Objectives: To install 12 bottles of water-refill points in building A of FTU within 2 months from 6-7/2021 with an estimated budget of 60 million VND.. The water dispensers would be dis
Trang 1FOREIGN TRADE UNIVERSITY FACULTY OF BUSINESS ADMINISTRATION
Project Group Work
To install water dispensers on building A of FTU
Instructor: Dr Dao Thi Thuong, Dr Nguyen Thi Hoa Hong
Hanoi, 2021
TABLE OF CONTENTS
download by : skknchat@gmail.com
Trang 2C Requirements
D Project Limits and exclusions
II Work Breakdown Structure
III Organization Breakdown Structure
IV Responsibility Matrix
V In-Depth Schedule
VI Preliminary risk analysis
Trang 3I Scope Statement
A Objectives: To install 12 bottles of water-refill points in building A of FTU
within 2 months from 6-7/2021 with an estimated budget of 60 million VND The water
dispensers would be distributed as follow:
8 water-refill points on the first floor
2 water-refill points on the 4th floor
2 water-refill points on the 6th floor
B Deliverables:
1 Research on Internet and evaluate between supplier to find suitable
dispenser and bottle supplier
2 Prepare proposal and compose project budget estimation to send to the
board of the university
3 Finding suitable location to place the water-refill points and places for
storage
4 Purchase bottles and dispensers
5 Logistics and transportation of bottles and dispensers after purchase
6 Refill-points and hotline installation
7 Project termination and delegate responsibility to other parties
C Milestones:
Choose a suitable supplier of bottles and dispensers 03.06.2021 FTU approval of suppliers and disbursement
23.06.2021 Receive all dispensers and bottles 28.06.2021 Dispensers and hotline installation 30.06.2021
Delegate responsibility to authorized parties 22.07.2021
D Technical requirements:
- Hotline available to contact when an issue occurs
- Setting up queue line and sign for refilling water
- Checking and replacing water when empty
- Bootle volume must be 19l
- The water temperature in the hot bulb must reach at least 60 Celsius degree
and able to contain at least 1l of water
- The water temperature in the cold bulb must decrease to at least 10 Celsius
download by : skknchat@gmail.com
Trang 4degree and able to contain at least 1l of water -The voltage of the dispenser must be 220V, 1.2A
E Limit and exclusion:
Decoration of the bottles and dispenser would not be include Removal or relocate bottles, dispensers due to any reason after delegation
of responsibility would not be induce Maintenance of dispenser would be responsible by both project team members and the contractors 1 week after delegation
Hotline of dispenser would be responsible project team members and the contractors 1 week after delegation
Project team members have no right and responsibility to plug in the dispensers Those rights are held by the board of the university.
F Customer review: Dr Dao Thi Thuong, Dr Nguyen Thi Hoa Hong
Trang 5II Work Breakdown Structure
For closer speciation here is the link that we did the diagram:
https://drive.google.com/file/d/1YhLEEe_jQdq2YJRTR043hGTekk-P3PHT/ view? usp=sharing
III. Organization Breakdown Structure
download by : skknchat@gmail.com
Trang 6For closer speciation here is the link that we did the diagram:
https://drive.google.com/file/d/1Lzb_hDvl8_TRuetitVZzsWZV2kL66SIy/view?
usp=sharing
Cost account table:
1.Market 2.Proposal 3.Finding 4.Purchase 5.Logistic 6.Installation 7.Termination
Trang 7research and evaluation Location Supplier
research team 1.1; 1.2; 1.3; 3.1; 3.2 Marketing
Proposal
department
Transportation
Logistic
Quality
department
IV. Responsibility Matrix
Personnel table:
Transportation
Trang 8download by : skknchat@gmail.com
Trang 9Long Hung Doanh Hai Khoa
Deliverable or Task
Market Research+Evaluation
Task 1: Do market research throughout both online and offline
channels (price, brand name, and other factors)
Choose the most suitable products and supplier
Task 2: Make comparison and evaluation among products R A S Task 3: Choose the most suitable products and supplier R A
Proposal
Task 1: Compose the purchase proposal + budget estimation A R S Task 2: Handle the purchase proposal +Receive the budget(reach
agreement on the date of budget receive, number of budgets, and A R S method of transfer)
Finding location
Task 1: Pick a fixed spot for the water dispensers on each floor S R A Task 2: Pick a spot for water bottles and spare dispensers storage S R A
Purchase
Logistics
Task 1:Decide logistics option and ensure safety requirements R A S Task 2: Receive and check the quality and quantity of the products
at hand
Installation
Termination
Trang 10download by : skknchat@gmail.com
Trang 11Task 1: Send the financial statement and the bill for the school R Task 2: Final inspection of the water-refilling points S A R Task 3: Delegate the responsibility of maintaining and preparing
the dispensers to the authority
V. In-Depth Schedule
A Activity duration table
Activity
Code no Activity Precedence Pessimistic Likely Optimistic Duration
1 Research+evaluation
Do market research throughout both online and offline channels (price, 1.1 brand name, and other factors)
Make comparison and evaluation 1.2 among products
Choose the most suitable products and 1.3 supplier
Proposal prepare +
2 budget estimation
C 2.1 Compose the budget estimation A
Handle the purchase proposal F
+Receive the budget(reach agreement
on date of budget receive, number of 2.4 budget, and method of transfer) E
3 Finding location
Pick a fixed spot for the water
B 3.1 dispensers
Pick a spot for water bottles and spare 3.2 dispensers storage
A
4 Product purchase
Trang 12download by : skknchat@gmail.com
Trang 13H 4.1 Purchase G 2 1 0.5 1
5 Logistic
G
Decide logistics option and ensure
5.1 safety requirements F
I
receipt and check the quality and
5.2 quantity of the products at hand H
6 INSTALLATION
7 TERMINATION
N
Send the financial statement and the
7.1 bill for the school L, K
Delegate the responsibility of
7.3 dispensers to the authority
B AOA chart:
Critical path: A-C-D-E-F-G-H-I-K-N-O.
