Microsoft Word 05 1 EPC GE PTC M PR 00166 PFP Application Procedure Rev D2 SAO VANG AND DAI NGUYET DEVELOPMENT PROJECT Type of Document Procedure Page 1 of 21 PASSIVE FIRE PROTECTION APPLICATION PROCE.
Trang 1
SAO VANG AND DAI NGUYET DEVELOPMENT PROJECT
PASSIVE FIRE PROTECTION APPLICATION PROCEDURE
D2 Re-approved for Construction 17 Dec 2019 P.Q.Huy H.M.Dung N.B Hoang
D1 Approved for Construction 28 Oct 2019 P.Q.Huy H.M.Dung N.B Hoang
C2 Re-issued for Approval 20 July 2019 P.Q.Huy H.M.Dung N.B Hoang
C1 Issued for Approval 21 June 2019 P.Q.Huy H.M.Dung N.B Hoang
B1 Issued comment for review and 28 Jan 2019 P.Q.Huy H.M.Dung N.B Hoang
Prepared
By Reviewed By Approved By Approved
By IKC EPCIC Contractor
Document No.: 05-1_EPC-GE-PTC-M-PR-00166
EPCIC CONTRACTOR: PTSC MECHANICAL & CONSTRUCTION
Trang 2
Revision Record Sheet
Trang 3
Title: Passive Fire Protection Application Procedure Rev.: Date: Page: Doc No.: 05-1_EPC-GE-PTC-M-PR-00166 D2 17 Dec 2019 3 of 21 TABLE OF CONTENTS 1 SCOPE 4
2 DEFINITIONS & ABBREVIATIONS 4
3 CODES, STANDARDS AND REFERENCES 5
4 PERFORMANCE CRITERIA AND MATERIAL REQUIREMENTS 6
5 PAINTING APPLICATION 8
5.1 APPLICATOR 8
5.1.1 BLASTER AND PAINTER 8
5.1.2 PFP OPERATOR 8
5.2 PRE-BLASTING PREPARATIONS 10
6 PFP APPLICATION 14
6.1 MATERIAL PRE-HEATING 14
6.2 PLURAL COMPONENT QUIPMENT 14
6.3 ENVIRONMENTAL CONDITION 15
6.4 PFP APPLICATION 15
6.5 FINAL COAT APPLICATION 16
7 INSPECTION/ QUALITY CONTROL 17
8 SAFETY 20
9 APPENDICES 21
Trang 4
1 SCOPE
This procedure covers all the requirements for surface preparation and Passive Fire Protection (PFP)- intumescent coating type of new built offshore structure It also describes CONTRACTOR’s practice and specific quality programs in achieving highest quality standard for all products and services as to meet CONTRACTOR or COMPANY’s requirements
PFP intumescent coating type shall be applied to the structural member, fire/blast wall, vessel, and not applied to piping, shell of Condensate Stabilizer column, ESDV valves as per Passive Fire Protection Schedule and Listing Document No 05-1_EPC-SV-AEI-S-LA-00003
2 DEFINITIONS & ABBREVIATIONS
Company/ IKC Idemitsu Kosan Co., Ltd
Contractor/
PTSC PTSC Mechanical & Construction Co., Ltd
Sub-Contractor Contractor’s sub-contractor party for any part of the EPCIC work scope
Sub-Contractor/
Vendor The party who supply the equipment or material the necessary for Contractor to fulfill the EPCIC work scope
SVDN Project Sao Vang Dai Nguyet Project
QA/QC Quality Assurance/ Quality Control
ASTM The American Society for Testing and Materials
ISO International Organization for Standardization
NACE National Association of Corrosion Engineers
NFPA National Fire Protection Association
ITP Inspection and test plan
SDSS Super Duplex Stainless Steel (25% Cr)
D2
Trang 5
NORSOK S-001 Technical Safety
NORSOK M-501 Surface Preparation and Protective Coating
ISO 4624 Paints and varnishes – Pull-off test for adhesion
ISO 8501-1
Preparation of steel substrates before application of paints and related products – Visual assessment of surface cleanliness – Part 1: Rust grades and preparation grades of uncoated steel substrates and of steel substrates after overall removal of previous coatings
ISO 8501-3 Preparation of steel substrates before application of paints and related products – Visual assessment of surface cleanliness – Part 3: Preparation grades of welds,
edges and other areas with surface imperfections
ISO 8502-3
Preparation of steel substrates before application of paints and related products – Test for the assessment of surface cleanliness – Part 3: Assessment of dust on steel surfaces prepared for painting (pressure sensitive tape method)
ISO 8502-6
Preparation of steel substrates before application of paints and related products – Test for the assessment of surface cleanliness – Part 6: Extraction of soluble contaminants for analysis – The Bresle method
Trang 6
ISO 8502-9
Preparation of steel substrates before application of paints and related products – Test for the assessment of surface cleanliness – Part 9: Field method for the conductometric determination of water-soluble salts
ISO 8503 Preparation of steel substrates before application of paints and related products – Surface roughness characteristics of blast cleaned substrates
ISO 8504-2 Preparation of steel substrates before application of paints and related products – Surface preparation methods – Part 2: Abrasive blast cleaning
ISO 12944-4 Paints and varnishes – Corrosion protection of steel structures by protective paint systems – Part 4: Types of surface and surface preparation
ISO 12944-5 Paints and varnishes – Corrosion protection of steel structures by protective paint systems – Part 5: Protective paint systems
ISO 19840 Paints and varnishes – Corrosion protection of steel structures by protective paint systems – Measurement of, and acceptance criteria for, the thickness of dry film
on rough surfaces ISO 20340 Paints and varnishes – Performance requirements for protective painting systems for offshore and related structures SSPC PA2 Paint Application Specification No 2, Measurement of Dry Coating Thickness
with Magnetic Gauges SSPC-SP 1 Solvent Cleaning
SSPC-SP 10 /
NACE No 2 Near-White Blast Cleaning
Carboline Paint Pyroclad X1- Fire barrier system application manual
In terms of fire rating, there are three main performance criteria throughout a prescribed time of exposure to heat:
Stability - the structure shall fulfil its load bearing capacity throughout the fire exposure period,
Integrity - partitions shall prevent spread of flames and hot fumes throughout the fire exposure period,
Insulation - the unexposed side of partitions shall not reach surface temperatures in excess
of a certain level throughout the fire exposure period
Fire rating and Area application will be defined in accordance with document No AEI-S-LA-00003 Passive Fire Protection (PFP) Schedule and Listing and No 05-1_EPC-SV- AEI-S-SA-00003 Specification for Passive Fire Protection
05-1_EPC-SV-All materials will be installed & durable in offshore marine environment
Trang 7
Reinforcement mesh of the insulation (if required) is to be of non-metallic fiber carbon type using
an attachment method appropriate to the form of structure member, applied in strict accordance with Manufacturer’s specification and appropriate Certifying Authority approval
System including Pyroclad X1 + High Temperature Mesh from Carboline paint manufacturer has been qualified and chosen as intumescent PFP coating for SVDN Project Carboline shall provide the required thickness and reinforcement systems on the basis of the fire protection requirements detailed in the specification Details shall be provided of all relevant calculations to support the proposed PFP product and associated thickness/ application of the material This shall include, but not necessarily be limited to, details of the product with respect to strain limits, maximum deflection characteristics and the transmission of heat for each size of beam
The PFP systems must have a current certificate from Lloyd’s, DNV or other equivalent classification bodies if necessary and be tested using acceptable international methods by a recognized testing agency
The original materials for testing and applying on product are manufactured at the premises of
manufacture that certify on the Type approval certificates
In the selection and proposal of the PFP material, attention shall also be paid to:
