Virtual Pre-Bid Conference PresentationUNIVERSITY OF MAINE AT AUGUSTA Campus Welcome Center Augusta, Maine March 19, 2020... Project Document Access and Communication Review THE FOLLOWIN

Trang 1

Virtual Pre-Bid Conference Presentation

UNIVERSITY OF MAINE AT AUGUSTA

Campus Welcome Center

Augusta, Maine

March 19, 2020

Trang 2

UMA and UMaine System

Ann Vashon – Project Manager, Capital Planning and Project Management

Walter Shannon – Assistant Director of Capital Planning and Project Management

Harriman Team

Will Gatchell – Architect, Project Manager*

Mark Lee – Principal-in-charge

*All questions and Bid RFI’s should be addressed to Will Gatchell: wgatchell@harriman.com

Trang 3

1 Project Information: Document Access and Bid Dates

2 Scope of Work and Project Goals

3 Project Overview

1 Site

2 Building

3 Plans

4 Project Phasing and Sequencing

4 Project Document Access and Communication Review

THE FOLLOWING PRESENTATION IS AN OVERVIEW AND OUR BEST REPRESENTATION OF EXISTING CONDITIONS BASED ON AVAILABLE ON-HAND PHOTOGRAPHY

Trang 4

IF YOU DO NOT HAVE ACCESS TO THE WEBSITE AND/OR ARE NOT ABLE TO ACCESS

DOCUMENTS, PLEASE EMAIL ANN.VASHON@MAINE.EDUAND

WGATCHELL@HARRIMAN.COM

Filed Sub-bids due: Thursday, April 02, 2020 at 3:00pm Refer to Addendum #1

GC Bids due: Thursday, April 09, 2020 at 2:00pm Refer to Addendum #1

THE FOLLOWING PRESENTATION IS AN OVERVIEW AND OUR BEST REPRESENTATION OF EXISTING CONDITIONS BASED ON AVAILABLE ON-HAND PHOTOGRAPHY

Trang 5

OVERVIEW-PROJECT SCOPE

CREATE A NEW CAMPUS WELCOME CENTER WITH RENOVATIONS TO RANDALL HALL

• NEW 8,300 SF SINGLE STORY ADDITION

• RENOVATE +/- 5,000 SF OF RANDALL HALL (TOTAL EXISTING +/- 40,000 SF)

• RELATED SITEWORK

PROJECT GOALS

• CREATE A NEW FRONT DOOR TO CAMPUS

• REORGANIZE STUDENT SERVICE DEPARTMENTS IN NEW ADDITION AND RANDALL HALL

• CREATE A LARGE, FLEXIBLE MEETING SPACE

• LIGHT TOUCH RENOVATIONS TO EXISTING OFFICES THROUGHOUT BUILDING

Trang 6

EXISTING CAMPUS-CONTEXT

I-95CIVIC CENTERUMA CAMPUSPROJECT SITE

UNIVERSITY DRIVE

CIVIC CENTER DRIVE

NORTH

Trang 7

EXISTING CAMPUS-CONTEXT

UNIVERSITY DRIVERANDALL PARKING LOT

RANDALL HALLPROJECT SITEKLAHR CENTERUNIVERSITY DRIVE

NORTH

Trang 8

EXISTING PROJECT SITE

1 NEW CONSTRUCTION AREA

2 RANDALL HALL RENOVATION

3 INFRASTRUCTURE WORK

5

5 6

Trang 9

EXISTING AERIAL VIEW

KLAHR CENTERRANDALL HALL

Trang 10

EXISTING SITE PLAN

KATZ LIBRARYKLAHR CENTERHOLOCAUST MEMORIALEXISTING PATH

RANDALL HALLRANDALL PARKING LOT

NORTH

Trang 11

PROPOSED SITE PLAN

KATZ LIBRARYKLAHR CENTERHOLOCAUST MEMORIALPROPOSED PATH

PROPOSED WELCOME CENTER

RANDALL HALL

NORTH

Trang 12

ENLARGED PROJECT SITE

KLAHR CENTERPROPOSED PATHWELCOME CENTER PATIONEW WELCOME CENTERRANDALL HALL

WELCOME CENTER ENTRY WALKWAY

PROPOSED PATH AT RANDALL PARKING LOT

Trang 13

3D VIEWS-PROPOSED

KLAHR CENTERPROPOSED WELCOME CENTERRANDALL HALL

Trang 14

ADDITIONAL EXTERIOR VIEWS

Trang 15

EXISTING SITE

Trang 20

EXISTING RANDALL-LOBBY

Trang 22

EXISTING RANDALL-BOOKSTORE

Trang 24

EXISTING RANDALL-CORRIDOR

Trang 26

EXISTING RANDALL-ADMISSIONS

Trang 27

EXISTING RANDALL-ADVISING AREA TO BE DEMOLISHED

Trang 28

EXISTING RANDALL-REGISTRAR AREA TO BE DEMOLISHED

Trang 29

EXISTING RANDALL-IT AREA TO BE DEMOLISHED

Trang 30

EXISTING RANDALL-STAIR

Trang 31

EXISTING RANDALL-2 ND FLOOR

Trang 32

MAIN ENTRY VIEW TO RANDALL

Trang 33

MAIN ENTRY

Trang 34

FUNCTION ROOM & PATIO

Trang 35

FLOOR PLAN-1A

Trang 36

FLOOR PLAN-1B

Trang 38

FLOOR PLAN-ROOF

Trang 39

PHASING PLAN

Trang 40

3 Phase III work shall include renovation of the first floor area containing the existing Advising, Registrar, IT

departments as well as renovation of the existing Enrollment and Information Services work area.

B The construction start dates shall be as follows:

1 Phase I shall be May 11, 2020.

2 Phase II shall be December 21, 2020.

3 Phase III shall be November 01, 2020.

C Completion dates for the work:

1 The work associated with the Campus Welcome Center shall be as follows:

Ngày đăng: 25/10/2022, 03:50