Relationships between Critical Factors Related to Team Behaviors and Client Satisfaction in Construction Project Organizations Luong Hai Nguyen, Ph.D.1 Abstract: Factors related to team
Trang 1Relationships between Critical Factors Related to Team Behaviors and Client Satisfaction in Construction Project Organizations
Luong Hai Nguyen, Ph.D.1
Abstract: Factors related to team behaviors (TBs) have been recognized as critical success factors (CSFs) of a project Numerous studies
on the topic of CSFs have been conducted, but the results have rarely emphasized developing a TB framework for construction project organizations and examining its relationship with client satisfaction, a key criterion for measuring project success; these less-researched topics are the aims of this study TB attributes were first developed using questionnaires that collected data on 195 completed construction projects in Vietnam By performing a principal component analysis, these attributes were organized into a four-factor TB framework: (1) project planning and organizing emphasis (P&OE); (2) coordination emphasis (CE); (3) contractor assurance emphasis (CAE); and (4) empowerment assignment emphasis (EAE) The findings reveal that P&OE, CE, and CAE have significant effects on client satisfaction with project quality (SPQ), whereas CAE and EAE contribute to improved client satisfaction with project schedule (SPS) and project budget (SPB) In addition, CAE is shown to be a relatively significant influencing factor for all criteria within client satisfaction The study findings suggest a useful tool both for supporting the project management process of construction professionals and for improving client satisfaction
Author keywords: Team behaviors; Behavior influence; Project performance; Client satisfaction
Introduction
Over the years, a large body of work has emphasized identifying
critical success factors (CSFs), which are described as factors
in-volved in a project’s success (Fortune and White 2006;Kandelousi
2011) Baker et al (1983) identified (1) the project team’s
commit-ment to goals; (2) the project manager; (3) availability of project
funds; (4) capability of the project team; (5) accuracy of early cost
estimates; (6) planning and controlling methods; (7) task
orienta-tion; and (8) an absence of bureaucracy as factors that contribute
positively to the success of a project Other studies (Belassi and
into a consistent model for factors that affect project success
Belassi and Tukel (1996) classified CSFs into four groups of factors
related to project characteristics, project participants (i.e., project
manager and teams), organization, and external environment
Sim-ilarly, Lechler (1997) elaborated on a conceptual success factor
model in which the CFSs were classified into three main groups:
environment, contributors, and functions In relation to this
frame-work, Gemuenden and Lechler (1997) conducted an empirical
survey and identified the qualities of top management, the project
team, and communication as significant contributors to project
success Cooke-Davies (2002) identified real factors influencing
three separate aspects of project success, including the success of
project management, success of the project, and consistency of
project success Summarizing previous findings, Chan et al (2004)
suggested placing CSFs relevant to construction project manage-ment into five categories: project managemanage-ment mechanisms, project-related factors, the external environment, procurement approaches, and team-related factors Jugdev and Müller (2005) suggested four conditions that need to be met for a project to succeed: the success criteria alignment of participants before the start of a project, main-taining a cooperative relationship between client and project man-ager, empowering the project manager in terms of flexibility in exceptional circumstances, and the focus of the owner on project performance
Among these CSFs, the factor related to team behaviors (TBs) has been identified as an essential determinant of successful project implementation (Chan et al 2004;Chua et al 1999;Cserháti and
approach to project success has received substantial attention from academics in the literature and has been the subject of a variety of viewpoints in descriptions of its attributes in recent decades Chua
et al (1999) defined TBs as factors related to behaviors of project teams (i.e., project managers, clients, contractors, consultants, sub-contractors, suppliers, and manufacturers) as the key players in project success with respect to (1) the competency, commitment, and contribution of the project manager; (2) the active involvement and collaboration of other key members; (3) the level of support from top management; (4) the team turnover rate; (5) suppliers’ track records; and (6) suppliers’ levels of service Chan et al (2004) classified team factors into two sets The first emphasizes the client aspects, including the experience and capability of the client; the client’s nature; the client organization’s capacity; the client’s focus
on project cost, schedule, and quality; and the client’s contribution
to the project The second set of factors is related to the project team behavior in terms of its leadership experience and skills; the project team leaders’ commitment to project schedule, cost, and quality; the project team leaders’ contribution to the project; the project team leaders’ flexibility and working relationships; and the support
of the top management for the project teams
1 Lecturer, Univ of Transport and Communications, No 3 Cau Giay St.,
Lang Thuong Ward, Dong Da District, Hanoi City 100000, Vietnam.
Email: hainl@utc.edu.vn
Note This manuscript was submitted on March 12, 2018; approved on
September 6, 2018; published online on January 2, 2019 Discussion period
open until June 2, 2019; separate discussions must be submitted for
indi-vidual papers This paper is part of the Journal of Construction
Engineer-ing and Management, © ASCE, ISSN 0733-9364.
Trang 2Furthermore, several studies have provided evidence that a high
performance of TBs is associated with the success of a project
Behavioral management among construction project participants
related to project commitment and participation is likely related
to project participants’ satisfaction (Leung et al 2004) The
com-mitment, coordination, and competence of construction project
par-ticipants can support successful project performance (Jha and Iyer
2007) Likewise, in project management settings, human resource
management (Papke-Shields et al 2010), involvement of high-level
management (Kandelousi 2011), leadership of the project manager,
communication mechanisms, partnership, and cohesiveness of the
project teams (Yang et al 2011) can contribute to the success of
a project
However, the evolution of project organizational behavior
success frameworks has not yet clarified the nature and extent of
these frameworks’ impacts in terms of guaranteeing the project’s
objectives The literature has reported on critical problems related
to construction project performance, including poor quality, budget
overages, a lack of timeliness, unsafe construction, and client
dis-satisfaction (Ibrahim et al 2010; Kashiwagi et al 2012; Xiong
behavioral approach to the success or failure of a project; it is a
matter of which behavioral dimensions best explain project success
to specifically define each behavioral factor and examine how each
interacts with project success, a rare approach that has not been a
topic of focus in the previously mentioned literature
In addition, among numerous project performance measurement
indicators that have been recognized in the construction industry to
assess construction projects’ success, client satisfaction
measure-ment is a pervasive concern (Baloi and Price 2003;Leung et al
to investigating behavioral factors involved with client satisfaction
within the construction industry (Kärnä et al 2009) Although
multiple studies have mentioned TBs in construction, such research
has been disparate and rarely addressed the issues of explaining and
evaluating the relationships between TBs and client satisfaction
In addition, different perspectives result in significant differences
in views on behavioral success factors Currently, three groups of
key project participants—clients, contractors, and consultants—are
studied as the construction professionals’ assessments of
manage-ment practice, which regulate diverse relationships between project
success and behavioral factors
The aims of this study are not only to define the attributes of TBs
and develop a framework in construction projects but also to reveal
TBs’ links to project success with respect to client satisfaction This
approach is vital for project management practices by providing a
useful tool for supporting construction professionals in delivering
project management function, thereby contributing to the success
of construction projects The study design is structured into four