The compatibility of the PFP material with the final coating product (i.e polyurethane) as indicated in Coating and Painting Specification (05-1_EPC-SV-AEI-M-SA-00001)
Smoke generation and toxicity of the PFP
Surface/Operating temperature of the piping or vessel to be PFP If structure elements are
to be PFP-ed, it is assumed highest ambient temperature
Weather ability and mechanical impact strength of the product The PFP material is required to survive to the offshore environmental conditions1 as defined for SV-CPP
Its resistance to chemicals (salts, solvents, acids, bases)
Fire performance, with regard to the duration and type of fire, to provide evidence acceptable to COMPANY that the PFP product proposed has been tested and shown to provide adequate protection Test details will also be required
Anti-corrosion performance if applied directly on substrate or compatibility and adhesive strength to underneath anti-corrosion coatings
Weight limitation imposed by the strength of the supporting structure The weight limitation will be achieved by the use of optimum PFP thickness that commensurate with the required level of protection
Adhesive strength and durability, providing evidence that the proposed PFP product has performed satisfactorily, with regards to adhesive strength and durability, under comparable environmental conditions
Trang 8
Ease of application and repair
The appropriate type of PFP for each Vessels and structure
The intumescent epoxy shall not be used in enclosed area where personnel could be present such as LQ and buildings The buildings shall be protected by inactive insulation that does not release toxic material
The proposed PFP material shall be approved for low smoke emission and non-toxicity and shall be submitted to COMPANY for acceptance
PFP Material Document shall have minimum:
- Fire Approval Certificate
- Certificate of Quality including Type/Designation, Batch Number, Name of Supplier,
Manufacturer
- Certificate of Origin,
- Quantity and Identification in accordance with delivery documentation
- Batch Numbers, Manufacture Date and Expiry date
- MSDS
- Product Datasheet
5.1 APPLICATOR
5.1.1 Blaster and Painter
Operators shall be qualified to tradesman level as blast-cleaner, painter, applicator etc The personnel shall have relevant knowledge of health and safety hazard, use of protection equipment, coating materials, mixing and thinning of coatings, coating pot-life, surface requirements etc
Personnel not qualified to tradesman level, shall document training and experience to the same level as a formalized tradesman education
5.1.2 PFP Operator
Personnel qualified will be selected for PFP coating sprayer qualification
Only personnel have passed the qualification test as described in below or trained by the PFP coating manufacturer are allowed to spray the PFP coating during production on the project
Each sprayer shall select the airless spray tip, mix components of the coating and add thinner according to the manufacturer’s instructions in use Adjust the spray pressure suitable for the coating manufacturer’s recommendations, carry out spraying of the coating in overlapping or crossing passes onto the surfaces to be coated The areas that cannot be properly coated by spraying will be trowel applied and rolled Measure WFT to ensure that the required coating thickness has been achieved
D2
Trang 9
Install the mesh reinforcement into the wet coated surface, overlap between the adjacent mesh pieces approximately 50mm to 150mm and roll thoroughly into the wet coated surface with the short nap roller lightly dampened with the coating manufacturer’s recommended thinner
Continue to apply PFP coating by trowel in the corners or areas that cannot be properly coated by spraying, then carry out spray application Measure WFT to ensure that the required coating thickness has been achieved Areas applied by trowel will be rolled by using the short nap rollers lightly dampened with the coating manufacturer’s recommended thinner to remove trowel marks
After the coating application is completed, the following inspection items shall be carried out:
Visual inspection of coating 100% of surface Coating shall be uniform
without sagging, trowel marks
or missed areas Dry film thickness 10 measurements Obtain the specified thickness
If the operators have not been working with the type of application or material within a period of
12 months, the applicator shall document that necessary supplementary training have been given before start of any work
5.1.3 Paint Manufacturer Support at Site
Irrespective of the Work Site or contracting entity, the paint manufacturer’s technical representative shall be present during the following operations:
Attending the painting / coating procedure qualification process to verify correct application of materials and use of equipment,
Attending the pre-start meeting,
Attendance on Site at the start of each different painting / coating system application,
Providing technical advice in the event of painting / coating problems with painting/coating materials and their application,
Site surveillance visits during the painting /coating execution period to ensure that the coating/painting systems are being applied in accordance with the manufacturer’s recommendations,
Providing a written report confirming satisfactory performance of painting/coating operations following each Site visit
Technical support described above shall be applied to all Work Site locations managed by the main fabrication Site including all subcontracted Work
Any technical concerns raised by the painting / coating manufacturer shall be addressed to the satisfaction of paint manufacturer and Company
Trang 10
5.1.4 Role of Inspector and Qualification
The Contractor inspector, Paint manufacturer shall be present in the fabrication yard during execution of painting activities
Minimum 01 inspector from Contractor and 01 inspector from Paint manufacturer and minimum qualification requirements for inspectors is NACE 2 or equivalent approved by Company
5.1.5 Qualification of supervisors, foremen and QC personnel
The Contractor’s foremen, supervisors and coating inspectors shall be present during Qualification and Training of PFP coating sprayers to ensure that coatings are being applied in accordance with the approved procedures
Personnel carrying out inspection and verification shall be certified as NACE coating inspector level II or a Company approved equivalent Inspection personnel shall have a minimum of five (5) years of painting/coating experience
On completion of PFP coating sprayer qualification test, the Contractor’s coating inspector shall issue and submit the sprayer qualification test to Company for review and approval
Any major surface defects, particularly surface laminations or scabs detrimental to the protective coating system shall be removed by suitable dressing Where such defects have been revealed during blast cleaning, and dressing has been performed, the dressed area shall be re-blasted to the specified standard
All welds shall be inspected and, if necessary, repaired prior to final blast cleaning of the area Surface pores, cavities etc shall be removed by suitable dressing or weld repair
Material list and IRN (if required) is available before blast cleaning
Trang 11
PS Ball/SC ball (size 0.6mm – 1mm & 1mm – 2mm)
Garnet 30/60, Garnet 16/30
Shot/Grit mix 30/60
Cut wire/ Steel shot
Blasting abrasive shall be dry, clean and free from contaminates It shall be of a type and size adequate to give required surface profile/ anchor pattern The abrasive shall free of contamination
