184 VALP Draft Plan - 2016
‘News For Parishes’ July 2016
4.1 The formal public consultation was accompanied by a request from AVDC for each parish
and town council website to display a statement ‘News for Parishes’ of publicity provided
by AVDC explaining the public consultation
4.2 There was an advertisement on mix 96 radio station on 3 June 2016
and-a-brand-new-town/
https://www.mix96.co.uk/news/local/2004421/33000-new-homes-for-aylesbury-vale-Parish and Town Council Presentation/Information session, July 2016
4.3 On 13 July 2016 an engagement event took place with parish and town councils held at
Aylesbury Gateway All parish and town councils were invited to send a representative; 67 people attended
4.4 An officer presentation shared information on progress of preparing the plan, the findings
of further evidence including the HEDNA, HELAA and green belt review and, the
application to make Aylesbury a Garden Town A key area discussed in both the
presentation and question and answers was what the emerging Draft Plan housing target and settlement hierarchy meant for individual settlements/parishes and neighbourhood plans in preparation
Draft Plan Public Consultation
4.5 From 7 July to 5 September 2016, consultation took place on the Vale of Aylesbury Draft
Plan
Publicity
4.6 See Appendix C for who was contacted by emailed letter or posted letter on 6 July 2016 on
this public consultation, in accordance with our adopted SCI
4.7 The Council webpages were changed for 7 July 2016 displaying:
the consultation document – the Draft Plan
new and updated evidence base documents including the Sustainability Appraisal
information about how to comment – the online comment form, how to write to the Council and email us
exhibitions to come and see displayed consultation material including the plan itself, talk to officers, make representations
4.8 A press release was made on 7 July 2016 notifying and briefing the media on the start of
the public consultation period on the Draft Plan and the exhibitions that will take place
Trang 194.9 80,000 VALP Summary Leaflets were distributed in the 'Change of bin collections days'
mailed to households a month in advance of the consultation starting, and displayed at Commercial AVDC roadshows and parishes where additional exhibitions were held 4.10 45 posters were printed and displayed in car parks, community centres and libraries 4 e-
bulletins were sent to 30,000 residents 1 tweet announced the consultation on 7 July
2016
4.11 The consultation documents including evidence base were made available electronically
on a memory stick, available on request either given at exhibition or posted
Exhibitions – July to September 2016
4.12 Exhibitions included static displays at locations including the AVDC Office at The Gateway,
Aylesbury and the swimming pools at Aylesbury and Buckingham, and a roadshow of manned interactive exhibitions around the Vale over the summer:
Manned Exhibition
Roadshow
Haddenham Village Hall Social Centre 11 July 11am-8pm
Buckingham Community Centre 13 July 11am-8pm
Aylesbury Friar’s Square Shopping
Centre
14 July 10am-5pm
Newton Longville Village Hall, 2 Paradise 27 July 10:30am-7.30pm
Wendover St Anne’s Hall 4 August 11am-8pm
Aylesbury Friar’s Square Shopping
Centre
5 August 10am-5pm
Whaddon Jubilee Hall 8 August 4pm-8pm
Winslow Public Hall 10 August 10am-8pm
Aylesbury AVDC Office, The Gateway 11 August 4pm-8pm
Weedon Bucks County Show 1 September
8.30am-4.30pm 4.13 There was an estimated average turnout of over 350 visitors per manned exhibition event
Consultation Questions
4.14 There were no specific consultation questions this time – it was simply inviting comments
on the VALP Draft Plan and supporting evidence
The Response
4.15 More than 1,600 responses were received, comprising over 5,000 comments
Trang 20Summary of the main issues identified
4.16 A summary report (57 pages) of the response and the actual response content received
has been published at https://www.aylesburyvaledc.gov.uk/valp-previous-consultations
Set out below is an overview of key themes and issues raised by respondents in their responses to the Vale of Aylesbury Draft Local Plan consultation summer 2016 This is based on a extract from a summary report currently being drafted, therefore, the contents should be treated as provisional, incomplete, and may be subject to change in the final report The following is an extract of that report on the identified issues raised:
Housing Need and Housing
4.17 Direct or indirect reference to the need for Housing was included in almost all responses
The majority of respondents focussed on the 33,000 housing units’ requirement,
questioning this figure, with the general public objecting to the volumes and development bodies suggesting the figures could be too low, particularly with reference to specific land allocations
4.18 There was a marked dislike for the AVDC area potentially picking up unmet housing need
from neighbouring districts In particular it was strongly perceived that High Wycombe, was planning to allocate its own needs into the AVDC area Respondents strongly agreed with statements in the VALP that AVDC will resist actions of this nature
4.19 The volume of housing proposed influenced the discussion (as a cause) of the following
issues below Many respondents were concerned that the proposed housing volume will fundamentally alter the character of the existing villages and communities and result in
‘infilling’ development throughout the area Another concern is that the increase will mainly serve for an increase in demand for housing from London and other areas resulting
in an increase in commuting and would not serve the needs of existing communities 4.20 A minority of respondents brought up the issue of Brexit and its potential impact on future
housing needs for the area not being sufficiently incorporated into the VALP
Transportation Infrastructure
4.21 This concern went ‘hand-in-glove’ with the concern over housing volume Respondents
noted that the proposed housing allocations will impact the ability of the current
infrastructure to handle additional demand and questioned the ability of the existing systems to absorb this increase Respondents questioned that recent traffic modelling and planning had either allowed for the VALP proposals, or that the VALP had adequately considered this issue in its planning stage The majority concern was for regional traffic (vehicular) although the upgrading of rail infrastructure and cycle routes were also
frequently mentioned
4.22 Traffic increase, with its attendant impacts on air quality, noise and community safety
(particularly around schools) was of concern to respondents The impact of traffic