sections First, the study design is justified in terms of TBs and
client satisfaction in construction project organizations, and the
re-search hypothesis is developed Second, the rere-search methods and
methodology are introduced Third, in a key section of the paper,
the research results are presented with integrated interpretations
In the fourth and final section, conclusions are drawn
Justification for Study Design
Identification of Factors Related to Team Behaviors
An organization is defined as a deliberately coordinated social
en-tity in which a group of people gather to continuously work toward
achieving shared goals (Kinicki et al 2010) The core of all suc-cessful organizations is the effectiveness with which people work together, and the manner in which they interact is the key to meet-ing organizational objectives (Walker 2011) The study of TBs within organizations is part of the field study of organizational behavior (OB), in which the influence of individual and group behavior within organizations is investigated, applying such under-standing to improve an organization’s effectiveness Accordingly, team behaviors are concerned with how people interact at work and how their behavior influences the organization’s performance
2013) Specifically, the construction project organization (CPO) functions as a temporary entity-based contract in which diverse contracting organizations (i.e., project teams such as clients, con-tractors, and consultants) gather and set the pattern of interrelation-ships, ability, and responsibility to achieve the project’s goals and objectives (Walker 2015) within the project life cycle Thus, the typical CPO’s function must be designed for working extensively with organizations other than its own
In such circumstances, much of the authority and responsibility are conferred by contractual terms or the power of agency and therefore are less direct than those of an internal business affair
As a result, the understanding of TBs within a CPO is concerned with issues of project participants within different organizations (i.e., project teams’) collective behaviors and how their behavior affects the project performance as a whole Those collective behav-iors are expected to build an effective CPO by establishing shared project team expectations and a common understanding, promoting desirable behavior among project teams, and supporting project team members with behavior problems to get back on track and fulfilling the CPO’s self-management functions to fulfill the CPO’s objectives
In the domain of construction project management, factors related to managerial support, communication, commitment, coor-dination, and project team leaders’ performance (Chan et al 2004;
which may be viewed as the TBs’ manifestations related to project teams within CPOs that assess the patterns of project participants’ regular work behaviors over the course of a construction project
In this form, TBs are reflected in actions that characterize the in-teractions between project teams for achieving the project CPO’s effectiveness
This study therefore proposes that TBs can be identified by examining relevant work behaviors of project participants that re-flect the methods of implementation, explanation, or resolution for works and/or difficulties faced over the course of a construction project To develop each behavioral attribute, it was consequently relevant to study the sources of practice works and problems that project participants must resolve or for which they must clarify methods and solutions Building upon this approach of behavioral identification, examining project teams’ work behaviors is pivotal
to determining TBs within project organizations Measuring behav-ioral attributes is relevant to exploring the level of project teams’ work behaviors When examining the dimensions of the TBs of
a construction project, one could argue that a relevant source of knowledge should be obtained in consultation with key practi-tioners involved over the course of the project
Client Satisfaction Numerous performance measurement indicators have been used
to assess construction projects’ effectiveness and efficiency
with-in the construction with-industry Both early studies (Avots 1969;
Trang 3Pinto and Slevin 1988;Shenhar and Dvir 2008) implicitly propose
that project success involved concern for the “iron-triangle” of
project quality, project time, and project budget In further
consid-eration of those specifications, the satisfaction of the client is
ad-vised as a significant supplementary aspect of this formula (Bedell
1983) In a further holistic investigation, Pinto and Slevin (1988)
highlighted the key areas related to the success of a project,
includ-ing projects (i.e., quality, time, and budget) and clients (i.e., use,
satisfaction, and effectiveness) The importance of measuring client
satisfaction within construction projects’ effectiveness was also
clarified by Baker et al (1983), who conducted an extensive survey
over 650 project managers Indeed, the study of customer
satisfac-tion was launched in the early 1980s, and this concept is commonly
applied in social fields such as psychology, business, marketing,
and economics (Liu and Leung 2002) Essentially, satisfaction is
the expression of the disparity between“How much is there?” and
“How much should there be?” (Wanous and Lawler 1972)
There-fore, it is relevant to apply the same to the measurement of
perfor-mance outcomes (Nerkar et al 1996)
Recently, satisfaction has become increasingly used, with an
emphasis showing a positive increasing shift from purely business
performance to more stakeholder performance (Love and Holt
2000) In the context of CPOs, in which different project
stakehold-ers may have different pstakehold-erspectives on project success because
of their different aims (Davis 2014), project teams are primarily
asked to coordinate to deliver value for the client Therefore,
mov-ing beyond the traditional measurement of project performance
outcomes in terms of time, cost, and quality, measuring satisfaction
has proved an effective alternative approach to improve
construc-tion projects’ effectiveness (Cheng et al 2006;Davis 2014;Ling
satisfac-tion in a construcsatisfac-tion context is perceived as a holistic entity
consisting of quality (Alias et al 2014; Baloi and Price 2003;
To measure how the customers of a business rate the service offered
to them, the Service Quality (SERVQUAL) model is commonly
used (Mauri et al 2013); this model measures customer satisfaction
with service quality (i.e., constructed facilities and construction
process) as the discrepancy between the client’s needs and
expectations versus their experiences (Omonori and Lawal 2014;
when the experience exceeds expectations, and it is low when
experiences of service quality are below expectations
As for construction projects’ setting, clients form their
percep-tions of project quality, schedule, and budget from their interacpercep-tions
with project participants (i.e., contractors, subcontractors, and site
supervisors) Clients’ opinions about quality, time, and cost are
formed by interrelating with behavioral aspects of project teams
over the course of project The sum total of all interactions
influ-ences their level of final satisfaction with the project’s overall
quality, time, and cost Barrett (2000) mentioned that construction
project quality can be viewed as the fulfillment (i.e., satisfaction)
of a set of performance criteria owned by a host with regard to
other related project stakeholders In this regard, expectations are
an effective measurement for determining client satisfaction The
strength of the client satisfaction approach is that it emphasizes
importance to clients rather than establishing specification-based
judgments that may be ambiguous (Kärnä 2004) Client satisfaction
thus approaches quality from a client’s perspective that is relatively
straightforward to measure
Research Hypotheses
In any generic business setting, there is relevant evidence that indi-viduals’ behaviors, which are viewed as numerous series of actions within an organization, are significantly connected to customer satisfaction (Kattara et al 2008;Oguz and Serkan 2014) However, construction projects involve the acquisition of a capacity to pro-duce rather than the mere purchase of a finished product (Leung
and diverse in terms of the project teams involved Therefore, the management of a construction project is not so much a process sim-ilar to the internal affairs of a single company as one of the organi-zational practices of coordinating and regulating all the elements needed to accomplish the job at hand
In addition, multiple individuals and groups with diverse back-grounds contribute to CPO, which results in different behaviors and different expectations for a project This practice requires project teams that present complicated behaviors and/or attitudes to work
in a highly collaborative manner to permit the accomplishment