of dust & chlorides Abrasive which have a tendency to shatter & adhere or embed in the steel surface shall not be used
To achieve the required anchor profile, abrasive particle size shall follow the surface preparation commentary of the SSPC, ISO manual as necessary to comply with SSPC-SP 10/ Sa 2.5
Surface preparation for coating application should be carrying out after all structural, mechanical, piping and welding works have been completed on the equipment
All fused flux shall be removed from welded areas and appurtenances When electrodes using a basic flux have been used, the welded area shall be cleaned of alkaline residues by rinsing with warm water prior to blast cleaning
Before and after blasting, all weld-lines shall be closely inspected for the presence of welding flux and spatter, silvers, inclusions, lamination, and underlying mill scale Imperfections shall be mechanically removed and the immediate area re-blasted
Working parts of machinery and valves, instruments, glass faces of gauges, light fittings, control panels and consoles, etc shall be protected (masked) against damage during abrasive blasting and from the ingress of blasting abrasives and residue, and from paint overspray
The final blasting is not permitted if the relative humidity is greater than 85%, or if the surface temperature is less than 3o C above the air dew point Blasting shall not be done adjacent to painting operations or coated surface that are not fully dry Blasting shall overlap previously coated surface by at least 150 mm
The compressed air supply for blasting shall be free of detrimental amounts of oil and water, adequate separators and traps shall be provided and shall be frequently checked, cleaned and emptied The compressed air shall be checked frequently by blotter test as per ASTM D 4285
Stainless steel and aluminum surface which are coated shall be solvent cleaned or/and roughening the steel surface by non-metallic sweep blasted or sanded down with sandpaper
No acid washes, cleaning solutions, solvents, or inhibited washes intended to prevent rusting shall
be applied to surfaces after abrasive blasting and prior to the first primer coat application
After blasting completed, all of contamination and spent abrasive shall be removed completely by clean and dry air compressed blowing or vacuum cleaning method The particle quantity and size
do not exceed rating 2 of ISO 8502-3
5.3.2 Solvent Cleaning and Power tool cleaning
If surfaces on machinery, equipment and/or other areas cannot be abrasive blasted without damage or contamination of moving parts or other critical surfaces, the surfaces shall be solvent
Trang 12
cleaned as specified in SSPC-SP 1 After solvent cleaning, the surfaces shall be cleaned by hand /
or power tool as specified in SSPC-SP 2/St2, SSPC-SP 3/St3 or SSPC-SP 11.
5.4 PAINTING APPLICATION
Coatings shall be applied under the environmental conditions established by the coating manufacturer No coating shall be applied under following circumstances:
On wet surfaces
When the Relative Humidity is above 85%
When the Surface Temperature is less than 3o C above the dew point
When ambient or Surface Temperatures are below 5oC and above 50oC or manufacturer’s recommendation
The Contractor shall verify that these conditions are met before coating begins, on a daily basis, with instruments in his possession, and keep records of these measurements
Wherever painting is carried out in the field and poor weather condition prevail adequate precautions shall be taken to protect the activity from adverse effects of wind, contamination and rain shall be covered by suitable material or canvas which do not absorb water
5.4.1 Primer coating
The initial primer coat shall be applied as soon as possible after surface preparation In all cases the primer coat shall be applied during daylight hours on the same day the surface is prepared, normally maximum 4 hours after blasting or before any rusting indication on the surface occurs However, this time can be shorter basing on the actual surround climate condition
In all cases the primer coat shall be applied during daylight hours on the same day the surface is prepared and before deterioration of the surface
Any surfaces inaccessible for proper coating application and / or inspection, shall be coated prior
to final assembly Specifically, flanges face and bolt holes shall be coated prior to final installation The IKC’s representative will designate inaccessible areas
5.4.2 Dryness
Prior to applying a successive coat, all coatings shall be allowed to dry at site ambient conditions for at least the minimum time specified by the coating manufacturer and the actual coating surface condition during inspection
5.4.3 Re-coating and Next coat
Each coat shall be in a proper state of cure or dryness before the application of the next coat Material shall be dry for re-coating when an additional coat can be applied without the development of any detrimental film irregularities, such as lifting or loss of adhesion of the undercoat Manufacturer’s instructions shall be followed
The maximum and minimum re-coating interval specified in the manufacturer's data sheets, will
be observed before successive coats are applied
Trang 13
Before apply next coat all damage to previous coats shall be touched up with the specified coating following item 5.5 Touch-up and Repairs of Paint Damage
The only exception to this may be after the application of a mist coat where the recommended coat interval may be reduced in accordance with the coating manufacturer's recommendations
re-Any thin spots or area missed in the application shall be re-coated and permit to dry before the next coat is applied
Each coat shall be sanded by proper sandpaper, cleaning or washing incase requirement before apply next coat
All areas such as external corners and edges, welds, bolts, nut and interstices (excluding galvanized surface) shall receive a stripe coat prior to application of the specified coat (excluding the inorganic zinc silicate primer) to ensure these areas have at least the minimum specified film thickness as to ensure continuity of the coating The stripe coat shall be allowed to become touch dry prior to coating with the specified coat
When successive coats of the same product have been specified, alternate coats shall be tinted sufficiently to produce enough contrast to indicate complete coverage of the surface When the paint is color of steel, or when the tinting of the final coat is objectionable, the first coat to be applied shall be tinted The tinting material shall be compatible with the material and not detrimental to its service life
The contact surface of earth bosses shall be masked after blast cleaning
Nameplates which cannot be removed shall be suitably masked before blast cleaning to protect from blasting abrasive and paint
5.4.5 Stripe coating
The stripe coat shall be carrying out by brush or by roller before and/or after each spray application on areas where difficult to cover by spray such as corners, edges, welds, bolts, nuts and interstices (excluding galvanized surfaces) to ensure the coating thickness as per paint specification The “stripe” coat shall be allowed to become touch-dry prior to coating with the specified coat The color of the stripe coat shall be different from the previous or subsequent coat
Trang 14
thickness as listed or clarified in Doc.No.05-1_EPC-GE-PTC-Q-LA-00101 Project Coating and Painting Matrix.