volumes and mix on village roads and main feeder routes was seen to be an important issue including the impact on journey times into Aylesbury at peak times
4.23 A minority of respondents linked the requirement for transportation infrastructure in the
VALP with HS2 development and suggested that cumulative impacts required further investigation
Trang 214.24 Respondents were concerned that the proposed housing volumes would create significant
strain on the area’s infrastructure in general terms This includes the built environment, in addition to transportation infrastructure, (transportation infrastructure was often
mentioned as a separate concern) Respondents would have greater comfort in the VALP
if an infrastructure plan was available which took account of or incorporated the VALP proposals Respondents were not convinced that the infrastructure, as exists currently, would be able to handle significant increases in capacity and use
Transport
4.25 The concern of transport provision and capacity was highlighted as a separate concern to
the transportation infrastructure per se The capacity of bus route connectivity to main centres such as Aylesbury was a concern as well as access to the proposed rail
developments in the area
Services
4.26 With regard to the provision of services, social and structural to support the influx of
proposed new household levels, respondents were concerned that the current services (health, doctors, hospitals, schools, shops and pubs) would be overwhelmed by demand resulting in lower levels of access for current residents and loss of amenity Access to Doctors and GPs was a key concern along with education provision and availability of school places for the children and young people in the area
Conservation
4.27 This concern was strongly tied in to the possible impacts of development and change, to
the existing community infrastructure and character, surrounding landscapes and a worry that development will ‘infill’ areas destroying the Character of the area Respondents were protective of what assets they perceive their area already possesses and are
concerned that these will be lost under the VALP proposals
Affordable Homes
4.28 The need for affordable homes was raised by many respondents, who strongly agreed
with the VALP proposals on requirements for affordable housing A concern is that the provision for this in the VALP will not prove to be strong enough, or enforced, resulting in local residents being ‘priced out’ of their communities by the external demand This was a cross generational concern from current residents
Settlement characterisation
4.29 This was raised by respondents who disputed the community/village classifications in the
Settlement Hierarchy which informed the VALP and which, it was felt, opened up
communities to receiving larger development allocations All the general public
respondents who made a statement in this category felt that their community had been overstated, and therefore required the VALP to review this issue
Trang 22Consultation Process
4.30 The VALP consultation process itself was raised by respondents as a concern There were
three main areas of concern The first was the form itself Many respondents stated that they found it confusing and difficult to use The second concern was the timing of the consultation process, which, having occurred over the summer period, was seen as a holiday period which made it more difficult for those respondents to fully assimilate the information and participate in the process A number of respondents who had
participated in a presentational event stated that they found the materials available insufficient to properly understand the potential impacts on their local area
Neighbourhood Plans
4.31 Respondents questioned how the recently agreed and approved Neighbourhood Plans
(NPs) had, or had not, been taken into consideration into the VALP process NPs were widely seen to have reflected local community needs and agreements and many
respondents were concerned that this process had apparently been superseded by the VALP, with minimal cross fertilisation from the NPs This had the potential to disillusion participants with the local democratic processes
Agricultural Land
4.32 Respondents concerns were related to general conservation issues, with respondents
stating that it was undesirable that agricultural land should be used for housing
development
Employment
4.33 Respondents were concerned that the increase in household volumes would not be
supported by an increase in employment opportunities in the area, and that the result would be an increase in out of area commuting and additional social strains, potentially on the current residents for employment access
VALP Plan
4.34 Many respondents were positive for the VALP plan, seeing it as a statement of Aspiration
for the area, as well as proof that a range of key issues and positions had been considered
in the regional planning process However, these respondents also recognised that the delivery of the VALP will determine the success of the plan and most were concerned that this would not match the principles and approaches espoused in the VALP documentation Consequently the VALP was seen as a ‘positive step’ not necessarily the final answer These respondents outnumbered those who rejected the VALP plan as a cynical and unrepresentative process aiming to foist development on the region
4.35 Many of the Developer/landowner submissions questioned whether national Planning
guidelines had been followed and approaches to the VALP process suggesting that the VALP was unnecessarily restrictive in its approach to site allocation and density
Trang 234.36 This was a general response, mainly from neighbouring Authorities, as a statement of
recognising (and endorsing) the need for co-operation across District and Borough lines and to the wider area of potential influence Individual respondents tended to see co-operation as a mechanism to minimise the allocation of unmet demand from surrounding areas into the VALP area
Environment
4.37 A minority of respondents focussed on the environmental impacts of the proposed
development plans as a key concern, for biodiversity, water quality and habitat protection
It was referenced more widely by the site development responses which referred to site specific studies which concluded minimal impacts for the proposed developments
Development Management Policies
4.38 The draft local plan included a full suite of development management policies for
consultation They did not carry any weight at present and could be revised prior to
