When interviewing procurement manager, the writer realizes that procurement department is facing with lots of problems including late delivery of equipment, poor quality of equipment, wr
Trang 1UNIVERSITY OF ECONOMICS HO CHI MINH CITY
International School of Business
-
MASTER OF BUSINESS ADMINISTRATION
LATE DELIVERY OF EQUIPMENT - THE CASE
STUDY OF KOREA NATIONAL OIL CORPORATION VIETNAM OFFICE
LE THI TUNG ID: 20150077
Ho Chi Minh City - 2017
Trang 2CONTENTS
Excecutive summary 2
Introduction 3
Overview of oil & gas industry in Vietnam 4
CHAPTER 1: PROBLEM IDENTIFICATION 6
1.1 Company background 6
1.2 Problem symptoms 7
1.3 Problem definition and importance of the problem 10
1.4 Problem existence 11
1.5 Potential causes of problem and the justification 11
1.5.1 Ineffective company policy 11
1.5.2 Inappropriate procurement procedure 14
Conclusion 19
Cause and effect map 21
Chapter 2: ALTERNALTIVE SOLUTION 22
2.1 Solutions 22
2.2 Solution comparison 22
2.3 Solution selection 23
2.4 Solution details 24
Chapter 3: ACTION PLAN 31
Appendix A: In depth Interview information 32
Appendix B: Terms and conditions 38
Appendix C: Procurement Procedure 48
Reference 61
Trang 3EXCECUTIVE SUMMARY
Korea National Oil Corporation is production sharing contract with Petro
Vietnam
Its activities take place in exploration
,
development,
and production of oil & gas in Block 11-2,
approximately 320 kilometers offshore VietnamProcurement of equipment is considered one of the most importance works of the company such as a factor determinant of revenues
,
expenditure costsTo build and
maintain a significant effect to organization
,
the procurement department needs to know that problems are affecting its businessWhen interviewing procurement manager
,
the writer realizes that procurement department is facing with lots of problems including late delivery of equipment,
poor quality of equipment,
wrong itemAmong many issues
,
late delivery of equipment will create significant impact to the project objective,
specifically for the project in the remote area such as offshore where access for transportation and delivery is geographically limitedIts existence
,
importance and causes have also been justified by interviewing with KNOC’s Procurement ManagerThe consequences are clarified late delivery of equipment leads to cost overrun and poor production capacity
Moreover
,
in order to findsolution for central problem
,
the writer makes an attempt to discover its possible causes which are ineffective company policy and inappropriate procurement procedureFrom those points
,
the solution for central business problem is determined to build a process for supplier selection and performance evaluation in order to work well for further purchase ordersThe company will take action on the third quarter of 2017
Trang 4
INTRODUCTION
Global business trends have led the oil and gas industry to seek better solutions to overcome the emerging challenges and critical issues
,
such as the need for procurement process based on new values and contextual factors including multi-cultural complexityOne way to overcome some of these critical issues is to adopt new innovative approaches
to suit different locations
,
countries or regions while trying to incorporate the differencesin business philosophy
,
culture or values within the oil and gas organization themselves into these approachesNew innovative approaches to procurement process are also required to meet the contextual needs found in different locations and countries around the world
These approaches also need to accommodate specific project needs and different values either in the business philosophy or culture within the oil and gas organization themselves
Oil and gas exploration and production is a highly risky business in a very complicated industry
It links government
,
owners of the natural resources with operators,
investors of private capital,
technology and equipment necessary for resource development,
in a single industry where the stakes and risks,
as well as the possible profit margins,
can be very highEffective procurement of equipment will have an impact on company's competitive advantage
The quality of equipment inputs to finish products’ quality as well as
stakeholders’ satisfaction and revenue
If the procurement process management is not Trang 5
effective and efficient input costs will rise and be a large part of the total cost
Being an important factor in determining revenues and cost
,