6 PFP APPLICATION
6.1 MATERIAL PRE-HEATING
Prior to introduction into plural component equipment the material shall be pre-heated to a minimum of 38 oC for 24 hours prior to application Cold material will not spray well and material that is over-heated will reduce the pot-life and working time Material can be heated using heated storage units or hot rooms These are normally constructed from storage containers that are insulated to maintain designed temperature and fitted with a suitable temperature controllable heater Smaller customer made hot boxes can be used for small projects to heat enough pails to maintain daily production Heated storage units or hot rooms shall be designed by PTSC engineering team for heating painting material Material temperature can be measured using a probe thermometer or IR gun
6.2 PLURAL COMPONENT QUIPMENT
Pyroclad X1 shall be applied by plural component equipment that is specifically designed for epoxy PFP application Plural component equipment pumps the part A and part B separately through the equipment until mixed and sprayed through the short whip hose These fixed ratio displacement pumps are equipped with transfer pumps, pressurized/heated holding tanks, inline fluid heaters, material lines heaters and high pressure mixing block with static mixing tube, whip hose and spray gun Air and power requirements may vary from different equipment manufacturers
Plural equipment set up:
- Material shall be pre-heated to a minimum of 38 oC prior to introduction to the pump units Thoroughly mix part A and B separately prior to use
- The pump and all lines shall be clean and free from any contamination Make sure all the fluid lines, air lines, connections at air motor and lower units are tightened and check on daily basis
- Set tank heaters: part A 60oC / part B 60oC or the coating manufacturer’s recommendation
- Set inline fluid heaters and line heaters to 60-71oC or the coating manufacturer’s recommendation Re-circulate Pyroclad X1 at low pressure until the exit temperature of the material at the mixing block reaches 50-55 oC At this temperature range the material is sufficiently heated to begin spraying
- Check ratio to ensure a 1:1 ratio mix by volume
- Verify gun exit temperature of 50-55 oC (1230F-1320F)
- Displacement pump pressure should be between 175 bar-310 bar (2500 psi – 4500 psi)
- Verify that the spray tip is not worn in the range of 0.027”-0.035”
Trang 15
- Preparation of trowel, knife, scissors, roller, wet film thickness, table, balance, etc
Table 1: PLURAL EQUIPMENT SETTINGS FOR APPLICATION
6.3 ENVIRONMENTAL CONDITION
- Before application PFP, confirm that proper environmental conditions are met Minimum ambient temperature: 5oC (410F) and rising, maximum relative humidity 85%, steel surface temperature must be 3 oC (370F) above the dew point temperature
- Confirm that the surface has been prepared to specification
- Verify that Carboline primer coat and sealer coat approved has been correctly installed to correctly thickness and is properly cured
- Confirm that all block out and areas that may receive overspray are properly masked off
6.4 PFP APPLICATION
- Spraying PFP coating to PFP area, using overlapping and crossing technique
- The area that can’t be properly coated by spraying, it will be applied by trowel and roller
- Measure WFT to ensure that the required coating thickness in accordance with specification
- Only use Carboline High Temp Mesh, High temperature mesh design detail and application shall be followed Pyroclad X1- Fire barrier system application manual
- Pre-cut all High Temp Mesh prior to commencing the application of Pyroclad X1 and apply pre-cut High Temp Mesh reinforcement into the wet coating where required
- For exact design details on mesh placement and requirements refer to the Pyroclad X1 Application Manual
- For hydrocarbon pool fire ratings only, wide flange sections require mesh around the flanges terminating 50 mm (2”) on the inside of the flange If the web depth is greater than
355 mm (14”), the web must also be meshed with the mesh terminating a 12.5 mm (½”)
Trang 16
from the web radius Overlaps with adjacent mesh pieces must be a minimum of 50 mm (2”)
- All hollow sections require a complete (100%) wrap with High Temp Mesh with a 50 mm (2”) overlap at all seams
- All jet fire applications require a complete (100%) wrap with High Temp Mesh with a 150
mm (6”) overlap at all seams
- Apply the High Temp Mesh into the wet Pyroclad X1 at the approximate mid-point to the 2/3 point of the coating (dependent on specific design) ± 1 mm (40 mils)
- Ensure that the High Temp Mesh is completely embedded into the wet Pyroclad X1 using trowels and/or solvent resistant mohair rollers Lightly mist rollers with a Carboline approved solvent to aid in back rolling
- After the installation of the High Temp Mesh, a light 1mm (40 mils) coat of Pyroclad X1 should be spray applied to fully encapsulate the mesh or continue building the next full coat of Pyroclad X1
- Build material to final thickness in as many coats required using solvent moistened mohair rollers to smooth any imperfections in the coating Surface finish must meet project specifications
- After the passive fire protective coating material has cured, and before application of topcoat, the thickness of the coating shall be checked
6.5 FINAL COAT APPLICATION
- Carboline topcoat approved in accordance with Coating system No.5A of project shall be used
- Ensure that the Pyroclad X1 system has been properly installed and the High Temp mesh
is properly embedded into the material
- Ensure that Pyroclad X1 has been applied to the specified dry film thickness by using an electronic or magnetic dry film thickness gauge
- The Pyroclad must be sufficient cured and be clean, dry and free of any contamination prior to topcoat application
- Ensure topcoat is applied within manufacturer’s stated ambient conditions, temperature and relative humidity specifications