submission including to ensure consistency with any new Government planning policy requirements This would include the new starter homes requirement which had just received Royal Assent
The following policies were noted as being of particular interest:-
Affordable Housing Policy (S6) – this would require 31% affordable housing
The County Council’s parking standards (T1)
Policies to protect town and village centres (D10), and
The inclusion of an overall design policy (BE2)
Call For Sites – Updated position, July 2016
4.39 The Call For Sites webpage (which began at the end of the ‘Scope of the Plan’ consultation
with those sites submitted and was kept updated periodically with new sites thereafter) was updated on 6 July 2016 with the following text The text included a link to a summary report with all the basic information of the sites promoted, a set of location maps
showing the location of all the sites and a ‘Call For Sites’ form to send in more sites So as
at 6 July 2016, we had 407 sites promoted under the ‘Call For Sites’ process and those received at the Draft Plan would be added to those numbers Due to other work
commitments, the Call For Sites summary report and maps were not updated after 6 July
2016, but all sites submitted during 2016 up to the end of the Draft Plan consultation period were assessed in the HELAA study of capacity and maps and site details shown in that report
4.40 The following text is from the Council’s webpage summarising the position on received
Call For Sites promotions as at July 2016
In spring 2014, we carried out a Call for Sites consultation We asked developers and
landowners to promote sites, for any use, to be considered in the Vale of Aylesbury Local Plan (VALP) Sites submitted up to 5 September 2016 were included in HELAA version 4 Sites
submitted after this time will be included in future reviews of the Plan after its adoption
Trang 24There are currently 407 sites promoted as of 6 July 2016 The sites promoted do not indicate where we think future development should be they are just the views of site promoters Planning applications will continue to be determined in line with the adopted Vale of Aylesbury Local Plan (2004) policies until they are replaced by the VALP
The following summary report (6 July 2016) of Call for Sites submissions sets out key
information for all sites
To submit a site, please complete the following form
How the issued raised have been addressed
4.19 The issues raised were reported to a VALP Scrutiny Committee (7 November 2016) and
also what was to happen next This included the gathering of further or revised evidence, and the formulation of policy in response to all of the following: new evidence, the
representations, views of Members at the intervening meetings, updated events such as new household projections or planning decisions on sites or neighbourhood plan progress Table 3 to this consultation statement sets out the main issues and a council response as work proceeded towards the Proposed Submission plan
Website statement - December 2016
4.20 Changes to the VALP forward timetable and a likely reduction in housing numbers and a
new capacity approach for the villages were advertised on the Council website in
December 2016 as follows:
Changes to the Draft Vale of Aylesbury Local Plan 2016/17
The timetable for preparing the Vale of Aylesbury Local Plan (VALP) was extended to ensure that all essential evidence was in place before we submitted it for examination
The key reason for the delay was due to the complexity of the Sustainability Appraisal (carried out
by external consultants) and the task taking longer than predicted as a result This is a critical piece
of evidence which has to feed into the content of the Plan and, as such, we had to ensure there was sufficient time for this to be done thoroughly and to enable its findings to be taken into account There were a number of significant changes to the context of the Draft Plan after it was published in summer 2016, including:
The total number of houses we needed to plan for was reduced from 33,000 to around 27,000 due to an update to our housing requirements and other districts finding more capacity
As a result of the reduction in our housing figures, we suggested that the consideration of a new settlement should be deferred until we know the route of the Oxford-Cambridge Expressway
We moved away from the proposed percentage approach to apportioning development to
settlements, and instead used a capacity-led approach Please see the following The changes are set out in more detail in the December 2016 VALP Scrutiny Committee minutes
Trang 25VALP Progress Updates - April 2017
4.21 On 7 April 2017, a ‘Submission Draft Update’ was published on the Council website to
update on a short delay to the timetable towards Proposed Submission to allow for the completion of further evidence gathering to be completed (particularly Transport
evidence, the Sustainability Appraisal, SFRA Level 2 and Sequential Test on Flood risk) and
to be able to take account of the findings of those studies On 21 April 2017 an
Explanatory Note was published on the Council’s website to explain the changing
approach being considered for the VALP to determining the level of development in the villages as a number of queries have been raised as to how the approach will apply to those areas currently preparing neighbourhood plans
May 2017 Re-consultation
4.22 As part of our process of continuous quality checking, it came to our attention that some local plan consultees may not have received specifically addressed communication at the time the draft VALP was published for consultation In order to ensure that everyone who may have wished to comment on the draft plan was able to do so, we wrote to these consultees to invite them to make comments if they had not already done so This was done via email for those consultees who had provided an email address, and by letter to those who had only provided a postal address
4.23 The first paragraph of the letter sent out was as follows:
Last summer we undertook public consultation on a draft Vale of Aylesbury Local Plan This involved a flyer to all households in the Vale, ten public consultation events, static exhibitions and coverage in the local media As part of our process of continuous quality checking, it has come to our attention that some local plan consultees may not have received specifically addressed communication at the time the draft VALP was published for consultation last summer In case you had not been aware that the plan had been published for consultation, we are giving you the opportunity to comment now on the draft VALP before it is finalised in the next few months If you have already responded, please be assured that your comments are being taken into account and there is no need to comment again