it is obviously seen that procurement has recently been receiving more attention within business industriesA comprehensive procurement guideline on selection processes to be used by decision makers in the industry should be developed and produced comprising a set of phases and critical steps that needs to be followed and performed during the selection process
The thesis will focus to identify and validate the existence of problem of KNOC and to improve the procurement procedure
Overview of oil & gas industry in Vietnam
Petroleum is currently one of Vietnam’s most promising areas for foreign
investment
,
and it could be the engine that carries the nation into the ranks of Asia's newly industrialized countriesAs a source of desperately needed hard currency and a catalyst for private sector growth
,
the petroleum industry could play a vital role in Vietnam’seconomic development
Oil and gas projects in Vietnam are implemented through joint ventures
partnerships involving multinational companies like British Petroleum
,
Petronas,
Nippon,
Chevron etc
Such partners supply capital and high technologies needed for oil and gas projects which Vietnamese partners are still lacking
The participation of foreign partners makes the projects suffer from risks such as differences in practices between domestic and foreign partners
,
policy and political risks,
financial risks,
legal and political risksThe inflation rate in Vietnam is quite high; while the national currency is relatively weak
Trang 6
Vietnam is located in South East Asia
,
a region considered the most dynamic and challenging in the worldThe quality of management in Vietnam is still below world standard as the country is emerging from a planned economy
The oil and gas construction projects in Vietnam pose lots of risks that can cause adverse impacts on project
implementation
Today
,
the industry continues to grow strongly implying demands for constructionof new oil and gas facilities
Oil and gas construction projects are often capital intensive
Hence
,
their successful implementation is strategically importantHowever
,
oil and gas construction projects are exposed to risks because of large capital investment,
involvementof many stakeholders
,
using of complex technology,
high environmental and social impactTrang 7
CHAPTER 1 PROBLEM IDENTIFICATION 1.1 Company background
The Vietnamese full name: Korea National Oil Corporation- VPĐH tại Vietnam
The English name: Korea National Oil Corporation - Vietnam office
Address: 10th Floor
,
Diamond Plaza,
34 Le Duan Street,
District 1,
HCM city,
VietnamKorea National Oil Corporation Vietnam office (KNOC VN) began its operation in Block 11-2 by signing a production sharing contract (PSC) in May 1992
After confirming gas reserves in the block through the drilling of three explorative wells
,
the company signed a tentative gas sales agreement with Petro Vietnam to secure a stable sales channelin December 2004
It soon concluded a construction contract and placed a construction order
,
beginning full development of the blockAs the sole operator
,
KNOC VN carries out exploration,
development,
andproduction activities in Block 11-2
,
approximately 320 kilometers offshore VietnamKNOC VN holds 75% of participating interest in this block on behalf of the Korean Consortium which consists of LG International Corp
.,
Daesung Industrial Com.,
Daewoo International Corp
.,
Hyundai Corp.,
Samwhan Corp.,
and Seoul City Gas CoLtd
PetroVietnam Exploration and Production Company (PVEP) holds the remaining 25% of the interest in the block
Production began on December 25
,
2006The average daily production of natural gas from the seven production wells in the block reaches 171 million standard cubic feet
The block’s recoverable volume is 770 billion standard cubic feet
Production will Trang 8
continue until 2024
Total reserves are 770 billion cubic feet
Daily production is 108 million cubic feet
Production period is from 2007 to 2024 (17 years)
It is KNOCVN’s first overseas operating project
Successful production in the Rong Doi and Rong Doi Tay fields marked a milestone not only for the company
,
but for Korea’s oil and gas industryKNOC VN employees were involved in all stages of
exploration
,
development,
and production,
including important negotiations,
drilling,
reserve estimation
,
and engineering and construction of offshore facilitiesNumber of employees: 164
Departments: 4 (Admin & Finance
,
Operations,
Drilling
,
Sub-Surface)Procurement Team belongs to Operations Department
Procurement team has five members (one Procurement Manager and one
Sr
.