of the common goals of the project Behavioral differences are also believed to be capable of generating conflicts related to com-munication, which decreases the CPOs’ capacity to accomplish the project objectives (Tijhuis 2011) In the practice of construction project management, TBs should be considered a significant con-tributor that helps improve overall client satisfaction with the project received Thus, factors related to TBs arguably positively influence client satisfaction TBs should be measured based upon how positively project participants’ behavior relates to client satisfaction Therefore, the main hypothesis of this study is that TBs can positively influence client satisfaction
Research Methods
Developing TBs’ Attributes within the Construction Project Organizations
Focus group studies (FGS), focal interviews, field studies, and
a literature review were the key approaches used to develop behav-ioral attributes FGS are considered a good approach to studying specific behaviors or beliefs, the circumstances in which they occur, and the diversity of experiences and perspectives on spe-cific issues (Hennink 2013) In the first step of TBs develop-ment, three FGS were conducted in the three biggest cities in Vietnam, where most big construction companies are situated and operate, namely, Ha Noi (the capital city, situated in the north),
Ho Chi Minh (the biggest city in terms of businesses, situated in the south) and Da Nang (the midland capital city), with one FGS in each city
The participants for each FGS were selected from among indus-try professionals within private and public clients, contractors, and consultants in the cities, with eight participants from each FGS The selected participants’ backgrounds included project managers, supervisory officers, and senior engineers This step ensured the customization of the initial list of identified behavioral attributes
in Step 1 Targeted professional interviewees with satisfactory ex-perience in managing construction projects were invited Overall,
19 experts were invited to participate in the interviews: five from clients, nine from contractors, and five from consultant firms A sample size of 19 interviewees is considered acceptable in a quali-tative study because it exceeds the minimum acceptable sample size
of 15 and 12 interviews suggested by Bertaux and Bertaux (1981) and Guest et al (2006), respectively All 19 interviews resulted in
a consistent verification of the results obtained from the FGS
In addition, field observations were conducted within 15 ongoing
Trang 4construction projects in Vietnam to obtain a clear view of practices
related to the study’s data collection
The purpose of the FGS and focal interviews was to discuss
common problems in regard to the project delivery process and to
clarify the traits of the TBs over the course of a project Discussions
and interviews were semistructured, containing sequential
compo-nents: the introduction, opening questions, introductory questions,
transition questions, and closing questions (Hennink 2013) After
the participants provided a short description of their experiences,
the primary topics and associated inquiries were raised, and
addi-tional requests were then added as necessary In addition, the
par-ticipants and interviewees were initially provided with the current
literature on the definitions of TBs in terms of project success to
help clarify the notion of team behavioral attributes They were
then asked related questions about the study attentions A selection
of primary questions are as follows:
1 How do you understand the project management functions?
2 What common problems in terms of project management
func-tions occur over the course of a project?
3 Can you provide a detailed description of how project teams
address those problems?
4 What do you understand about team-related behaviors within
CPOs?
5 How would you describe team-related behavior?
6 What attributes should be measured in terms of project
partici-pants’ behaviors?
7 In your experience, what types of participant behaviors over the
course of a project lead to good or poor performance in terms of
quality, schedule, and budget?
8 How would you describe the client satisfaction with a complete construction project?
9 In your experience, who should assess these behaviors? The focal interviews and FGS with participants recommended that the aspects should measure behavioral attributes that reflect project teams’ managerial support, communication, commitment, coordination to management function practices with regard to project planning, project organizing, project leadership, and project control Hence, TBs should first pertain to project planning, which covers describing a project organization’s objectives, forming a comprehensive strategy for accomplishing those objectives, and de-veloping a comprehensive set of plans to integrate and coordinate activities (Martin and Miller 1982) Second, TB indicators should connect to project organizing, which includes defining project tasks, clarifying responsible stakeholders for those project tasks, establishing a communication mechanism over the course of the project, and determining the roles and duties of decision makers Third, TBs also involve project leading, which covers the project leaders’ function of directing project teams’ activities, motivating the project team and team members, coordinating all project teams and contributors, and/or resolving risks and conflicts during the project implementation (Robbins and Judge 2013) Finally, TBs should describe the capabilities of the project controller, which en-sures that project tasks are proceeding as planned; project manage-ment must monitor task performance and compare it with the baseline to detect any significant deviations or problems and take corrective action to get the project back on track (Pierce 2013) As a result, 23 attributes were compiled and suggested for measurement
as TB success factors (Table1)
Table 1 Attributes of team-related behavior
Clarification of project objectives TB1 Objectives and values of the project are clearly understood by project teams.
Project planning clarification by project teams TB2 Project teams clearly understand their required roles and duties on the project plan Ability of clients to define roles TB3 The client clearly understands and defines required roles and duties to project teams Mutual understanding TB4 All project teams concern each other ’s objectives, expectations and values.
Communicates about implementing project plan TB5 All project teams first look at how the project would be implemented effectively rather
than how they would benefit from the project.
Interactions at work TB6 Interrelated working relationships among the project teams are promoted in terms of
exploring innovative solutions and reducing costs and time spent.
Communicates with information TB7 Information is shared, transparent and available to project teams over the course of the
project.
Effective communication TB8 Project team leaders assist and clearly communicate with their subordinates and other
teams, ensuring accomplishment of project objectives.
Responsibility clarification TB9 Project participants are always ensured their responsibility over the course of project Mutual respect and openness TB10 The project teams are open and respectful of one another.
Idea exchange and support TB11 The project participants are encouraged to exchange ideas and to help one another Risk and conflict resolution TB12 All project teams are encouraged using “joint problem-solving” when things go wrong
over the course of a project.
Valuing project participants ’ contributions TB13 All project members are valued as significant participants in the success of the project Supports team members TB14 All project participants are encouraged to receive constructive feedback to enhance their
performance.
Promotes empowerment TB15 Project team leaders are authorized to make appropriate decisions by themselves Fosters motivation TB16 Project teams are always supported and encouraged to maintain a high level of motivation
over the course of the project.
Control of project quality by contractors TB17 Contractors emphasize the monitoring and comparing plan for project quality Control of project schedule by contractors TB18 Contractors emphasize the monitoring and comparing plan for project schedule Control of project budget by contractors TB19 Contractors emphasize the monitoring and comparing plan for contract costs.
Encourages team decisions TB20 Project teams are respectfully encouraged to raise any question at every level Participation in decision making TB21 All project participants are encouraged to be involved in any decision making over the
course of the project.
Trust-sharing atmosphere TB22 There is an atmosphere of mutual reliance generated by project teams.
Direction by project leaders TB23 Project team leaders always ensure that their subordinates know what is expected of them.