The Response
4.24 Summary of responses to VALP further consultation May 2017
A total of 17 responses were received as follows: Utilities (CLH Pipeline x2), Parish Council (1), residents (5) developer/agent/landowner interest (9)
Summary of the main issues identified
A report has been published on the Council website
https://www.aylesburyvaledc.gov.uk/valp-previous-consultations
4.25 The following is a selection of key issues raised in the May 2017 consultation:
• North Marston Parish Council note that North Marston is a small village with few
facilities available They consider the school would be unable to cope with housing
Trang 26growth, noting that the transport network is poor and their village lacks the capacity to support a larger amount of housing
• Concern about agreeing housing numbers for Aylesbury Vale before Wycombe,
Chiltern and South Bucks have consulted on a housing figure for their areas
• Uncertain implications of the Housing White Paper
• Homes on newly built estates are too expensive and out of reach to normal
people Council representatives should say what is needed, otherwise find a builder who will
• The new homes being built are bland in design terms Even though land is
expensive and in demand, straight roads with terraced houses make more
housing
• Ecology: with the decline of bees and other useful insects, each house should have
a small front garden and a larger one at the back and include a safe place for small children to play
• All houses built should be for people who were born, reside or have connections with this area Young people have to move far away to find a home
• Concern about not receiving consultation material last year
• CLH Pipeline submitted two maps regarding a pipeline that runs through the
borough
4.26 Further site promotions were received in the May 2017 re-consultation:
Land at Adstock
New Settlement at Haddenham
Land at Aylesbury Golf Club, Bierton
Land South West of Weston Turville
Land at Hollingdon Road, Hollingdon
Land at Finmere Aerodrome Tingewick
Land adjacent To Raven Crescent and Linnet Drive, Westcott
4.27 Issues raised by site promoters included the following:
Further consideration should be given to identifying and meeting Objectively
Assessed (Housing) Needs (OAN)
Talk to neighbouring authorities to ensure unmet needs are met
A capacity led approach will not deliver the OAN While understanding the
capacity for each settlement is important, this should not be a limiting factor to development
The Draft Local Plan, as currently written, is unsound with respect to delivery The
proposed phasing of the housing requirement does not plan positively to address the District’s short-term housing need and would fail to provide a five year supply
of deliverable housing The Plan over relies on the delivery of very large
allocations, which will be slow to deliver and vulnerable to unanticipated delays
Limitations of 10 year migration trends In line with Professor Simpson’s research
referred to in the HEDNA, it would be more prudent to use the existing
demographic profile from the 2014-based projections rather than the 10-year adjusted projections
Following the LPEG report and the Housing White Paper (Fixing our Broken
Housing Market), a common OAN methodology is to be published for consultation Were this based on an LPEG approach there would be an uplift of 2,624 dwellings
Trang 27above the current proposals for Aylesbury Vale The Council should follow this approach in relation to migration trends in any subsequent consultation of the VALP
The Council would be unwise to halt progress on identifying a location for a new settlement until a Local Plan review as this important component of the
requirement for the District should be planned for in the current Plan Period
Haddenham can take more growth than indicated in the January 2017 HELAA and
September 2016 VALP consultation draft Evidence points towards Haddenham as the most appropriate location for a new settlement, which should be included as a preferred option in the Submission Local Plan and favour an approach which would increase growth to the village, over proposals for a new standalone
settlement
Would expect to see the inclusion of high level infrastructure and projects needed
to support the Local Plan and wider strategic initiatives planned for the Aylesbury area Evidence supports the use of the existing social and community
infrastructure at Haddenham to enable increased growth in the village
Growth south and west of Aylesbury has been sterilised by the proposed route
for HS2 Therefore, the focus for new development needs to be elsewhere
The restriction to only allow further development in exceptional circumstances at Bierton and Western Turville in paragraph 4.78 does not allow for the flexibility the NPPF requires
Wendover cannot be completely divorced from a strategy for development,
though the Council should be mindful of the Housing White Paper with regard to Green Belt
Support Draft Policy S3, insofar as it allows for future development at the village of
Westcott
Policies D7 and D8: The wording of D8 is very restrictive for villages that have
opportunities to provide small scale development Such development should be proportionate to the size of the village and have no outstanding material
considerations to address
Disagree that smaller villages and settlements have not been allocated any level
of residential development in the Plan Development should be distributed evenly across the District to spread the impact of new homes across services and facilities available The development of a small scale residential scheme in a small village will assist in the provision of homes for local people as the community grows
Support aspects of Draft Policy D7 with regards to directing new development to the edge of existing settlements However the Policy is unsound as parts are
inconsistent with national planning policy and the Framework’s objective to significantly boost housing supply The wording of the second paragraph is vague and should be revised
Due to cost it can often be difficult to deliver specialist housing for older people in
parallel to traditional residential development Specialist housing for older people such as Continuing Care Retirement Communities (CCRSs) often require greenfield sites that may not otherwise come forward for general housing The Plan must therefore be sufficiently flexible to support the development of specialist housing for older people to meet identified need
The Plan should reflect national guidance and make provision for the
