Hai Phong port III TRUCKING ROUTE: Hai Phong port -> Road No.. 1C Laos -> Nam Neun T-junction -> Provincial Road No.. Distance of trucking: 296 km 1 st section Specification on rou
Trang 1SURVEY REPORT For transit cargoes from Haiphong port-Vietnam to Huaphan province-Laos
I.Project information:
Name of project: Nam Peun 1 Hydro Power Plant project
Location: Nam Neun commune, Hua Muang district, Hua Phan province, Laos PDR
Lattitude: 19°57'58" N, 103°52'32" E
(pkg)
Dimensions (m) Weight
(tons/
pkg)
Remark
s Length Width Height
1 A.C GENERATOR with
4 ERECTION
II PORT OF DISCHARGE: HAI PHONG PORT
Port location:
Port's location: 20°52'N - 106°41'E
Pilot boarding position: 20°40'N - 106°51'E
Address: 8A Tran Phu street, Hai Phong city
Nam Peun 1 location
Trang 2- Length 42 km
- Channel depth: From pilot boarding position to Dinh Vu Port area: -7.3 m, From Dinh Vu Port to the main port
area: -5.5m
- Tidal regime: diurnal
- Average tidal range: 2.5m
- Maximum size of vessel accepted: 40.000 DWT
Storage facilities:
Total area: 521,570 m2,
Warehouse/shed: 36,550 m2 (of which CFS: 6,498m2)
Open storage: 485,020 m2, (of which CY: 247,640m2)
Hai Phong port
III TRUCKING ROUTE:
Hai Phong port -> Road No 5 -> Road No 10 -> Road No 1A -> Road No 7 -> Nam Can
border -> Road No 7 (Laos) -> Muang Kham junction -> Road No 1C (Laos) -> Nam Neun
T-junction -> Provincial Road No 3320 -> Nam Peun 1 jobsite Distance of trucking: 710 km
Trang 3Hai Phong port -> Road No 5 -> Road No.10 -> Road No.1A -> Dien Chau T-junction
Distance of trucking: 296 km
1 st section Specification on route:
- Some tolls on road, in which, Hoang Mai toll gate is the most narrow: Limited height of 5,5m, limited width of 4,5m
Hoang Mai toll gate
- Most of overhead bridges are 4.8m onwards
Overhead bridge at Km98+631/Road No.5
III.2nd section
Dien Chau T-junction -> Road No.7 -> Nam Can border gate: Trucking distance of 220
km
5, 0m
5,5
m
4,8
m
Trang 4Specification on route:
- Road is 6m – 7m in width and by asphalt
Road No 7 in Vietnam and welcome gates are from 5.3m – 7.1m
There is the passing point of raillway on road, there are some bridges without warning loading
capacity
III.3rd section
Nam Can border gate -Road No.7 – Muong Kham T-Juntion: Trucking distance of 77 km
6
m
5,3
m
Km 8 on road no 7
Trang 5
- Border gate size: Height of 4,8m and width of 3,75m However, there are bypass for over sized goods
Nam Can gate Bypass for oversized goods
- Laos border gate size
5.1m
9m 5.1m
Trang 6Nam Khan border gate (Laos)
- Hill is 10% in max and sharp curves and many curves over 27 metres
There are two sunk places at km06 and km40 on road
Many sections of road with 30 km limited speed maximum
III.4th section
Muang Kham T-junction -> Road No 1C (Laos) -> Nam Neun T-junction Distance of
trucking: 88 km
27-30 m
5 m
Trang 7Specification on road: all of 88 km from MuongKham to NamNeun has many hills and slopes and
curves with width of curve from 4.5 to 7 metres and the length of curve over 25 metres and slope
of hill upto 10%
Highway No 1C
- There are 3 bridges on this road However, critical bridge is named Nam Neun Song by
steel girders and concrete, length of span is 42m, payload 25 tons
25 m
m 4,5m
m
Trang 8
Nam Neun Song bridge
III.5th section
Nam Neun T-junction -> Provincial road No.3320 -> Nam Peun 1 hydro power plant
jobsite Trucking distance of 28.5 km
Specification on route:
Trang 9From Highway No.1C: Turn left, then turn right forward to job site
The route from Nam Neun T Juntion to site with the width from 4-6 metres
There is the total of 09 curves on route with the length from 20 – 27 metres
4m width
5.5m width
20m
Trang 10Curves together with high slope of hill (7-14%)
There are 03 muddy places on roads as pictures
There are 03 curves are sunk and damaged as above pictures
Ground of corner sunk and damaged
Ground of corner sunk and damaged
Trang 11There are some points sunk as above pictures
There are many places with the electrical column on road with limited width from column to
mountain wall
At km 26 + 500, turn left at Nampern Bridge forward the job site
3 metres (Km18) 3 metres
Job Site here (02
km from Nampern bridge)
4.8 m
Trang 12
IV.CONCLUSIONS AND SUGGESTIONS:
This route is sole alternative route for trucking goods from Vietnam port to site However the roads from Nam Can border gate to Muong Kham T Juntion and Nam Neun T Juntion to job
site have been deteriorated much with many dangerous points and making the difficulties in
operation of transport as above pictures
For stator of 65 tons, we must use hydraulic trailer of 8 axles minimum to transport to Nam Neun T Juntion and doing many works at this area before moving to site Use 2 prime movers to
pull trailer through the hill
Unloading area