Trang 5Data Collection
Based on the literature and discussions with key project
stakehold-ers, case-specific data were collected by practitioners involved in
construction projects in Vietnam who served as project managers
for clients, contractors, and supervisors This approach was also
validated by consultations for a pilot study, which helped to clarify
that clients, contractors, and supervisors with responsibilities as
project team leaders or managing directors were the most
appro-priate survey respondents As a result, official questionnaires were
distributed to 239 randomly targeted participants who were asked
to answer specific survey inquiries based on the participants’
ex-periences with their most recently completed construction project
A final sample of 195 valid responses was obtained for
inves-tigation Among the final set of valid samples, 92 and 73 of the
respondents were clients and contractors, respectively, and the
re-maining 30 were supervision consultants Regarding respondents’
backgrounds, 100% of the respondents had held the position of
project managers during the project delivery, and 79% of them
had worked in the construction industry for over 10 years, with
a minimum of 5 years work involvement in construction project
management For the construction project categories, 106 of the
projects surveyed were infrastructure facilities, including roads,
bridges, and water supply structures; 62 of the projects surveyed
were residential and/or office buildings; and the remaining 27
proj-ects were manufacturing facilities Regarding the projproj-ects’ size, 48
were large-scale investments (national level), 111 were midrange
investments (budget> VND 15 billion), and 36 were small-scale
investments
Measures
The survey items were divided into two parts First, respondents
were asked to clarify their demographic characteristics and describe
the features of their projects, and the second part aimed to collect
data on behavioral attributes and client satisfaction aspects The
respondents were requested to specify their experience with a
re-cently completed construction project on a five-point Likert scale
of 1 (strongly disagree/not at all satisfied) to 5 (strongly agree/
extremely satisfied)
The principal component analysis (PCA) method is commonly
employed to examine the essential dimensions of multiple
indica-tors (e.g., collection of TB aspects) PCA is an effective tool for
principally diminishing a large set of observed variable factors
into its underlying components (Grimm and Yarnold 2000;Hair
eigen-value criteria are the most commonly used to eliminate or retain
the components extracted from the number of parameters (i.e., TBs
aspects) As a result, those extracted factors with eigenvalues
greater than or equal to 1 are retained, and conversely, those with
eigenvalues less than 1 are eliminated
Additionally, Cronbach’s α was analyzed as an integrated test to
evaluate the internal consistency of the factorized items (Sharma
higher theα coefficient, the more consistent the alignment of items
A Cronbach’s α value greater than 0.7 is considered acceptable in
internal consistency testing (Hinkin 1995; Pallant 2007; Sharma
The stepwise technique is the most commonly employed to
de-termine the set of predictors in a regression model (Ratner 2010)
and the extent to which predictors are properly integrated into the
fit model Although this selection method has the capability to
determine an explanatory subset among many variables based on
statistical criteria, the limitations of stepwise selection have been recently criticized because of the biasedR2and coefficient values,
generating a false confidence interval, severe problems with multi-collinearity, unstable selected variables, and a problem with redun-dant predictors (Prost et al 2008;Ratner 2010;Wang et al 2004;
aver-aging (BMA) technique BMA has ability to model uncertainty using the posterior probabilities as a goodness of fit assessment for numerous selected possible models to perform all inferences and predictions (Fragoso and Neto 2015;Xu et al 2012) BMA also provides a higher frequency of selection and lower standard deviations for estimated criteria than the stepwise technique (Prost
MATLAB, R, and PYTHON have been utilized Here, R was used
to analyze the study model
Results and Discussion Results of Factor Analysis on TBs’ Attributes PCA was employed to explore the principal factors from the set of
23 behavioral attributes The outcomes of the PCA (Table2) used the Kaiser-Meyer-Olkin (KMO) index test for sampling adequacy, which was relatively greater than the accepted threshold of 0.60
(p > 0.000) (Hair et al 1998), showing that the data were suitable for factor analysis Factor loadings above the 0.40 threshold were considered (Cserháti and Szab ´o 2014;Field 2000) The final results
of the PCA showed that the four behavioral components that were primarily extracted accounted for 59.19% of the total variance in the 23 behavioral attributes with an eigenvalue greater than 1, in-dicating that those extracted attributes can help clarify the four TBs The Cronbach’s alpha values ranged from 0.704 to 0.871, which indicates that the internal consistency reliability of all the extracted components was acceptable (Cserháti and Szab ´o 2014)
Eight aspects were extracted as significant in Management factor 1: clarification of the project’s objectives (TB1); project plan-ning clarification by project teams (TB2); ability of clients to de-fine roles (TB3); mutual understanding (TB4); communicates with information (TB7); effective communication (TB8); responsibility clarification (TB9); and valuing project participants’ contributions (TB13) Taking into account the aspect explanations specified in Table2, aspects TB1, TB2, TB3, and TB4 reflect the effectiveness
of project planning clarification over the course of a project The remaining items in Behavioral factor 1 can be applied to assess the effectiveness of the project organization These results are con-sistent with the FGS findings that those eight TBs are grouped
in the detailed description of the first two project management functions: project planning and project organizing This behav-ioral factor is called project planning and organizing emphasis (P&OE)
Management factor 2 was composed of eight items: communi-cates with implementing project plan (TB5); interactions at work (TB6); openness and mutual respect (TB10); idea exchange and support (TB11); risk and conflict resolution (TB12); fostering motivation (TB16); trust-sharing atmosphere (TB22); and direction
by project leaders (TB23) The conceptualization of the aspects extracted in Factor 2 contributes to collaboration in the work envi-ronment, in which disparate project teams come together to create
a shared understanding to achieve project goals and objectives The results are also compatible with previous works suggesting that the coordination process primarily involves the creation, dis-semination, and processing of information in managing resources
Trang 6efficiently (Hossain 2009) Thus, Cultural factor 2 is called
co-ordination emphasis (CE)
Three items were significantly organized in Management
fac-tor 3: control of project quality by contracfac-tors (TB17); control
of project schedule by contractors (TB18); and control of project
budget by contractors (TB19) These aspects reflect the degree
to which the contractor made efforts and took appropriate actions
to guarantee that the project remained on track This result is to be
expected based on the FGS findings that the controlling function
is essential to project management to help ensure the project is
pro-ceeding as planned Thus, this management factor is called
contrac-tor assurance emphasis (CAE)
The taxonomy of Factor 4 included four items: supports team
members (TB14); promotes empowerment (TB15); encourages
team decisions (TB20); and participates in decision making (TB21)
This cultural factor is called empowerment assignment emphasis
(EAE) because the items loaded reflect how team members are
em-powered to be involved in making decisions about achievement
of the project objectives
In summary, the PCA identified the following four factors of the
TBs for the CPOs: P&OE, CE, CAE, and EAE These factors are
suggested as the formulation of a TB framework for construction
project management in industry
Analysis of Variance
The ANOVA indicated that at a 99% confidence interval (Table3),
the mean scores of the four behavioral dimensions assessed
be-tween groups of respondents are similar This result specifies that