redevelopment of existing employment sites, including Vale Industrial Estate, in
order to meet housing needs Draft Policy E2 conflicts with the NPPF in applying a
Trang 28level of protection outside key employment areas and which may not be required
to be retained for employment
Clarity sought with regard to the number of new homes that RAF Halton could
deliver and whether new homes replacing those on the barracks would count as
‘new homes’
4.28 In terms of response to the issues raised at the Draft Plan stage – please see
Table 3 in Appendix A
Trang 295 VALP Proposed Submission – 2017
(Regulation 19)
Stakeholder Forums prior to Public Consultation, 2 and 4 October 2017
5.1 The formal public consultation was preceded by stakeholder forums All district
members were invited to an event on 2 October and all parish and town councils were invited to send up to two representatives to an event on 4 October
4 October 2017 Parish Forum - How bodies and persons were invited to make
comments
5.2 An officer presentation shared information on progress of preparing the plan, provided
an update on the Duty to Co-operate, introduced the Infrastructure Delivery Plan as a recent submission to the evidence base, and discussed the current weight of the Plan
as well as forward timetable A Buckinghamshire County Council officer also presented further on infrastructure delivery and submission of a bid for the Housing
Infrastructure Fund This was followed by a visual demonstration of how to comment
on the online consultation system and an accompanying leaflet handout, ‘How to make your views known’, was distributed There was then a question and answer session where those attending could raise queries and comments 57 people attended
5.3 Two key areas were discussed in both presentation and question and answers The first
was the spatial strategy, in particular the site allocation process in terms of the
settlement hierarchy and its relation to Neighbourhood Plans The second was the potential changes to housing numbers if the Plan were not submitted before the end of March 2018, due to the Government’s proposed standardised calculation for
objectively assessed housing need (OAN)
Proposed Submission Consultation
5.4 The main consultation ran from 2 November to 14 December 2017 (6 weeks)
Comments on the early draft of the Proposed Submission Plan
5.5 On the penultimate day of the consultation, the Council became aware that an earlier
draft version of the Plan could be accessed online through the Council’s website This was the case even though the main VALP consultation page – to which the vast
majority of respondents referred – contained the link to the most up to date draft The responses which referred to the older draft were identified, six in total, and carefully reviewed The Council’s view was that none of these six consultees had been
prejudiced by referring to a previous draft However, in an abundance of caution these six consultees were notified and given an extended deadline of 15 January 2018 to submit any amended or further representations on the changed elements of the Plan which were minor Five of the six consultees responded
Trang 305.6 Further checking during the processing of representations in the New Year identified a
further three responses referring to the older draft were identified Again, these respondents were contacted and given an extended deadline to submit amended or further representations on the changed elements of the Plan Two of the three
consultees responded
Publicity
5.7 A letter was emailed or posted on 24 October 2017 to all statutory consultees and
active consultees on our mailing list This correspondence encouraged consultees to activate their account on the consultation system or register a new account It included
a web link to the consultation system and provided information on other ways to respond A further letter was sent on 1 November 2017 informing consultees of the impending start of the consultation This provided a link to the Vale of Aylesbury 2013-
2033 page of the website, a list of which documents were available to view and further information on using the consultation system Also included were a Statement of Representation Procedure and a Statement of Availability, the latter of which listed the opening times of all the locations where documents could be viewed An emailed letter was used where there was an email address, otherwise a printed and posted paper letter was relied on See Appendix C for who was contacted by emailed letter or posted letter on this public consultation, in accordance with our adopted SCI
5.8 The Council webpages were changed for 2 November 2017 displaying:
the consultation document – the Proposed Submission Plan
the publication documents, including supporting evidence base and drafted topic papers
the Statement of Representation Procedure and Statement of Availability,
providing information on the documents available to view electronically and in hard copy as well as the location information to access hard copies
How to comment – the online comment form, how to write to the Council and email us
A slot on the rotating images on the main Council homepage to drive people to visit the VALP pages
5.9 The consultation publication documents, including evidence base, were made available
electronically on a memory stick, available to be posted on request
5.10 The consultation was advertised in the July and November edition of the Aylesbury
Vale Times, the magazine for residents of Aylesbury Vale which is distributed to 80,000 households
5.11 An article was published in Aylesbury Town Matters, Aylesbury Town Council’s
publication
5.12 An opinion piece was published in the Bucks Herald
5.13 Posters were displayed in town centre car parks, community centres, libraries, internal
Council noticeboards and sent to parish councils
Trang 315.14 Content in the MyAccount e-newsletters for August, September, October and
November informed 44,000 MyAccount holders of the upcoming consultation
5.15 An animated ‘Powtoon’ video on the progress of the Plan was posted on the Council’s
website, Facebook page, Twitter feed and YouTube account
5.16 4 posts on the Council’s Facebook page announced and advertised the consultation, as
well as 11 tweets
5.17 The consultation was announced and promoted on mix 96 radio station on 23 October
and 7 December
5.18 There were press releases in October, November and December to generate coverage
in local and regional media
Consultation Questions
5.19 Consultees were encouraged to frame their comments within the context of the Plan’s