Procurement Officer,
three Procurement Officers) take care of purchasing mechanical equipment,
electrical equipment,
logistic services and consumableAll are generally called equipment
remains unchanged
Report for yearly flight
Trang 9Year Description
Trang 10Report for transportation cost of chopper
Trang 11
Late delivery of equipment is the first reason cause to cost overrun
Year Description
The third reason is wrong item
The equipment has not been delivered correctly part number in accordance with the purchased order
It will take time to return back and receive the replacement
In accordance with report and information
,
it can be concluded that the issue of latein delivery materials and equipment is the central problem
1.3 Problem definition and importance of the problem
Al-Momani 1 stated that late delivery of equipment was a major cause of project delays along with notices to proceed being later to site
Ismail et al 2 indicated that late or Trang 12
irregular delivery or wrong types of material delivered during construction can lead to poor productivity and cost overrun
Flyvbjerg et al 3 defined that cost overrun is the difference between the actual cost at completion and initial budgeted cost
1.4 Problem existence
Based on the definition and information of interview
,
the company is now dealing with cost overrunFrom 2007 to 2012
,
the transportation cost from onshore to offshore was still the same for each yearThe company had been used equipment from spare parts that were purchased with main machinery of project phrase
From 2013 to 2015
,
company has paid a lot of money of each year for transportation cost from onshore to offshore for adhoc chopperThose each adhoc choppers have been using to carry critical equipment due to late delivery
Compared with Rosneft Vietnam (former TNK-BP Holding)
,
they recruitedqualified and skillful employees for procurement team
Rosneft also has appropriated procurement procedure to apply for worldwide offices
With high resource of human capital and supportive system
,
their procurement team has been working very efficiencyThey are seldom using adhoc chopper or supply boat to carry equipment onshore to
offshore for emergency case
1.5 Potential causes of problem and justification
1.5.1 Ineffective company policy
In accordance with the interview with Ms
Giang
,
The function of procurement is responsible to support company to procure equipment of the right quality,
at the most cost Trang 13effective price and ensure that equipment is available when needed
All equipment is purchased and delivered to KNOC warehouse at Vung Tau city
According to the need of end-users on Rong Doi Platfrom offshore
,
the equipment will be sent to offshore by supply boat or chopperNormally
,
the company runs two regular supply boats for every month to carry cargoes such as foods,
equipment to offshore,
and two regular choppers on Monday and Thursday of every week to bring manpower and small items of equipment to offshoreAll equipment is required delivery on-time in accordance with choppers’ schedule as well
as supply boat’s schedule
Among five members of the procurement team
,
there are two staff was shifted from document controlling departmentThose two staff has been assigned procurement works without experience and background
Their contributions were not met the
requirements
In accordance with job assignment
,
procurement officer is assigned a key person to act as the primary point of contact for suppliers on a daily basis maintaining pro- active communication channels with suppliers to ensure the equipment on-time deliveryBut some purchase orders were not on-time delivered
It is resulted from low response and decision making from procurement officers
When the seller informed issues of purchase orders
,
they do not know who to dealing with and take lot of time to make decisioninforming to seller
Some critical orders were failed when dealing with vendors because lack of communication and support within internal parties
Negotiation skill is a must for procurement staff
Negotiation can solve the disputes
of day to day works
Negotiation can be required as a result of procurement role in
challenging user identified requirement
This is important because through negotiations Trang 14
procurement professionals can ensure that the requirements are commercially sound and add value
Negotiations can also be applicable as a means of conflict resolution between the buyer and the supplier
In successful negotiation
,
a negotiator will obtain something of greater value in exchange for something on which he or she places a lower relative valueLack of negotiation skill was leaded to lengthy process results in which delays in the award of projects that lead increase in costs
From 2013 upto now
,
the company is facing with oil price deceasingCompany do not have training budget for staff
Without proper training
,
employees both new andcurrent do not receive the information and develop the skill sets necessary for
accomplishing their tasks at their maximum potential
Employees refer to training programs that provide information
,
new skills,
or professional development opportunities in order to fulfill their responsibilitiesTherefore
,
training program is a necessity in the workplace
Effective training and development programs aimed at improving the employees’ performance
The company is used the MBO (Management by objectives) program to evaluate employees’ performance
However
,
staff has not been received any feedback from human resource department for the result as well as salary increasingCompany did not increase salary for staff by 2014
Evaluating and ranking the employees working in organization are challenging tasks involving several factors
Each employee achieves certain performance levels in various factors and the resulting information can be overwhelming
An effective program should do more than set salary and promotion decisions on past performance
Trang 15
In many cases the procurement is technically very complex and uncertain as each project is unique
This means that procurement is a very important aspect within the industry and has an enormous impact on the profitability
Procurement activities are often depicted as a sequential process which reflects the different decisions made by different people with different authorities
Procurement process covers all activities from deciding
on a business need to committing to a supplier to satisfy that need
,
and ensuring that the outcome is acceptableShehzad 4 stated that among the five most frequent causes of oil & gas construction project delays were identified is shortage of skilled labor
Derek et al 5 explained on human capital and ways in which its effectiveness can be leveraged through procurement systems
Human capital consists of the skills
,
competences and knowledge and creative energy that employees bring an organization1.5.2 In-appropriate procurement procedure
According to the article 7
.