despite their association with different roles in the course of project, there was no significantly different assessment of TBs among the three types of professionals in the construction industry As such, the three groups of professionals are in agreement with the four factors identified by the PCA, which are valid measures of TBs
in the construction industry This result may well explain why, de-spite the fragmentation and complexity in the construction industry, the project participants appear more in agreement with the efforts of the project teams in project planning, organizing, directing, and controlling over the course of a project It can be inferred from this finding that there are no significant conflicts among stakeholders
in terms of contract terms under the dominance of the traditional procurement approach (Nguyen and Watanabe 2016)
In summary, the overall agreement among different project teams means that despite their diversely involved organizations, the three groups of project stakeholders (clients, supervisions, and contractors) had similar views of TBs within the industry
Table 2 Results of factor analysis on behavioral attributes
Behavior components
Internal consistency reliability (Cronbach ’s alpha) — 0.855 0.871 0.870 0.704 Kaiser-Meyer-Olkin measure of sampling adequacy 0.912
Bartlett ’s test of sphericity
Table 3 ANOVA in regard to respondents ’ professions Respondent Statistics P&OE CE CAE EAE Client Mean significant score 3.82 3.41 3.41 3.45
SD 0.49 0.62 0.75 0.55 Contractor Mean significant score 3.74 3.30 3.78 3.32
SD 0.53 0.69 0.64 0.59 Supervisory
consultant
Mean significant score 3.80 3.50 3.34 3.52
SD 0.56 0.66 0.86 0.63 Kruskal-Wallis
test
Chi-squared 1.537 2.132 4.671 3.442 P-value 0.463 0.344 0.0716 0.178
Trang 7However, this finding differs from previous studies, which have
argued that the diverse contracting organizations within a CPO
have different backgrounds, business intentions, responsibilities,
and work patterns Thus, the different contracting organizations
may perceive TBs differently within CPOs (Ankrah and Langford
groups of respondents generally agree with the practices on
repre-sentativeness of the identified behavioral factors instead of their
conventional perceptions, which indicates the highly relevant
prac-tice pursuant to which contracting organizations can develop
common core values within a project
Impact of TBs on Client Satisfaction
Multiple regression analyses were performed to predict and explain
how the behavioral factors affect the project outcomes The
inde-pendent variables as predictors included the four dimensions of
TBs, whereas the dependent variables were client satisfaction
measured within three dimensions, including (1) satisfaction with
project quality (SPQ), (2) satisfaction with project schedule (SPE),
and (3) satisfaction with project budget (SPB) The BMA technique
was applied to select the set of predictors in the possible regression
models, and outputs were obtained (Table4) The results present
the goodness of fit of selected regression models; the highest value
of the Bayesian information criteria (BIC) and the highest absolute
value of postprobability (post prob) indicates a good fit with the
data among the possible models
Table4indicates that the three TB dimensions of P&OE, CE,
and CAE are conducive to increasing client SPQ The
recom-mended models explained 52% of the variation in SPQ (p < 0.000),
whereas CAE and EAE had a positive effect on client satisfaction
with project schedule and client satisfaction with project budget,
which collectively explained 40.3% and 28.5% of the variation
in SPS and SPB, respectively (p < 0.000) The ANOVA results also
clarified that the recommended models are able to significantly
(P < 0.000) improve the prediction of project performance
Addi-tionally, a variance inflation factor (VIF) test was carried out to
ensure that the issue of multicollinearity was ruled out in the
regression analysis The VIF values (all of which are below 2.25)
are much lower than the threshold of 10 (Hair et al 1998), which
implies no multicollinearity or small standard errors within the data
regres-sion models, analyses of residuals are commonly used The
histo-gram of standardized residuals of the models show a bell-shaped
distribution, indicating that the normal assumption has not been
violated In addition, the normal Q-Q plot of the models shows that
the observations plotted against a theoretical normal probability display points forming a roughly straight line, supporting the con-clusions regarding the normal assumption drawn from the histo-grams of standardized residuals
Three predictors—P&OE, CE, and CAE—have a positive influ-ence on SPQ, which may indicate that projects with higher levels of these predictors also have higher levels of project quality satisfac-tion The behavioral dimension of P&OE can be connected with the cultural trait of mission in the model of Denison (2000) The specific indexes in this cultural dimension clarify the goals and objectives, vision, and strategy that can offer project teams a clear working map, answering the questions “Where are they going?” and“How is their daily work?” that contribute to the achievement
of project goals This finding is also compatible with the work of Cheung et al (2011), who found that “goal setting and accom-plishment” were significant along with cultural dimensions in Hong Kong’s CPOs This finding clarifies the belief that a CPO
is recognized by its project participants’ behaviors, which in turn are formed by project aims that are established and manifested
by the activities implemented by the project members over the course of a project In other words, clear project objectives instruct the construction of a project plan and make its execution viable This primary project performance criterion can be accomplished only through a process of clarifying the project’s objectives and strategies, clearly assigning roles and responsibilities to the team members, and effective communication through which project par-ticipants clearly understand the requests and schedule and how they can obtain support for their work, which in turn enables them to fully contribute their joint efforts to the success of the project The behavioral dimension of CE refers to a coordination and integration culture with diverse participants and units of a project’s organization, which helps project participants understand the mu-tual influences of their actions and ensures that all project members work together toward common goals This result is to be expected The construction industry is characterized by its fragmented nature and temporary cooperation; as such, a high level of coordination characterized by a commitment to project benefits, promoting in-teractions at work, openness and mutual respect, idea exchange and support, risk and conflict resolution, and the clarification of responsibility among construction project participants all form
an essential foundation for the success of a project By offering coordination, project teams look forward to higher project qual-ity and shared project risks, contributing to higher client SPQ These findings are also consistent with those of Zou et al (2008), who revealed that overall project performance is enhanced by a cooperative environment Similarly, Leung et al (2004) found that behavioral management related to commitment, team involve-ment and shared goals can positively contribute to participant satisfaction
CAE also plays a vital role in all project outcomes This behav-ioral dimension was a relatively significant aspect, aptly reflecting the importance of contractors’ obligation to their contracts These findings are also consistent with previous studies, which found that the contractor significantly influences project performance (Chua
the fact that contractors are more concerned about reacting to and serving the client and constantly committing the capacity necessary
to satisfy the client’s future needs and expectations Moreover,
it is intriguing that factors of construction project performance such as poor quality, overspending, and time delays have been re-ported for years in developing countries such as Vietnam (Nguyen
ap-pear to prioritize contractors on site These findings also clarify
Table 4 Bayesian model averaging of selection
Model
Satisfaction with project quality
Satisfaction with project time
Satisfaction with project cost Intercept 0.566a −0.133 0.800a
F-statistic 69.11b 64.75b 38.59b
a p < 0.01.
b p < 0.05.
c p < 0.001.