soundness, legal compliance and compliance with the Duty to Co-operate Both the form on the consultation system and the downloadable document response form had tick boxes for respondents to explicitly state a yes or no answer on these three
elements, as well as selecting which of the four tests of soundness they felt were not fulfilled The response also had ‘free text’ fields to enter a full representation, a
summary and suggested changes to the Plan Respondents were also required to indicate whether or not to participate in the oral examination and how to be notified about future updates on VALP According to paragraph 182 of the NPPF, the four ‘tests
of soundness’ are defined as:
Positively prepared – the plan should be prepared based on a strategy which seeks to meet objectively assessed development and infrastructure
requirements, including unmet requirements from neighbouring authorities where it is reasonable to do so and consistent with achieving sustainable development;
Justified – the plan should be the most appropriate strategy, when considered against the reasonable alternatives, based on proportionate evidence;
Effective – the plan should be deliverable over its period and based on
effective joint working on cross-boundary strategic priorities; and
Consistent with national policy – the plan should enable the delivery of
sustainable development in accordance with the policies in the Framework
Methods of Feedback
5.20 We received feedback by the following methods:
an online consultation system was the Council’s preferred method of feedback: https://aylesburyvaledc.jdi-consult.net/localplan
or written to AVDC at the Gateway offices
Trang 32The Response
5.21 988 responses were received, comprising 2441 comments Of the original responses
658 (67%) were made via the online consultation system, 262 (26%) were submitted via email and 68 (7%) were posted paper responses
Summary of the Main Issues Identified
5.22 This section summarises the main issues raised at the proposed submission publication
stage It is not intended to be a definitive list of all representations received; it is a broad summary of the main issues raised (in accordance with Regulation 22(1)(c)(v))
5.23 The main issues raised are summarised below For each policy or supporting text the
total number of representations are identified, which is then broken down into how many representors supported or objected to the plan
SA - The SA for the VALP fails to appropriately consider alternatives,
alternatives suggested include looking at a smaller scale of growth for Aston Clinton, looking at NLV001 combined with NLV020, a variation with some growth at edge of MK and reduced amounts at strategic settlements and options relating to higher levels of growth
HEDNA - There are a number of comments on the HEDNA some in support but more in objection, relating also to the comments made on S2 Comparison is made between older versions of the HEDNA and the newer ones where the OAN has reduced
The plan fails to recognise the Oxford to Cambridge growth corridor and the NIC work done in relation to this The Government’s proposed standardised method to calculating the OAN is commented on too It is suggested that additional provision for housing should be made in the context of these two issues
Unmet need - There is support for unmet need being provided for in Aylesbury Vale but also comments saying further work should be done to find more capacity in the southern bucks authorities – suggestions include increasing density, more capacity at Princes Risborough, further additional sites Concerns have also been raised that in the future there is likely to be additional need identified for Aylesbury Vale through the issues mentioned above may mean the unmet need can’t then be met
DTC - There is little evidence of cooperation with councils to the north of the district, particularly Milton Keynes, specifically concerning the proposed spatial distribution and allocation at the edge of Milton Keynes, provision of a bypass, and the East to West rail link The Buckinghamshire authorities have not cooperated enough on employment needs
Trang 33 The best fit HMA identified is ‘convenient’, in reality it’s more complicated and the needs of the wider region should be looked at
It is suggested there should be a additional policy on Canals
Reliance on large MDAs being delivered quickly around Aylesbury is optimistic
Infrastructure – not enough focus on road capacity, footpaths, Stoke
Mandeville Hosptial, Chiltern railways services, Tring train station, broadband, sewerage
Neighbourhood planning – further growth at places that have a neighbourhood plan should be decided by the local community through the neighbourhood plan process– e.g Buckingham and Stoke Mandeville VALP undermines
neighbourhood planning
5.25 Chapter 2: Vision and Strategic Objectives
Total number of Comments received 49
Main issues:
Spatial vision doesn’t mention the growth of Milton Keynes
The vision and objectives do not give enough emphasis to the Chilterns AONB
There is no policy regarding education that will deliver the vision
Supported 16 S3 Settlement hierarchy and cohesive development Objected 44
Trang 34Mains issues:
Policy S1
Having such a large amount of growth concentrated around Aylesbury will lead
to more traffic problems, this is not sustainable
Policy S2
HEDNA
Comments were made questioning the latest assessment of housing need in the HEDNA with comparisons being made to previous assessments which produced a higher OAN, saying it shouldn’t be lowered at a time of pressure for increasing housing delivery
Most comments made stated the OAN should be higher, with a number of detailed technical reports and comments identifying why
OAN
There are also comments suggesting the plan should adopt the Governments proposed OAN methodology now in VALP which would mean 30,000 new houses over the plan period plus 8,000 unmet need, and not leave it until a Local Plan review
As it is considered that the OAN is underestimated significant additional
allocations should be identified
The housing requirement should be expressed as a minimum
Concerns have been raised that the plan is proposing too much housing and the impact this will have on wildlife
Unmet need
The plan should acknowledge that the 8,000 unmet need is provisional
depending on the examination of Wycombe and South Bucks/Chiltern’s Local Plan
There is a suggestion that unmet needs shouldn’t be taken from the part of South Bucks that is outside the functional HMA
If the capacity cannot provide for the unmet need on top of such a increase in Aylesbury Vale’s own OAN then it is questioned whether the MOU is useless
Comments made that Aylesbury Vale should take some of Luton’s unmet needs