3 of procurement procedure,
selection of bidders is required work before sending inquiry to supplierSuppliers (Bidders) shall be selected based on their technical and financial capabilities
The following criteria may be considered for companies to be included in the Bidder List: experience
,
trackrecord
,
previous performance,
financial statement,
key personnel experience of companyBut there is no systematic process to select and evaluate supplier performance in KNOCVN procurement procedure
There is no logical and strategic decision on the supplier selection process
Most of the sourcing is based on experience of each individual Trang 16
procurement officer
Equipment will generally be procured from the familiar suppliers and/or suppliers in the record of Purchase Order and Contract
In addition
,
there is no record of the performance on other dimensions such as product quality,
delivery delay,
and etcThe procurement process of KNOC VN starts from the purchase requisitions generated by offshore engineers or onshore engineers
The purchase requisition is the document which contains the information of the required materials
,
such as quantity,
description
,
specification,
required on site date,
drawing,
and etcIn the purchase
requisition
,
the manufacturer or brand of each item will be clearly identifiedFor the standard or generic items
,
the purchase requisition creator may not specify the brand or manufacturer nameAfter receiving purchase requisition
,
procurement officer will request for quotations from the suppliersSubsequently
,
engineer will conduct technical evaluationof supplier’s quotation
,
if required,
while procurement officer will carry out pricecomparison
The purchase order will be awarded to the technically acceptable supplier who proposed lowest cost
There are many purchase orders with small value
The end-user raised a lot of purchase requisitions
Procurement officer sends all small inquiries to big suppliers but they do not combined all in one
The procurement officer does not realize that big
suppliers are busy and often do not pay their attention to small orders
Because
procurement officer required for many small purchase orders with small value
,
supplier does not agree to apply penalty clauseWith unsuccessful dealing with big supplier
,
procurement officer placed purchase order to the supplier which is a trading company
Trang 17without knowing that trading company does not have stock item until they got the
purchase order from their client
During purchase order processing
,
procurement officer did not require supplier send them shipping document for checking before sending to shipping agentIf any
mistake on these documents
,
it could delay customs clearancePurchase order closeout is the last step in procurement procedure of KNOCVN
It does not include the step of supplier performance evaluation
Equipment required for maintenance work will be sourced from local and oversea suppliers
Therefore
,
suppliers are one of the most essential components of the procurement process,
effective supplier selection and performance evaluation is considered to be one of the importantresponsibilities of procurement
The benefits of supplier evaluation are expressed in
various ways
Carr et al6 represented one common view when arguing that supplier
evaluation provides the buying firm with a better understanding of which suppliers are performing well and which suppliers are not performing well
Without tracking suppliers performance can lead to wrong supplier selection and poor supplier performance
Sambasivan 7 stated that poor supplier performance is one of the most significant causes in causing the construction delays
“Inefficient and poor performance of supplier” was identified as an important risk to address in the oil and gas industry of Vietnam
KNOC VN is not exception
The competence of supplier is always a source of concern for owners
In Vietnam projects often suffer from time delays
,
cost overrun,
low productivity,
and low quality due to suppliers failure to performance due to lack of financial ability
,
Trang 18relevant experience
,
trained manpower,
technology and equipment,
good management skills,
good construction methods and inadequate resource availabilityTypically in huge projects
,
there are many sub-suppliers working under main suppliersIf the sub-supplier is capable
,
the project can be completed on time as plannedThe project can be delayed if the sub-supplier under performs because of inadequate experience or capability
High degree of sub-supplying leads to high risk of delays and leads to inefficiencies in the oil & gas industry
Poor sub-supplier performance was identified on the top five reasons for delays Oil
& Gas construction project
The performance of the sub-supplier is one of the most
important factors governing project performance
,
as they physically carry out the work not the main contractorMany sub-suppliers lack qualifications or proper training
They reiterated further that it is difficult to identify their workers and properly train them and to endeavor to enhance their welfare and safety
Many sub-suppliers are not registered
,
operated with a minimum of paid up capitalAliya et al 8 concluded that subcontracting led to problems including unsatisfactory time and cost performance
There was the lesson learnt for sub-supplier on the nitrogen purging leak test equipment on shutdown campaign of 2013