Trang 8contractors’ contributions to project success within the
environ-ment of traditional construction project procureenviron-ment
CAE and EAE enhanced client satisfaction with both project
schedules and budgets Unsurprisingly, the contractor plays a
sig-nificant role in ensuring the success of a project Furthermore,
these results were related to the variables included in the TBs of
EAE The behavioral dimension of EAE provides project members
with the requisite authority, initiative, capacity, and opportunities to
organize and oversee their responsibilities at work over the course
of a project These results are not surprising within the field of
con-struction project management Given the natural complexity and
uncertainty of construction project management, promoting an
em-powerment culture enhances the capacity to acquire feedback or
suggestions from project members at various levels of management
and the decision-making process, which is pivotal to reducing risks
and improving project performance Additionally, fostering this
behavioral culture generates a sense of ownership and
accountabil-ity for all project team members, promoting greater commitment
to the project’s objectives and goals For organizations in which
employees are encouraged to raise their voice and be heard, this
reflects that organizations are“using their greatest asset to its
high-est potential and, in return, are becoming more competitive in the
emerging global economy” (Maxwell 2005)
In summary, these results provide empirical evidence that TB
frameworks play vital roles in enhancing client satisfaction within
CPOs, at least to an extent Although this study used data collected
in Vietnam, the research claims (i.e., inferences, interpretations,
methodologies, and conclusions) were developed based on studies
that were conducted overseas The findings of this study will help
the construction industry and academia gain a deeper
understand-ing of the sources of critical success factor–related project TBs and
the influence of project TBs on project success For construction
professionals, this paper aims to provide guidance to practitioners
involved in project management activities by developing
measur-able controls for participant behavior and attitudes These controls
will enable practitioners to adjust their interactions with
partici-pants during the course of a project to achieve better project
out-comes In addition, the study aims to extend the body of knowledge
in project management by developing a project team behavior
framework and examining the influence of project team behavior
on project success with regard to client satisfaction
Conclusions
This study aimed to better define attributes of TBs and to detect
their framework in construction projects, which was characterized
by practices derived from specific CPOs In this respect, 23
attrib-utes of TBs were first derived through FGS, a literature review, and
focal interviews with practitioners in the industry Using Vietnam
as a case study, the TBs’ measurements were collected and then
used in PCA to classify these attributes into four factors of TB
The TB factors of P&OE highlight the importance of clarifying
project goals and a comprehensive plan in which all project
mem-bers are clearly provided direction and scope for their work over the
course of the project Additionally, the TB factor of CAE reflects
the culture of customer focus, within which contractors are the
piv-otal element to assure project performance The TB factor of CE
highlights the fragmented nature and diverse individuals involved
in a construction project This factor makes perfect sense in
con-struction project management because having a cooperative
atmos-phere ensures that all project members understand each other and
work well together toward common goals The EAE factor reflects
people-focused cultures within which leadership is viewed as the
most powerful Thus, project management invests more in leader-ship behaviors, and project members experience a greater feeling of ownership and accountability, which helps to promote effort and a capacity for autonomy to achieve a CPO’s goals and objectives The study identified no significant differences in the assessment
of the TB factors provided by project stakeholders The shared acceptance of these factors with moderate mean scores by the three groups of construction professionals suggests that core common values in projects can be generated by devoting efforts to derive project goals and objectives instead of individual benefits among contracting organizations The policy implication is that project stakeholders should place more emphasis on efforts to promote managerial practices that are deemed most behavioral in the con-struction industry, potentially contributing to the practice of effec-tive change in project management
These behavioral factors were then used to analyze the signifi-cant associations between behavioral dimensions and different aspects of client satisfaction These dimensions can be used to es-timate and explain project performance in terms of client satisfac-tion; these dimensions were developed through the three robust models presented in Table 4 The findings indicate that P&OE,
CE, and CAE contribute to better client SPQ Two behavioral di-mensions, CAE and EAE, can predict client SPS and project budget This study demonstrates that CAE plays the crucial role in interpreting all aspects of client satisfaction These judgments re-garding behavioral effects infer that TBs must be emphasized as a prioritized project management tool that contributes to project ac-complishment, suggesting that greater effort is needed to promote positive behavior among project teams as part of the project management
However, this study has to confront the limitation of collecting data only from practitioners in Vietnam; the data are therefore certainly valid for the specific case, but their applicability outside Vietnam is unclear In addition, this study was limited by a rela-tively small sample size; increasing the volume of data could offer
a comparative analysis based on data derived from separate project stakeholders, which would specifically evidence how diverse stake-holders view the common practices of project delivery
Data Availability Statement Data generated or analyzed during the study are available from the corresponding author by request Information about the Journal’s data-sharing policy can be found here:http://ascelibrary.org/doi/10
Acknowledgments The author expresses appreciation to the construction professionals
in Vietnam who kindly contributed their professional experiences and knowledge to this study
References
Alias, Z., E M A Zawawi, K Yusof, and N M Aris 2014 “Determining critical success factors of project management practice: A conceptual framework ” Procedia Soc Behvav Sci 153 (Oct): 61–69 https://doi org/10.1016/j.sbspro.2014.10.041
Ankrah, N A., and D A Langford 2005 “Architects and contractors:
A comparative study of organizational cultures ” Constr Manage Econ 23 (6): 595 –607 https://doi.org/10.1080/01446190500126973 Avots, I 1969 “Why does project management fail?” Calif Manage Rev.
12 (1): 77 –82 https://doi.org/10.2307/41164208
Trang 9Baccarini, D 1999 “The logical framework method for defining project
success ” Project Manage J 30 (4): 25–32 https://doi.org/10.1177
/875697289903000405
Baker, B., D Murphy, and D Fisher 1983 “Factors affecting project
success ” In Handbook of project management, edited by D Cleland
and W King, 902 –919 New York: McGraw-Hill.
Baloi, D., and A D Price 2003 “Modelling global risk factors
affec-ting construction cost performance ” Int J Project Manage 21 (4):
261 –269 https://doi.org/10.1016/S0263-7863(02)00017-0
Barrett, P 2000 “Systems and relationships for construction quality.” Int J.
Qual Reliab Manage 17 (4 –5): 377–392 https://doi.org/10.1108
/02656710010298409
Bedell, R J 1983 “Terminating R&D projects prematurely.” Res Manage.
26 (4): 32 –35 https://doi.org/10.1080/00345334.1983.11756785
Belassi, W., and O I Tukel 1996 “A new framework for determining
criti-cal success/failure factors in projects ” Int J Project Manage 14 (3):
141 –151 https://doi.org/10.1016/0263-7863(95)00064-X
Belout, A 1998 “Effects of human resource management on project
effectiveness and success: Toward a new conceptual framework ” Int.
J Project Manage 16 (1): 21 –26 https://doi.org/10.1016/S0263
-7863(97)00011-2
Bertaux, D 1981 “From the life-history approach to the transformation of
sociological practice ” In Biography and society: The life history
ap-proach in the social sciences, edited by D Bertaux, 29 –45 London:
Sage Publications.