- The topcoat shall be applied in accordance with the manufacturer and project specification 6.6 COAT BACK
In accordance with NORSOK S-001, Coat-backs are required on unprotected structural elements with a cross-sectional contact area equal or greater than 1 000 mm2 per m2 of fireproofed structural elements Minimum coat back distances shall be 450 mm
6.7 PFP THICKNESS
Trang 17
PFP thickness will strictly follow Carboline Paint Manufacturer’s recommendation and calculation (Appendix 1)
Inspection and testing shall be carried out in accordance with Table 2 and ITP for PFP Coating Surfaces shall be accessible until final inspection is carried out
Table 2 - Inspection and testing
In accordance with
Specified requirements
No blasting or coating
Visual
examination
Visual for sharp edges weld spatter slivers, rust grade, etc ISO 8501-3
100 % of all surfaces
No defects, see specified requirements
Defects to be repaired
Cleanliness a) ISO 8501-1 b) ISO 8502-3
a) 100 % visual
of all surfaces b) Spot checks
a) In accordance with specified requirements b) Maximum quantity and size rating 2
a) Re-blasting b) Re-cleaning and
retesting until acceptable
Salt test ISO 8502-6 and ISO 8502-9 Spot checks
Maximum conductivity corresponding to
20 mg/m2 NaCl
Repeated washing with potable water and retesting until
acceptable
Roughness
Comparator, stylus instrument or testex tape (see ISO 8503)
Each component
contamination, solvent retention, pinholes/popping, sagging and surface defects
100 % of surface after each coat
According to specified requirements Repair of defects
sheet
Repair, additional coats or recoating
Trang 18
as appropriate
Adhesion
ISO 4624, using equipment with an automatic centered pulling force, and carried out when coating system are fully cured
Batch Test/
Spot checks
5 Mpa with DFT 6mm without mesh
Coating to be rejected
PTSC MC shall give a painting schedule (Painting Inspection Request) to client a minimum of 24 hours noticed in advance of surveillance
7.2 VISUAL INSPECTION
Individual coats and completed coating shall be visually inspecting for appearance Coating shall
be free from sagging, dry spray, pinholes, blisters and other types of coating application defects and shall bear no coating damages
7.3 FILM THICKNESS
7.3.1 Measurement thickness
During coating, the wet film thickness shall be spot- checked, thickness of each coat shall be measured DFT by means of an electronic magnetic type thickness gauge E345 or E456
Equipment for measurement thickness shall be in testing date and calibrated before using
7.3.2 Dry Film Thickness (DFT) Value
The thickness of each coat shall be determined prior to the application of subsequent coats in accordance with SSPC PA-2 with the allowed spot average maximum and minimum coating thickness as listed or clarified in 05-1_EPC-GE-PTC-Q-LA-00101- Project Coating and Painting Matrix
At least three gage readings shall be taken for each thickness determination At least five separate thickness determinations shall be taken for each 10 square meters of coated surface On coated surfaces less than 10 square meters in area, at least three thickness determinations shall be taken The results of the coating thickness check shall be recorded on the Contractor’s coating inspection report
Minimum Thickness: The average of the spot measurements for each 10 m2 (100 ft2) area shall not be less than the specified minimum thickness No single spot measurement in any 10 m2 (100
Trang 19
ft2) area shall be less than 80% of the specified minimum thickness Any gage reading may underrun by a greater amount If the average of the spot measurements for a given 10 m2 (100 ft2) area meets or exceeds the specified minimum thickness, but one or more spot measurements is less than 80% of the specified mini-mum thickness, additional measurements may be made to define the nonconforming area
Maximum Thickness: The average of the spot measurements for each 10 m2 (100 ft2) area shall not be more than the specified maximum thickness No single spot measurement in any 10 m2(100 ft2) area shall be more than 120% of the specified maximum thickness Any gage reading may overrun by a greater amount If the average of the spot measurements for a given 10 m2 (100
ft2) area meets or falls below the specified maximum thickness, but one or more spot measurements is more than 120% of the specified maximum thickness, additional measurements may be made to define the nonconforming area Manufacturers’ literature may be consulted to determine if higher maximum thickness readings are allowable under specific circumstances
Particular attention should be made to corners of painted surface Where minimum thickness levels are not reached, the corners will be repainted to achieve the minimum DFT requirements
7.4 TEMPERATURE AND RELATIVE HUMIDITY
Temperature and relative humidity shall be measured with a calibrated temperature gauge and a hygrometer
Readings shall be taken prior to the commencement of blasting and/or painting and at regular intervals if there are changes in climatic conditions
7.5 ADHESION
Coating may be tested by the Company for adhesion when deficiencies in the surface preparation
or painting system are suspected, or each batch Where adhesion is not sufficient to provide sound protection, the coating shall be removed and the area recoated as specified Adhesion will be checked with the Contractor supplied Elcometer Adhesion Tester in accordance with ISO 4624 at locations selected by the COMPANY
7.6 SURFACE PREPARATION- FINAL CONDITION
The blast cleaned surface shall be inspected to ensure that the areas are clean, dust free, dry and comply with standard requirements
Surface cleanliness shall be check according to ISO 8501-1 picture standard and measurement of dust level after blast cleaning Reference ISO 8502-3 Class 2 or better
Surface profile shall be checked accordingly to ISO 8503 by Comparator, stylus instrument (Elcometer 224) or testex tape