When main supplier was awarded for contract
,
they called their sub-supplier to provide manpower to perform service
When he arrived at KNOC VN warehouse to check equipment for before sending to offshore
,
he did not pay attention to the tag on pressure valve that not met the technical specification as per on the contractAfter sending to working site at offshore
,
his crew recognized that the pressure of Trang 19the valve is under pressure and unable to install to processing system
Therefore
,
main supplier has hand-carried another pressure valve from oversea to Vung Tau and thecompany had been one addhoc chopper to send this valve to offshore to perform service in accordance with shutdown campaign schedule
There was another case of poor performance by sub-supplier
It was for leak test Nitrogen purging leak test equipment on shutdown campaign of 2014
Contactor submitted lifting certificates for nitrogen tanks which were still valid
However
,
the equipment was arrived KNOC warehouseThe HSE team of KNOC VN conducted a visual inspection all the gears were corroded so much
Therefore
,
main supplier was requested to do lifting service again and requested to change all new gearsLinh et al 9 concluded that to meet the high technology in the construction part
,
especially in oil and gas and petrochemical industry
,
the role of foreigncontractors/manufacturer is decisive
Almost equipment is purchasing from developed countries such as USA
,
UK,
Europe and Singapore etcThe procured items shall be used for the area of maintenance
,
repair,
and operations such as booster compressors,
valves,
pipes and fittings
,
controllers etcThose are critical items and very importance for rig operating
They are required long lead-time and delivery from oversea to Vietnam
To achieve the goal
,
it is required skillful employee and appropriated procurement procedureYik et al 10 identified fluctuation in prices of raw materials is in the top three factors of cost overrun
In addition
,
there are significant challenges that exist incommodity volatility associated with major raw material inputs into oil and gas
exploration as well as downstream capital projects
,
including fabricated steel,
nickel,
Trang 20copper and other major commodities
This requires significant effort to hedge prices for these commodities
,
as well as to monitor and to plan for purchases against uncertain project schedules,
leading to significant shortfalls between supply and demandTo prove for this issue
,
MsGiang informed that on the year of 2013
,
the company placed order for one unit of anti-surge valve with inlet 12 inches and outlet 10 inches,
gross weight is around 1300kg
The material of valve body is duplex stainless steel type A995 Gr
4A
Due to the fact of fluctuation in prices of raw materials
,
the manufacturer has spent more time to procureTherefore
,
the delivery time was pro-longed for more than two monthsWhen the equipment was arrived KNOC VN warehouse in Vung Tau city
,
it had not been catched-up the supply boat scheduleTherefore
,
the company has paid for adhoc supply boat to carry it from onshore to offshore in order to meet shutdown planConclusion
The cause of delivery problems of purchased materials is often related to late requisitioning by other departments In practice this leads not only to a higher price being paid (as a result of extra work, speed of delivery, buying from stock-keeping wholesalers), but also in many cases to higher organizational costs and operational problems (the delivered materials do not comply with the specification, many deliveries, postponed delivery of critical parts)
The delay in supplying of equipment by suppliers which is found at KNOC VN caused to the cost overrun in transportation from onshore to offshore
The quality of supplied materials is another problem found
The writer believed that one of the causes of the aforementioned problems is that there is no systematic supplier’s measurement put in Trang 21
place
Equipment sourcing based on experience of the procurement officer does not always guarantee that the company will award contract to the suppliers who have high
performance
From these results
,
again,
it is noted that most causes of delay and cost overrun relates to the qualification of staff and procurement procedure problemsTrang 22
The initial cause and effect map is showed as below:
21
Trang 23CHAPTER 2 SOLUTION 2.1 Solutions
The company is now facing with cost overrun for transportation from onshore to offshore
It is caused by the qualification of staff and procurement procedure
There any many solutions to solve this problem such as provide to staff necessary training courses
,
stock equipment
,
provide clearly supplier selection and performance evaluation process to procurement staff- To enhance the ability
of employees to perform their jobs at peak level
- Available to use at any time
- To control the production capacity
- To select the right supplier
- To build a good relationship with supplier
Boundary
conditions
- Local in-house courses
Every item needs to
be available at
On job training by Sr
Procurement Officer /
Trang 24- Professional development courses from oversea centers
warehouse using for one replacement
Procurement Manager
Benefit USD 234
,
090 USD 468,
180 USD 234,
0902.3 Solution selection