There is a objection to taking any unmet needs and the suggestion the
acceptance of this should be delayed
The housing need should be met closest to where it arises Only the southern part of Aylesbury Vale is well related
In terms of the new settlement option some suggest this in addition to existing allocations and some instead of so much growth at Aylesbury or other existing settlements
Trang 35 There are also the suggestions of various other amendments to the distribution
of growth including that there should be more growth on the edge of Milton Keynes instead of Aylesbury or Buckingham, more growth at Haddenham, more growth at Buckingham, both the more and less growth at Aylesbury, both more and less growth at RAF Halton
Objections were raised to the amount of housing around Aylesbury and the impact this would have on its character, the AONB, coalescence with surrounding villages, the roads and other infrastructure Concern is raised that there isn’t enough employment in the town for these houses If this amount of housing is proposed at Aylesbury a full ring road is needed
There is a concern that the transport effects of Aylesbury Garden Town haven’t been considered alongside the growth at Wendover and Princes Risborough or other impacts from outside the district
Objections to the allocation of sites in Buckingham and Winslow above the amount of growth set out in the neighbourhood plans and comments that the location of further growth should be decided by a review of neighbourhood plans
Suggestion there should be more growth at Aylesbury and Buckingham
Concerns about coalescence between Halton and Wendover and the impact on infrastructure
Comments are made that Halton should be treated separately to Wendover and just as a smaller village There is also support them to be considered together as the growth will impact on both settlements
Objections to the amount of growth proposed at Maids Moreton, which is higher than growth proposed at the other medium villages
Suggestions that Brill and Marsworth should be classed as smaller villages
Surplus and vacant existing employment sites can be released for allocation of housing rather than so much greenfield land
A number of additional sites were put forward for allocation, mainly for
housing sites, including (but not exclusively):
o Land at Buckingham Road, Winslow - Crevichon Properties Ltd 31845
o NLV020 (SWMK phase 2) - SWMKC 32287
o Number of sites to the south west of Milton Keynes - Marrons planning
29372
o CAL003 - FCC Environment 32265
o Marsworth Airfield - Ainscough Strategic Land 32319
o Land at Gawcott -The University of Buckingham 31844
o Land south of Gawcott – Mr T Annable 32241
o Waldridge Garden Village to the east of Haddenham - Waldridge Garden Village Consortium 32314
o Greenway Project, Land north of Winslow - Amarillo Ltd & Scandale Ltd
32109
o Berryfields, East Aylesbury - Arnold White Estates 32001
o North of Waddesdon - Arnold White Estates 32001
Trang 36o Land East of Fenny Road, Stoke Hammond - September Properties
32277
o HAD002 - Richborough Estates 32286
o GHW013 - Taylor Wimpey South Midlands 32254
o Eaton Leys, Milton Keynes - Gallagher Estates Ltd 32326
o Finmere airfield - Corbally (Finmere) Group and Mrs Vanessa Tait
32293
o Haddenham Airfield, Haddenham - Lands Improvement Holdings (LIH)
32300
o Land South West of Weston Turville - Bellway Homes 32302
o Site adjacent Leighton-Linslade - Paul Newman New Homes 32292
o BIE027 and GUW008 - CALA Homes Limited 32297
o Stoke Mandeville sites - Manor Oak Homes 29966
o Land at Winslow Road, Wingrave- Careys New Homes 32267
o Land at Calvert Green - Persimmon Homes Midlands 32264
o Land at Cheddington - Society of Merchant Ventures 32202
o Land West of Canal and south of Halton Lane, Wendover - Manlet Group Holdings 32324
o Land north of Aylesbury Road, Wendover - CEG 32243
o AYL087 – Aviva Life & Pensions 32283
o Brook Farm, Broughton - Land at Brook Farm 32131
o Fleet Marston, Aylesbury - Barwood Land and Estates 32310
o Additional land at Rabans Lane, Aylesbury - Aylesbury Vale Estates LLP
32240
o
Delivery
It was suggested that the plan needs greater flexibility/contingency
Comments were made about the delivery rates, particularly about large
strategic sites not being able to deliver as needed with suggestions that there is
an over reliance on these It was suggested that more smaller sites should allocated in the larger and medium villages
Comments were made on whether Aylesbury can deliver such high levels of housing and whether market saturation will be reached
It was suggested that there needs to be a higher allowance for
non-implementation than the 5.2% buffer currently proposed
The use of reserve sites was suggested
It was stated that VALP doesn’t deliver a robust 5 year housing land supply against VALP’s housing requirements
Employment
There is a lack of justification for Aylesbury Vale meeting the unmet
employment needs of the southern Bucks authorities, Aylesbury Vale has poor connectivity and is unlikely to meet B8 requirements and sites delivered
The site selection and SA process is flawed
Comment that the employment provision should be higher for the amount of housing
Other
Preparation of the Charging Schedule should be undertaken alongside the VALP as the two documents will directly influence the deliverability and sustainability of one another
Trang 37 The Sustainability Appraisal of the VALP, states that a more dispersed approach was examined but no further detail is provided within the SA, this should have been examined as a alternative option
There needs to be up to date flood modelling for sites WTV018, BIE022 and STO016 to satisfy that the sites can accommodate the proposed amount of development
Milton Keynes should be recognised as a strategic settlement in the settlement hierarchy, otherwise its role is undermined
Policy S3
A number of comments state that the Aylesbury Vale District Council does not adhere to its own policy, as the planned developments at Halton, Hampden Fields, Stoke Mandeville and BUC043 in Buckingham lead to coalescence and the diminishing of settlement identities and are therefore contrary to this policy
Comments have been made stating that the commitment to the preservation
of the character and identities of settlements and the prevention of coalescence is important, but the wording in the supporting paragraph 3.22 is too weak to ensure this
Comments have stated that the proposed hierarchy is considered the
appropriate way to deliver housing requirements
Comments have been made stating that there is an over-reliance on a small number of development locations to achieve housing targets