Chan, A P C., D Scott, and A P L Chan 2004 “Factors affecting the
success of a construction project ” J Constr Eng Manage 130 (1):
153 –155 https://doi.org/10.1061/(ASCE)0733-9364(2004)130:1(153)
Cheng, J., D G Proverbs, and C F Oduoza 2006 “The satisfaction levels
of UK construction clients based on the performance of consultants:
Results of a case study ” Eng., Constr Archit Manage 13 (6):
567 –583 https://doi.org/10.1108/09699980610712373
Cheung, S O., P S P Wong, and A W Y Wu 2011 “Towards an
organi-zational culture framework in construction ” Int J Project Manage.
29 (1): 33 –44 https://doi.org/10.1016/j.ijproman.2010.01.014
Chua, D K H., Y C Kog, and P K Loh 1999 “Critical success factors for
different project objectives ” J Constr Eng Manage 125 (3): 142–150.
https://doi.org/10.1061/(ASCE)0733-9364(1999)125:3(142)
Cooke-Davies, T 2002 “The ‘real’ success factors on projects.” Int J.
Project Manage 20 (3): 185 –190 https://doi.org/10.1016/S0263-7863
(01)00067-9
Cserháti, G., and L Szab´o 2014 “The relationship between success criteria
and success factors in organisational event projects ” Int J Project
Manage 32 (4): 613 –624 https://doi.org/10.1016/j.ijproman.2013.08
.008
Davis, K 2014 “Different stakeholder groups and their perceptions of
project success ” Int J Project Manage 32 (2): 189–201 https://doi
.org/10.1016/j.ijproman.2013.02.006
de Carvalho, M M., L A Patah, and D de Souza Bido 2015 “Project
management and its effects on project success: Cross-country and
cross-industry comparisons ” Int J Project Manage 33 (7): 1509–1522.
https://doi.org/10.1016/j.ijproman.2015.04.004
Denison, D R 2000 “Organizational culture: Can it be a key lever
for driving organizational change ” In The handbook of organizational
culture, edited by S Cartwright and C Cooper, 347 –372 London:
Wiley.
Dozzi, S P., S M AbouRizk, and S L Schroeder 1996 “Utility-theory
model for bid markup decisions ” J Constr Eng Manage 122 (2):
119 –124 https://doi.org/10.1061/(ASCE)0733-9364(1996)122:2(119)
Field, A P 2000 Discovering statistics using SPSS for Windows:
Advanced techniques for the beginner London: Sage Publications.
Fong, P S., and C W Kwok 2009 “Organizational culture and knowledge
management success at project and organizational levels in contracting
firms ” J Constr Eng Manage 135 (12): 1348–1356 https://doi.org
/10.1061/(ASCE)CO.1943-7862.0000106
Fortune, J., and D White 2006 “Framing of project critical success factors
by a systems model ” Int J Project Manage 24 (1): 53–65 https://doi
.org/10.1016/j.ijproman.2005.07.004
Fragoso, T M., and F L Neto 2015 “Bayesian model averaging: A systematic review and conceptual classification ” Preprint, submitted September 29, 2015 http://arxiv.org/abs/1509.08864
Gaddis, P O 1959 The project manager Boston: Harvard Univ Garbharran, H., J Govender, and T Msani 2012 “Critical success factors influencing project success in the construction industry ” Acta Structilia
9 (2): 90 –108.
Gemuenden, H G., and T Lechler 1997 “Success factors of project management: The critical few-an empirical investigation ” In Proc., Innovation in Technology Management —The Key to Global Leader-ship: Portland Int Conf on Management and Technology, 375 –377 Piscataway, NJ: IEEE.
Grimm, L G., and P R Yarnold 2000 Reading and understanding MORE multivariate statistics Washington, DC: American Psychological Association.
Guest, G., A Bunce, and L Johnson 2006 “How many interviews are enough? An experiment with data saturation and variability ” Field Methods 18 (1): 59 –82 https://doi.org/10.1177/1525822X05279903 Hair, J F., W C Black, B J Babin, R E Anderson, and R L Tatham.
1998 Multivariate data analysis Upper Saddle River, NJ: Prentice Hall.
Hennink, M M 2013 Focus group discussions New York: Oxford University Press.
Hinkin, T R 1995 “A review of scale development practices in the study of organizations ” J Manage 21 (5): 967–988 https://doi.org/10.1177 /014920639502100509
Hossain, L 2009 “Communications and coordination in construction projects ” Constr Manage Econ 27 (1): 25–39 https://doi.org/10 1080/01446190802558923
Ibrahim, A., M Roy, Z Ahmed, and G Imtiaz 2010 “An investigation of the status of the Malaysian construction industry ” Benchmarking
17 (2): 294 –308 https://doi.org/10.1108/14635771011036357 Jha, K., and K Iyer 2007 “Commitment, coordination, competence and the iron triangle ” Int J Project Manage 25 (5): 527–540 https://doi org/10.1016/j.ijproman.2006.11.009
Jugdev, K., and R Müller 2005 A retrospective look at our evolving understanding of project success Newton Square, PA: Project Manage-ment Institute.
Kandelousi, N S 2011 “Key success factors for managing projects.” World Acad Sci Eng Technol Int J Social Behav Educ Econ Bus Ind Eng 5 (11): 1541 –1545.
Kärnä, S 2004 “Analysing customer satisfaction and quality in construction-the case of public and private customers ” Nordic J Surv Real Estate Res 2 (2): 67 –80.
Kärnä, S., J Junnonen, and V Sorvala 2009 “Modelling structure of cus-tomer satisfaction with construction ” J Facil Manage 7 (2): 111–127.
https://doi.org/10.1108/14725960910952505 Kashiwagi, D., J Kashiwagi, I Kashiwagi, and A Kashiwagi 2012.
“The source of degradation of the construction industry performance.”
J Adv Perform Inf Value 4 (2): 206 –222.
Kattara, H S., D Weheba, and O A El-Said 2008 “The impact of em-ployee behaviour on customers ’ service quality perceptions and overall satisfaction ” Tourism Hospitality Res 8 (4): 309–323 https://doi.org /10.1057/thr.2008.35
Kinicki, A., N Cole, V Digby, N Koziol, and R Kreitner 2010 Organizational behavior New York: McGraw-Hill.
Kinicki, A., and R Kreitner 2012 Organizational behavior: Key concepts, skills & best practices, Boston: McGraw-Hill.
Lechler, T 1997 Erfolgsfaktoren des Projektmanagements [Success factors of project management] Frankfurt, Germany: Lang Leung, M Y., S T Ng, and S O Cheung 2004 “Measuring construc-tion project participant satisfacconstruc-tion ” Constr Manage Econ 22 (3):
319 –331 https://doi.org/10.1080/01446190320000000000 Ling, F Y., S P Low, S Wang, and T Egbelakin 2008 “Models for predicting project performance in China using project management practices adopted by foreign AEC firms ” J Constr Eng Manage.