With above comparison
,
the writer believes that the best way to solve thecompany’s problems that the company should built-up a supplier selection and
performance evaluation process
It is a crucial process to identify strengths and
weaknesses of suppliers which can help the company to manage their suppliers
The supplier selection and performance evaluation process can also be applied to monitor day- to-day operations with the suppliers
It has been recognized it as a key process that contributes to the competitive advantage of the firms
Organizations have started focusing on their core competencies and outsourcing the remaining activities to outside suppliers
Suppliers have even been responsible for design of new products
,
sub-assemblies and component partsHotabe et al 11 found that supplier’s competency
,
service quality control,
transaction cost-drivers
,
supplier’s brand image and supplier’s country characteristics are more important than othersThe supplier selection and evaluation performance process Trang 25
should not only consider price but also a wide range of factors such as quality
,
organization and relationship with a view to decision making by considering the whole supplier capability in a long term and strategic way
Shenhar et al 12 suggested that adopting effectiveness measures will more often lead to project success
,
by relating success to long-term impacts to the business2.4 Solution details
Qualifying and selecting new suppliers method
To survive in the intensely competitive global economy
,
it is often critically important to not only develop existing suppliers but also to discover new suppliersThere are many factors make new suppliers important
First
,
there may exist new suppliers that are superior in some way to a firm’s existing suppliersOr a new supplier may have a structural cost advantage over existing suppliers
,
for example,
due to low labor costs or favorable import/export regulations in its home countrySecond
,
existing suppliers maygo out of business
,
or their costs may be increasingThird
,
the buyer may need additional suppliers simply to drive competition,
reduce supply disruption risks or meet otherbusiness objectives such as supplier diversity
Production delays due to parts shortages and recalls of faulty products produced by noncompliant suppliers have cost buyer firms millions of dollars through recalls
,
warranty costs,
and associated inventory adjustments,
and have inflicted untold damage on their reputations and future sales potentialTrang 26
Lopez stated that supplier selection is one of the most crucial components of the purchasing function of a firm
It becomes a strategic decision when the purchasing
organization attempts to establish a long-term and win-win business relationship with its suppliers
In order to select the right supplier
,
comprehensive and configurable metrics for supplier selection must be outlined early in the processDepend on each industry
,
the supplier selection criteria is being consideredThe proposed model here takes from company’s strategy incorporating top level policies and requirements
To develop a fundamental framework for Supplier Portfolio management
,
including supplier selection and empowerment,
based on the company’s corporate and procurement strategiesIt is used to combine similar requirements from various projects into attractive package of business for suppliers who are then selected not only based on their price and quality but also by strategic partnership initiatives and long- term development outlooks
In this model
,
outsourced items are grouped into two distinct 80-20% Pareto setsThe first set
,
80% of non-critical items,
with 20% price,
may still be purchase with simple or traditional methodsThe second set
,
20% of is chosen within Supplier Portfolio methodologies looking at corporate,
business,
and procurement strategic elementsThe guidance regarding the performance criteria used to evaluate potential sources
of supply or to evaluate an existing supplier for an item not traditionally provided by suppliers
Management wants to make sure that supplier selection occurs only after
purchasing thoroughly reviews all criteria
Supplier selection criteria include the following:
Trang 27‐ Price/cost competitiveness
‐ Product quality
‐ Delivery performance
‐ Financial condition
‐ Engineering and manufacturing technical competence
‐ Management of its own suppliers
‐ Management capability
‐ Ability to work with the customer
‐ Potential for innovation
Supplier performance evaluation method
Teng 14 stated that there are a number of approaches being used to assist the supplier performance evaluation
Four commonly-used traditional methods stated in several studies are categorical method
,
weighted-point method,
cost ratio approach and dimensional analysis model,
analytic hierarchy process (AHP)The AHP model approach was selected with a strong credence that this approach can respond and fulfill the objective of company
This is due to the fact that each
evaluation criterion has difference relative level of importance when compares with homogenous criteria
AHP is designed to break down a complicate
,
multiple criteria problem into levels of hierarchyWith its flexibility and systemization
,
it can signify the elements of a complicate problemPerformance evaluation criteria are also selected to form the conceptual framework