The above reading shall be submitted together with the daily blasting and Painting Inspection Report
Tests for soluble salts on blasted surface- Reference ISO 8502-9 Measurement of the levels of soluble salts corresponding to a NaCL content of 20 mg/m2
Trang 20
7.7 DAILY LOG/REPORT
The daily log of the items which have been painted will be available to the COMPANY at all
times The daily log is a supplement to the Subcontractor’s standard painting inspection reporting
system and it shall be maintained accurately and reviewed for content and accuracy by
COMPANY Inspector on a daily basis
Contractor shall maintain the following conditions in the daily log as a minimum:
As a minimum requirement for each system the following aspects of the work shall be documented and recorded in coating inspection report:
Ambient conditions (at each occasion of abrasive blast cleaning or coating application) including ambient temperature, surface temperature, dew point and relative humidity
Coating Supplier, coating batch number, cure time, thinner and percentages used and gallons of material used
Quality of surface preparation/surface profile
Dry film thickness of each coat
Dry film thickness of the total system
Visual aspect of the coating
The coating inspection reports must be counter signed by the COMPANY’s nominated Representative
Material Safety Datasheets (MSDS) shall always be available for review during transport and prior to the application of the product Manufacturer’s instructions for the safe handling of products shall be followed to minimize the risk of injury or creation of health hazards to personnel
Storage, mixing and application of the paint and coating materials shall be performed strictly in accordance with the manufacturer's recommendations
The correct use of personal protection equipment (PPE) shall be employed during the coating preparation and application
Abrasive blasting and spray coating shall be performed with approved equipment by experienced operators
The Contractor shall provide all operators with hoods for protection against abrasive and with paint masks that are OSHA approved for extended service The hoods and masks shall be worn at all times when work is being done
Pressure vessels, such as sand hoppers and compressed-air volume tanks, shall be protected from over-pressurization with automatic pressure relieving devices
Trang 21
Pressure nozzle controls shall be of the fail-safe, dead-man type
Pressure hoses shall be pressure tested and certified and hose connections shall incorporate a positive locking mechanism to prevent accidental disconnection (for example, quick-connect connections shall have safety wire in place)
Adequate ventilation shall be provided in confined areas with blowers capable of a minimum of
12 air changes per hour
Spray and blasting equipment in confined areas shall be securely grounded to dissipate static electrical charges
Hand tool shall be made of spark-proof materials
Appropriate air-fed masks should be used during blasting and coating operations Other personnel
in the vicinity shall wear suitable protective masks or respirators when necessary Adequate ventilation must be provided in confined spaces and when using air-fed masks in these areas, attention should be paid to the possibility of explosive vapors build-up As a minimum, dust, rust and vapors should be directed away from the operator by wind or extraction fan
All equipment, particularly nozzles, tanks, piping and cable trays and cable ladders shall be earthed to prevent sparking and electric shocks from static electricity
9 APPENDICES
- Appendix 1: PFP Thickness Calculation Table_ Remove PFP application for Pipe spools,
- Appendix 2: Pyroclad X1- Fire barrier system application manual
D2
Trang 22Design and thickness of Pyroclad X1 for fire protection
of divisions and supporting structure for Sao Vang
Definitions of fire rated divisions
There are some misconception over the requirements of a fire rated division (bulkhead), what he requirements of the construction are and what the fire protection coating is required to achieve
We refer to the design guidelines issued by DNVGL and HSE in the UK explaining what the requirements are (both documents available on request from Carboline)
There are two separate requirements, ‘insulation’ period is designated by the number but stability/structural integrity is independent of the number Regardless of the number the division and all its components must be maintained for 120min Practically this means that the supporting structure must be maintained with a 2-hour rating to 400oC This applies whether the fire source is Hydrocarbon or jet fire
PFP arrangement for fire divisions constructed along Truss 2 and Truss 5
TRUSS 2 Truss 2 shall be protected to a rating of H-0 This shall require 6.5mm of Pyroclad X1 incorporating high temperature reinforcement
Should jet fire protection be required then in accordance with the DNV certification, the thickness shall again
be 6.5mm incorporating high temperature reinforcement
TRUSS 5 Truss 5 shall be protected to a rating of H-60 This shall require 11.6 mm of Pyroclad X1 incorporating high temperature reinforcement
Should jet fire protection be required then in accordance with the DNV certification, the thickness shall again
be 11.6 mm incorporating high temperature reinforcement
FIRE WALL - UNDER CELLER DECK Fire Wall shall be protected to a rating of H-0 This shall require 6.5mm of Pyroclad X1 incorporating high temperature reinforcement
Should jet fire protection be required then in accordance with the DNV certification, the thickness shall again
be 6.5mm incorporating high temperature reinforcement
(DNV certification is an attachment to this document)
Appendix 1
Trang 23Certificate No:
TAF00000G3
This is to certify:
That the Class H Fire Wall and Bulkhead
with type designation(s)
Pyroclad X1 - Bulkhead
Issued to
Carboline Company
St Louis MO, United States
is found to comply with