For closer speciation here is the link that we did the diagram:
https://drive.google.com/file/d/1KX0MgZT0t5s6sb9ZfcMaiQbzd-ZZdZCs/view?
usp=sharing
C Gantt Chart:
Trang 14download by : skknchat@gmail.com
Trang 15For closer speciation here is the link that we did the chart:
https://sharing.clickup.com/g/h/5ebue-124/96bd190e1076fa2
VI. Preliminary risk analysis
1Project staff incompetence
2Chosen supplier do not meet with requirements
3The actual price differs from price estimation
4There is no good location for installation
5 The university doesn't want to grant the project because the cost is too high
6Price higher than estimation
7Unable to record bill
download by : skknchat@gmail.com
Trang 168 The transportation takes longer than expected
9 Issues in transporting goods: not enough quantity, wrong models, damaged goods during transporting
10 Installation error
11 Hotline contact doesn’t work
12 Product defect after shipping to university
13 Authority refuse to take responsibility
14 Overwhelming demand from the students make the service reach capacity
15 Set up inventory and refill
B Qualitative method
Likelihood Low Medium High
Consequences Medium 7, 12 8, 15,11 14
High 1, 4, 13 9 10,5,6
C Quantitative method
risk Pm Pc Pd Pf Cc Cs Cr Cp Cf Scoring Risk factor
0.266 66666
1 0.1 0.5 0.7 67 0.1 0.5 0.3 0.7 0.4 0.56 Moderate risk
0.133
2 0.1 0.3 0.3 33 0.3 0.5 0.3 0.3 0.35 66667 Moderate risk
3 0.1 0.5 0.5 0.2 0.7 0.3 0.1 0.3 0.35 0.48 Moderate risk
4 0.1 0.9 0.9 0.333 0.3 0.9 0.7 0.7 0.65 0.76666 High risk
Trang 17download by : skknchat@gmail.com
Trang 185 0.3 0.9 0.9 0.4 0.1 0.9 0.3 0.7 0.5 0.7High risk
0.466 66666
6 0.7 0.5 0.7 67 0.9 0.5 0.3 0.5 0.55 0.76 High risk
7 0.5 0.5 0.7 0.4 0.7 0.5 0.7 0.7 0.65 0.79High risk
8 0.7 0.3 0.5 0.4 0.1 0.5 0.5 0.5 0.4 0.64 Moderate risk
0.466
9 0.5 0.9 0.9 67 0.1 0.7 0.9 0.9 0.65 33333 High risk
0.533 33333
10 0.7 0.5 0.9 33 0.1 0.7 0.7 0.7 0.55 0.79 High risk
0.466
11 0.7 0.1 0.7 67 0.1 0.1 0.3 0.3 0.2 33333 Moderate risk
0.533 33333
12 0.7 0.3 0.9 33 0.9 0.9 0.9 0.7 0.85 0.93 High risk
13 0.7 0.7 0.5 0.4 0.3 0.7 0.7 0.7 0.6 0.76 High risk
0.466 66666
14 0.7 0.7 0.7 67 0.7 0.5 0.3 0.7 0.55 0.76 High risk
15 0.5 0.5 0.7 0.4 0.7 0.5 0.7 0.5 0.6 0.76 High risk
D Risk Mitigation Strategies
01 Pre-checking of the staff's competence
2 Prepare multiple suppliers with the same quality so we have many options to choose from
03.Try to negotiate and Set-up the contract to get a fixed price first
Trang 19download by : skknchat@gmail.com
Trang 204 Do the research in terms of students behavior to find out where is potential to set up the dispensers (the place students spend most of their time)
5 Figure out the benefits the school can get (student experience => raise profit from raising tuition fee); carefully do the market research to minimize the cost as much as possible
6 Prepare an unexpected budget with the number of 10% of the total budget estimation
7 Record bill through electronic means such as email or taking pictures
8 Call in advance to make sure they remember the schedule and remind them to go on time
9 Set up insurance contract for damaged products in transportation
10 Make sure the installer has installed the dispenser successfully before and print out specific guidelines to follow
11 Get more than one hotline contact from the supplier; check the number before the termination process
12 Set up a term in case of a product defect in the contract (exchange, refund,
warranty, )
13 Work with the authority to find out what they do not satisfy with the project then fix it
14 Create another project, which is expanding the number of bottle-refilling dispensers
15 Find a new inventory near building A such as from the Security room or building B, logistics between those using xe day