134 (12): 983 –990 https://doi.org/10.1061/(ASCE)0733-9364(2008) 134:12(983)
Trang 10Liu, A M., and M.-Y Leung 2002 “Developing a soft value management
model ” Int J Project Manage 20 (5): 341–349 https://doi.org/10
.1016/S0263-7863(01)00023-0
Liu, A M M 1999 “Culture in the Hong Kong real-estate profession: A
trait approach ” Habitat Int 23 (3): 413–425 https://doi.org/10.1016
/S0197-3975(99)00015-6
Love, P E., and G D Holt 2000 “Construction business performance
measurement: The SPM alternative ” Bus Process Manage J 6 (5):
408 –416 https://doi.org/10.1108/14637150010352417
Martin, M., and K Miller 1982 “Project planning as the primary
manage-ment function ” Project Manage Q 13 (1): 31–38.
Mauri, A G., R Minazzi, and S Muccio 2013 “A review of literature on
the gaps model on service quality: A 3-decades period: 1985-2013 ” Int.
Bus Res 6 (12): 134 https://doi.org/10.5539/ibr.v6n12p134
Maxwell, J R 2005 “Management of employee empowerment.” J Organ.
Cult Commun Confl 9 (1): 61.
Nerkar, A A., R G McGrath, and I C MacMillan 1996 “Three facets of
satisfaction and their influence on the performance of innovation
teams ” J Bus Venturing 11 (3): 167–188 https://doi.org/10.1016
/0883-9026(96)00002-X
Nguyen, L H., and T Watanabe 2016 “An investigation of the relationship
between project organizational culture and procurement approach of
construction project organizations ” Int J Soc Social Manage Syst.
1 (10): 50 –61.
Nguyen, L H., and T Watanabe 2017 “The impact of project
organi-zational culture on the performance of construction projects ”
Sustain-ability 9 (5): 781 https://doi.org/10.3390/su9050781
Ogunlana, S O 2010 “Beyond the ‘iron triangle’: Stakeholder perception
of key performance indicators (KPIs) for large-scale public sector
de-velopment projects ” Int J Project Manage 28 (3): 228–236 https://
doi.org/10.1016/j.ijproman.2009.05.005
Oguz, T., and S Serkan 2014 “Employee behaviors creating customer
satisfaction: A comparative case study on service encounters at a hotel ”
Eur J Tourism Hospitality Recreation 5 (2): 25 –46.
Omonori, A., and A Lawal 2014 “Understanding customers’ satisfaction
in construction industry in Nigeria ” J Econ Sustainable Dev 5 (25):
115 –120.
Pallant, J 2007 SPSS survival manual: A step-by-step guide to data
analy-sis using SPSS version 15 Maidenhead, UK: Open University Press.
Papke-Shields, K E., C Beise, and J Quan 2010 “Do project managers
practice what they preach, and does it matter to project success? ” Int J.
Project Manage 28 (7): 650 –662 https://doi.org/10.1016/j.ijproman
.2009.11.002
Parasuraman, A., V A Zeithaml, and L L Berry 1988 “Servqual:
A multiple-item scale for measuring consumer perc ” J Retailing
64 (1): 12.
Pierce, D., Jr 2013 Project scheduling and management for construction.
Hoboken, NJ: Wiley.
Pinto, J K., and D P Slevin 1988 Project success: Definitions and
measurement techniques Newton Square, PA: Project Management
Institute.
Prost, L., D Makowski, and M.-H Jeuffroy 2008 “Comparison of
step-wise selection and Bayesian model averaging for yield gap analysis ”
Ecol Model 219 (1): 66 –76 https://doi.org/10.1016/j.ecolmodel.2008
.07.026
Ratner, B 2010 “Variable selection methods in regression: Ignorable prob-lem, outing notable solution ” J Targeting Meas Anal Marketing
18 (1): 65 –75 https://doi.org/10.1057/jt.2009.26 Robbins, S P., and T Judge 2013 Organizational behavior Harlow, UK: Pearson.
Sharma, S., and S Mukherjee 1996 Applied multivariate techniques New York: Wiley.
Shenhar, A., and D Dvir 2008 “Project management research-the challenge and opportunity ” IEEE Eng Manage Rev 2 (36): 112–121.
https://doi.org/10.1109/EMR.2008.4534315 Thomas, G., and W Fernández 2008 “Success in IT projects: A matter of definition? ” Int J Project Manage 26 (7): 733–742 https://doi.org/10 1016/j.ijproman.2008.06.003
Tijhuis, W 2011 “Report-developments in construction culture research: Overview of activities of CIB W112 culture in construction ” J Quant Surv Constr Bus 1: 66 –76.
Todorovi´c, M L., D Č Petrovi´c, M M Mihi´c, V L Obradovi´c, and S D Bushuyev 2015 “Project success analysis framework: A knowledge-based approach in project management ” Int J Project Manage 33 (4):
772 –783 https://doi.org/10.1016/j.ijproman.2014.10.009 Walker, A 2011 Organizational behaviour in construction New York: Wiley.
Walker, A 2015 Project management in construction New York: Wiley Wang, D., W Zhang, and A Bakhai 2004 “Comparison of Bayesian model averaging and stepwise methods for model selection in logistic regression ” Stat Med 23 (22): 3451–3467 https://doi.org/10.1002/sim 1930
Wanous, J P., and E E Lawler 1972 “Measurement and meaning of job satisfaction ” J Appl Psychol 56 (2): 95 https://doi.org/10.1037 /h0032664
Williams, B., A Onsman, and T Brown 2010 “Exploratory factor analy-sis: A five-step guide for novices ” Australas J Paramedicine 8 (3):
990399 https://doi.org/https://doi.org/10.33151/ajp.8.3.93 Williams, P., N J Ashill, E Naumann, and E Jackson 2015 “Relationship quality and satisfaction: Customer-perceived success factors for on-time projects ” Int J Project Manage 33 (8): 1836–1850 https://doi.org/10 1016/j.ijproman.2015.07.009
Xiong, B., M Skitmore, B Xia, M A Masrom, K Ye, and A Bridge.
2014 “Examining the influence of participant performance factors
on contractor satisfaction: A structural equation model ” Int J Project Manage 32 (3): 482 –491 https://doi.org/10.1016/j.ijproman.2013 06.003
Xu, C.-J., A van der Schaaf, C Schilstra, J A Langendijk, and A A van ’t Veld 2012 “Impact of statistical learning methods on the predictive power of multivariate normal tissue complication probability models ” Int J Radiat Oncol 82 (4): 677 –684 https://doi.org/10.1016/j.ijrobp 2011.09.036
Yang, L.-R., C.-F Huang, and K.-S Wu 2011 “The association among project manager ’s leadership style, teamwork and project success.” Int J Project Manage 29 (3): 258 –267 https://doi.org/10.1016/j ijproman.2010.03.006
Zou, J., G Zillante, and V Coffey 2008 “Project culture in the Chinese construction industry: Perceptions of contractors ” Constr Econ Build.
9 (2): 17 –28 https://doi.org/10.5130/AJCEB.v9i2.3018