The performance of many suppliers will be measured
by referring to four main-criteria
,
namely: quality,
delivery,
service,
and flexibility,
and eighteen sub-criteria under those four main- criteria
Trang 28
AHP can be considered as a problem-solving tool with flexibility and systemization
to signify the elements of a complicate problem
The AHP is designed to break down a complicate
,
multiple criteria problem into levels of hierarchy with the top level as the objective,
the intermediate levels as the criteria and sub-criteria,
with the lowest level as alternativesThe relative importance of each criterion determining which criterion has the highest priority
Ordoobadi et al 15 stated that a series of pair-wise comparisons of all criteria
,
the weights of the criteria are determined and can be used to construct a supplier evaluation systemSupplier Performance Evaluation Criteria
The most important part in supplier performance evaluation process is identifying the evaluation criteria which are related to the supplier performance
There are many major criteria for supplier performance evaluation
Kwong et al 16 pointed out that the supplier performance is not just related to price or quality
,
instead,
supplier performance evaluation requires a multi-criteriaevaluation process
However
,
it is fair to accept that the quality will be on the top priorityto satisfy the customer
,
but there are other attributes which are important and need to be consideredTherefore
,
the buying companies need to select and identify the evaluation criteria which will serve the company’s objectives,
activities,
and to satisfy thecustomers
Cormican et al 17 concluded that it is very important to identify the criteria and metrics which are objectively relevant to the company at all levels
Trang 29
packaging/packing
Supplied goods are properly packed and packaging is suitable for transportation & storage Supporting Required supporting document and material Delivery On-time delivery Goods are delivered to the required destination as
Delivery accuracy Goods are delivered accurately with no missing or
Non-splitting delivery Goods are delivered in large lot and with no
Advance informing of delivery
Supplier informs in advance if the delivery schedule is not as planned
Shipping document accuracy
Shipping document is issued correctly and accurately
Ability to arrange replacement
Supplier promptly arranges replacement delivery
if defect or discrepancy is found Service Responsiveness to
request for quotation
Supplier promptly submits quotation after receiving a request for quotation
Responsiveness to Supplier quickly responses back when
Information sharing Supplier willingly supports and shares
information
,
e.
gQuality of sales person Salesperson is knowledgeable about the goods and
accurately and courteously to support company’s Communication
systems
Supplier has good and reliable communication system
,
e.
gemail system
,
document tracking Trang 30Inventory availability Supplier always has inventory on-hand to fulfill
customer’s demand
Flexibility
Capacity to respond to Supplier always has inventory on-hand to meet Order customization Supplier has ability to customize order as per Negotiability Supplier is willing to negotiate on price and
delivery schedule
Supplier evaluation often follows a rigorous
,
structured approach using formal surveysAn effective supplier survey should have certain characteristics
First
,
the survey should be comprehensive and include the performance categories considered important to the evaluation and selection processSecond
,
the survey process should be as objective as possibleThis requires the use of a scoring system that define the meaning each value on a measurement scale
A third characteristic is that the items and the measurement scales are reliable
The supplier performance evaluation should be proceed yearly by the end of the year
The result needs to be informed to all procurement officers in order for implementing incoming orders
The reason for these problems usually can be traced back to unclear specification
or a careless supplier selection Another reason may be that suppliers are not
systematically evaluated, as a result of which troublesome suppliers stay on board and delivery problems occur time after time
The presented purchasing model may help manager to structure their purchasing decision-making processes and the optional processes involved The results will not only
Trang 31pay off in terms of lower prices paid for materials and services, but certainly also in lower organizational costs and a higher productivity
Trang 32CHAPTER 3 ACTION PLAN
The best way to ensure supplier is to achieve a common view of the potential for improvement and systematically track the implementation of purchasing
The process of supplier selection and performance evaluation should be applied
It will help both buyer and seller understand each other’s
The program needs to be implemented as soon as possible
According to the current company’s financial status
,
the program will be drafted bySr
Procurement officer with reviewed and commented by Procurement Manager
The timeline is as below:
1 Draft the process of supplier
selection and performance evaluation
process
Sr
Procurement officer 31 March 2017
2 Review and comment Procurement Manager 21 April 2017