DNV GL offshore standards
Application :
Approved for use as fire retarding bulkhead of class H-0, H-60 and H-120
Product approved by this certificate is accepted for installation on all vessels classed by DNV
GL
This Certificate is valid until 2021-12-02
Issued at Høvik on 2016-12-03
for DNV GL DNV GL local station: Houston
Approval Engineer: Tomasz Werchowicz
Petter Langnes Head of Section
This Certificate is subject to terms and conditions overleaf Any significant change in design or construction may render this Certificate invalid The validity date relates to the Type Approval Certificate and not to the approval of equipment/systems installed
Trang 24Wet density of Pyroclad X1 is 1035-1110 kg/m3
Table 1: H-bulkhead rating and corresponding thickness of “Pyroclad X1”:
Rating DFT Comment
H-0 6,5 mm No temperature limit
H-60 11,6 mm Max temperature rise of 140 ºC / 180 ºC (avg / single) after 60 min
H-120 12,5 mm Max temperature rise of 140 ºC / 180 ºC (avg / single) after 120 min
The materials are manufactured at the premises of: Carboline Company, 95 Airpark Vista Blvd Dayton,
NV 89403, USA
Application/Limitation
The protective coating is not defined as non-combustible and should not be used in accommodation or in enclosed areas
Minimum fabric overlap shall be not less than 50 mm
Restricted application: Fire against insulated side
The application of the protective coating is to be performed in accordance with the manufacturer's application manual Alternative primers and topcoats may be used provided they have been tested and approved by the manufacture
Each product is to be supplied with its manual for application and maintenance
Type Approval documentation
Certification in accordance with Class Programme DNVGL-CP-0338, October 2015
Pyroclad X1 Fire Barrier System Application Manual, Rev.0, dated February 2013 from Carboline Co., St Louis, US
• No 100515706SAT-003A, Rev.1 dated 14th June 2012,
• No 100515706SAT-003B, Rev.1 dated 14th June 2012,
• No 100700843SAT-004B, dated 28th February 2013,
• No 100463890SAT-016 dated 16th June 2012,
all from from Intertek Evaluation Center, Texas, US
Tests carried out
Tested according to IMO FTP Code Part 3 and in compliance with IMO 2010 FTP Code Ch 8, with the furnace temperature following the hydrocarbon curve specified in EN 1363-2
Trang 26Project – Idemetsu Sao Vang Dai Nguyet Cellar Deck Pyroclad X1 Loadings
Date: 18/07/2019
Ref: MJO
PFP Contractor: PTSC
Cellar Deck EOS + 16500 / 60 min jet fire protection 400oC limiting temperature
(m-1) Member
Pyroclad X1 thickness for
HC fire (mm)
Pyroclad X1 thickness for jet fire exposure (mm)
Total thickness of Pyroclad X1 (mm)
The MTO is estimated based on all available /information provided The Contractor shall verify the areas for fireproofing
The fire protection is based on Third Party Certification
The primer/ tiecoat and topcoat system shall be compatible with Pyroclad X1 and approved by Carboline
Michael J Ogles – Director Global Fireproofing
Trang 27Project – Idemetsu Sao Vang Dai Nguyet Main Deck Pyroclad X1 Loadings
Date: 18/07/2019
Ref: MJO
PFP Contractor: PTSC
Main Deck EOS + 24500 / 60 min pool fire protection plus 15 min jet fire, 400oC limiting temperature
Width Depth Web Flange Hp/a (m -1 ) Member
Pyroclad X1 thickness for HC fire (mm)
Pyroclad X1 thickness for jet fire exposure (mm)
Total thickness
of Pyroclad X1 (mm)
150.00 300.00 7.1 10.7 199.65 IPE 300 10.60 1.10 11.70 180.00 400.00 8.6 13.5 163.96 IPE 400 10.10 1.10 11.20 300.00 800.00 12.0 20.0 117.23 PG 51 8.50 1.10 9.60 300.00 390.00 11.0 19.0 108.56 HE400A 8.20 1.10 9.30 300.00 490.00 12.0 23.0 97.03 HE500A 7.40 1.10 8.50 400.00 800.00 16.0 25.0 86.50 PG 53 6.50 1.10 7.60 200.00 190.00 6.5 10.0 189.42 IPE 270 10.5 1.10 11.60 135.00 270.00 6.6 10.2 211.71 IPE 500 10.9 1.10 12.00
General Material
The MTO is estimated based on all available /information provided The Contractor shall verify the areas for fireproofing The fire protection is
based on Third Party Certification
The primer/ tiecoat and topcoat system shall be compatible with Pyroclad X1 and approved by Carboline.
Michael J Ogles – Director Global Fireproofing
Trang 28Project – Idemetsu Sao Vang Dai Nguyet Upper Deck Pyroclad X1 Loadings
Date: 18/07/2019
Ref: MJO
PFP Contractor: PTSC
Upper Deck EOS + 34500 / 60 min pool fire protection plus 15 min jet fire, 400oC limiting temperature
(m -1 ) Member
Pyroclad X1 thickness for
HC fire (mm)
Pyroclad X1 thickness for jet fire exposure (mm)
Total thickness of Pyroclad
The MTO is estimated based on all available /information provided The Contractor shall verify the areas for fireproofing The fire protection is
based on Third Party Certification
The primer/ tiecoat and topcoat system shall be compatible with Pyroclad X1 and approved by Carboline
Michael J Ogles – Director Global Fireproofing
Trang 29Project – Idemetsu Sao Vang Dai Nguyet Cooling Deck Pyroclad X1 Loadings
Date: 18/07/2019
Ref: MJO
PFP Contractor: PTSC
Cooler Deck EOS + 42500 / 30 min jet fire protection 400oC limiting temperature
Pyroclad X1 thickness for HC fire (mm)
Pyroclad X1 thickness for jet fire exposure (mm)
Total thickness of Pyroclad X1 (mm)
The MTO is estimated based on all available /information provided The Contractor shall verify the areas for fireproofing The fire protection is
based on Third Party Certification
The primer/ tiecoat and topcoat system shall be compatible with Pyroclad X1 and approved by Carboline
Michael J Ogles – Director Global Fireproofing
Trang 30Project – Idemetsu Sao Vang Dai Nguyet Pyroclad X1 Loadings
Pyroclad X1 thickness (mm)
SV-20-VA-001 Test Seperator 2600.00 1500.00 22.0 22.0 91.21 Saddle H60 6.00
SV-20-VA-002 HP Seperator 26400.00 1500.00 22.0 22.0 90.95 Saddle H60 6.00
Diameter Wall thickness
Width Depth Web Flange
SV-20-VA-003 MP Seperator 2250.00 1400.00 22.0 22.0 91.25 Saddle J60 8.50
Diameter Wall thickness
SV-20-VE-005 Condensate Stabilizer column 1500.00 Required Vessel J60