Comments request that additional development should be allocated to the identified Large and Medium villages
A comment requesting a third criterion to prevent development that would harm the Chilterns Area Of Outstanding Natural Beauty or its setting
One comment requested for settlement boundaries to be defined
Comments requested the housing requirement to be expressed as a minimum figure
Comments state that the wording of Policy S3 is too restrictive, which will
prevent the delivery of necessary levels of development
Policy S4
Objections to the removal of land from the Green Belt at Halton It isn’t
considered any less important that the Green Belt in Southern Bucks and should be kept to preserve the AONB That the site is already developed is not justification to remove it from the Green Belt Any redevelopment should not reduce its openness
There are also objections to the allocation of housing at RAF Halton if it’s still within the Green Belt
Support for the removal of land from the Green Belt to the north of Wendover
no longer being proposed
Support for the extension of the Green Belt to the west of Leighton Linslade and also objection to this based on the failure to demonstrate exceptional
circumstances
Policy S5
There is concern that sufficient infrastructure will not be delivered in reality Specific mention is given to infrastructure to support RAF Halton allocation and the funding/delivery of the link roads around Aylesbury, roads infrastructure in rural areas
Trang 38 The existing infrastructure is already under strain, it is important that the necessary infrastructure is delivered up front or early in the provision of new development The wording on this should be strengthened
Concern is raised that this policy is looking to address existing deficiencies, it should only be sought where they are necessary to make the development acceptable
More detail is required about the infrastructure that is needed
Where larger sites are under different land ownerships the delivery of
infrastructure needs to be ensured by having the appropriate mechanisms in place
There should be more recognition about East to West Rail and Oxford to Cambridge arc
There is also a number of support comments for this policy
Policy S6
The policy does not mention the requirement to monitor Gypsy and Travellers
or have a enforcement plan
Objections have been made to the allocation of Oaksview, Boarstall This has been recently refused permission, there is a over supply of sites in the area, it
is close to the MOD sites and prison, the site has a dominant and unnatural impact on the open countryside and would have a detrimental impact on the area, overlooks residential properties, has poor access to services and it doesn’t meet the criteria in D10 The site does not appear to have a sewerage connection, groundwater aquifers would need to be protected from pollution if
it does need disposal set up
Allocations should only be made for those that meet the definition, not those that are unknown, reducing the amount of allocations needed to just existing
sites that meet the criteria of policy D10
Policy S7
Five comments were supportive of Policy S7 and 10 were objections
One comment stated that the wording of Policy S7 was problematic as
‘previously developed land’ can be ambiguous
One comment requested a caveat in Policy S7 regarding the impact
development has on local character
Comments have stated their support of Policy S7, but have also noted that it is important the policy is not read such as to prioritise previously developed land over green field land for development
Policy S8
Comments were made stating that the allocation of specific sites in
Neighbourhood Plan Areas prejudges the Neighbourhood Plan process, and that S8 needs to ensure that neighbourhood plans are the principal vehicle by which allocations are made
Comments requested for Policy 8 to include a requirement for Neighbourhood Plans to be reviewed to ensure that the contribute towards the strategic policies of the VALP
Made comments stated that Policy S8 is not clear as to what weight
Neighbourhood Plans are to be given in the planning process and what the relationship between VALP and existing Neighbourhood Plans is
Policy S8 has received comments supporting it on the basis that it reinforces the need for Neighbourhood Plans, and that it recognises that Neighbourhood
Plans should be in general conformity with the strategic policies of VALP
Trang 39 It should be ensured that the allocations are deliverable within the expected time period and enough have been allocated
The delivery rates are ambitious and a significant increase, therefore a greater buffer should be used with further allocations to allow for flexibility
The windfall allowance should include larger sites than 4 dwellings too and therefore would be a higher number than 962
Two comments stated that Policy S9 should include a schedule of reserve sites
to be released if monitoring indicates a shortfall in the five year housing land supply position
Comments requested for Policy S9 to specify that the Plan will undergo an early review
A number of comments were made on specific issues on specific sites
Comments were made supporting references to settlement’s historic
environments in site allocation’s supporting paragraphs
5.27 Chapter 4: Strategic Delivery
Aylesbury
Supported 1 D-AYL052 PO Sorting Office, Cambridge Street,
Aylesbury
Supported 0 D-AYL059 Land at junction of Buckingham Street and
New Street, Aylesbury
Objected 2 Supported 0
Trang 40D-AYL077 Oaklands Hostel, 3 Bierton Road,
settlements, larger villages & medium villages
Supported 3 D-BUC043 Land West of AVDLP allocation BU1
Moreton Road, Buckingham
Supported 1 D-BUC051 West Buckingham, Land bound by
Brackley Road and the River Great Ouse
Supported 1 D-BUC046 Land off Osier Way (South of A421 and
East of Gawcott Road)
Supported 0 D-HAD007 Land North of Rosemary Lane Objected 12
Supported 2
Supported 5 D-WIN001 Land to East of B4033, Great Horwood
Road
Objected 19 Supported 0 D-SCD003 Land at Queen Catherine Road Objected 2
Supported 0 D-SCD008 Land at Molly’s Folly/Molly’s Field, West
of Addison Road
Supported 0 D-STO008 Land South of Creslow Way, Stone Objected 1
Supported 1
Supported 1 D-CDN001 Land North of Aylesbury Road and rear of
Great Stone House
Foscote Road
Supported 1 D-MGB003 Leopold Farm and area to the West Objected 1
Supported 3 D-NLV005 Land South of Whaddon Road and West
of Lower Road, Newton Longville
Objected 3 Supported 0 D-QUA001 Land South West of 62 Station Road Objected 0
Supported 1 D-QUA0014-016 Land adjacent to Station Road,
Quainton
Supported 1 D3 Housing development at smaller villages Objected 10