SV-20-VE-005 Condensate Stabilizer column 2000.00 Required Skirt J60 6.70
Diameter Wall thickness
Width Depth Web Flange
SV-20-VA-004 TU Slug catcher 2550.00 1500.00 22.0 22.0 91.21 Saddle J60 8.50
Diameter Wall thickness
SV-20-VG-002 Dewpointing LT Seperator 2000.00 80.00 13.02 Vessel J60 7.00
Width Depth
Trang 31General Material
The MTO is estimated based on all available /information provided The Contractor shall verify the areas for fireproofing
The fire protection is based on Third Party Certification
The primer/ tiecoat and topcoat system shall be compatible with Pyroclad X1 and approved by Carboline
SV-20-VG-002 Dewpointing LT Seperator 2000.00 12.00 83.84 Skirt J60 8.00
Width Depth Web Flange
SV-20-VD-001 HP Flare KO Drum 2400.00 1500.00 12.0 12.0 166.99 Saddle H60 9.00
Michael J Ogles – Director Global Fireproofing
Trang 32Form code: TA 1411a Revision: 2015-05 www.dnvgl.com Page 1 of 11
TYPE APPROVAL CERTIFICATE
Certificate No:
TAF00000G4
This is to certify:
That the Structural Fire Protection
with type designation(s)
Pyroclad X1 - I section
Issued to
Carboline Company
St Louis MO, United States
is found to comply with
DNV GL offshore standards
Application :
Approved for use as a system for fire protection of structural steel I sections
Product approved by this certificate is accepted for installation on all vessels classed by DNV
DNV GL local station: Houston
Approval Engineer: Tomasz Werchowicz
for DNV GL
Petter Langnes Head of Section
Trang 33Wet density of Pyroclad X1 is 1035-1110 kg/m3
The materials are manufactured at the premises of Carboline Company, 95 Airpark Vista Blvd, Dayton,
NV 89403, USA
Application/Limitation
The thickness of “Pyroclad X1” system to be applied to avoid temperatures to rise on the steel substrate less than 200ºC, 250ºC, 300 ºC, 350ºC, 400ºC, 450ºC, 500ºC, 550ºC and 600ºC for 'I” sections, are given in appendix table 1-9
The protective coating is not defined as non-combustible and should not be used in accommodation or in enclosed areas
Potential damage of the structural fire protection material following an explosion has not been
considered
Minimum fabric overlap shall be not less than 50 mm
The approval refers only to the fire resistance properties of the system
The application of the protective coating is to be performed in accordance with the manufacturer's application manual Alternative primers and topcoats may be used provided they have been tested and approved by the manufacture
Each product is to be supplied with its manual for application and maintenance
Type Approval documentation
Certification in accordance with Class Programme DNVGL-CP-0338, October 2015
Pyroclad X1 Fire Barrier System Application Manual, Rev.0, dated October 2012 from Carboline Co., St Louis, US
Technical Note 071912 dated 19th July 2012 from Carboline Co., St Louis, US
Test Report No 100463890SAT-011 dated 23rd July 2012 from Intertek Evaluation Center, Texas, US Test Report No 100463890SAT-016 dated 16th June 2012 from Intertek Evaluation Center, Texas, US Evaluation No 101513920SAT-008 dated 10th June 2014 from Intertek Testing Services, Texas, US
Tests carried out
Tested according to BS 476: Part 20 with HC-curve according to ISO 834-3
Trang 34Job Id: 262.1-024337-1
Certificate No: TAF00000G4
Appendix to certificate TAF00000G4 for Carboline Company
Table 1: Thickness of “PYROCLAD X1” system for fire protection of “I” sections for a critical temperature
The maximum thickness of protection material up to the required Hp/A [m-1] shall be used
Hp/A = Ratio between Heat perimeter and cross sectional Area of the section, [m-1]
Trang 35Job Id: 262.1-024337-1
Certificate No: TAF00000G4
Appendix to certificate TAF00000G4 for Carboline Company
Table 2: Thickness of “PYROCLAD X1” system for fire protection of “I” sections for a critical temperature
The maximum thickness of protection material up to the required Hp/A [m-1] shall be used
Hp/A = Ratio between Heat perimeter and cross sectional Area of the section, [m-1]
Trang 36Job Id: 262.1-024337-1
Certificate No: TAF00000G4
Appendix to certificate TAF00000G4 for Carboline Company
Table 3: Thickness of “PYROCLAD X1” system for fire protection of “I” sections for a critical temperature
The maximum thickness of protection material up to the required Hp/A [m-1] shall be used
Hp/A = Ratio between Heat perimeter and cross sectional Area of the section, [m-1]
Trang 37Job Id: 262.1-024337-1
Certificate No: TAF00000G4
Appendix to certificate TAF00000G4 for Carboline Company
Table 4: Thickness of “PYROCLAD X1” system for fire protection of “I” sections for a critical temperature
The maximum thickness of protection material up to the required Hp/A [m-1] shall be used
Hp/A = Ratio between Heat perimeter and cross sectional Area of the section, [m-1]
Trang 38Job Id: 262.1-024337-1
Certificate No: TAF00000G4
Appendix to certificate TAF00000G4 for Carboline Company
Table 5: Thickness of “PYROCLAD X1” system for fire protection of “I” sections for a critical temperature
The maximum thickness of protection material up to the required Hp/A [m-1] shall be used
Hp/A = Ratio between Heat perimeter and cross sectional Area of the section, [m-1]
Trang 39Job Id: 262.1-024337-1
Certificate No: TAF00000G4
Appendix to certificate TAF00000G4 for Carboline Company
Table 6: Thickness of “PYROCLAD X1” system for fire protection of “I” sections for a critical temperature
The maximum thickness of protection material up to the required Hp/A [m-1] shall be used
Hp/A = Ratio between Heat perimeter and cross sectional Area of the section, [m-1]
Trang 40Job Id: 262.1-024337-1
Certificate No: TAF00000G4
Appendix to certificate TAF00000G4 for Carboline Company
Table 7: Thickness of “PYROCLAD X1” system for fire protection of “I” sections for a critical temperature
The maximum thickness of protection material up to the required Hp/A [m-1] shall be used
Hp/A = Ratio between Heat perimeter and cross sectional Area of the section, [m-1]