Institute Information Project Name Protecting productivity, incomes and trade through improved health surveillance of Vietnam’s plantations Vietnamese Institution Forest Protection Re
Trang 1Ministry of Agriculture & Rural Development
023/07VIE
Protecting productivity, incomes and trade through
improved health surveillance of Vietnam’s plantations
MILESTONE 1 REPORT
Date: 4 September 2008
Trang 2Table of Contents
1 Institute Information 3
2 Project Abstract 4
3 Executive Summary 4
4 Introduction & Background 4
5 Progress to Date _ 6
5.1 Implementation Highlights _ 6 5.2 Smallholder Benefits 6 5.3 Capacity Building 6 5.4 Publicity _ 6 5.5 Project Management 6
6 Report on Cross-Cutting Issues _ 7
6.1 Environment 7 6.2 Gender and Social Issues 7
7 Implementation & Sustainability Issues _ 7
7.1 Issues and Constraints _ 7 7.2 Options 7 7.3 Sustainability 7
8 Next Critical Steps _ 7
9 Conclusion _ 7
10 Statuatory Declaration 7
Trang 3Institute Information
Project Name Protecting productivity, incomes and trade through improved health
surveillance of Vietnam’s plantations
Vietnamese Institution Forest Protection Research Division, Forest Science Institute of
Vietnam
Vietnamese Project Team
Leader
Dr Pham Quang Thu
Australian Organisation Department of Agriculture, Fisheries and Forestry, Office of the Chief
Plant Protection Officer
Australian Personnel Dr Ian Naumann
Date commenced March 2008
Completion date (original) June 2010
Completion date (revised) Feb 2010
Reporting period 5 months to August 2008
Contact Officer(s)
In Australia: Team Leader
Position: Director, SPS Capacity Building
Program
Organisation Department of Agriculture,
Fisheries and Forestry Office of the Chief Plant Protection Officer
In Australia: Administrative contact
Position: Director, SPS Capacity Building
Program
Organisation Department of Agriculture,
Fisheries and Forestry Office of the Chief Plant Protection Officer
v.au
In Vietnam
Position: Head of Forest Protection Research
Division
Organisation Forest Protection Research Division
, Forest Science Institute of Vietnam (FSIV)
Trang 4Project Abstract
Executive Summary
Progress during the first 6 month reporting period has been in accordance with the project Logframe Highlights include:
• Development of Forest Health Surveillance database and field forms
• Preparation for travel to Vietnam to deploy database and assess collections
• Development of baseline survey and draft questionnaire; and
• Procurement of equipment
Key challenges during the next 6 months include fine tuning the database and training FSIV staff in its use, accessing and identifying relevant forestry pest specimens in Vietnamese collections, and preparing for the upcoming training workshop to be held in Australia in early 2008
The rapid expansion of Vietnam’s forest coverage, provides opportunities for new international
export markets for timber products However, it also represents new and increased risks from
forestry pests Comprehensive surveillance and a database of pest and disease records are critical
to detecting incursions, managing outbreaks of pests and diseases, and producing pest lists
This project aims to establish a forest pest and disease database and reference collection, provide
training on pest surveillance and risk assessment, and establish a network of observation centres
supported by linkages with relevant national and regional organisations The project outputs will support forest pest detection and management, as well as provide the expertise and records to
underpin market access opportunities
Key achievements during the reporting period include:
• Development of Forest Health Surveillance database and field forms for distribution to
regional centres
• Preparation for travel to Vietnam to deploy database and assess collections
• Development of baseline survey and draft questionnaire
• Procurement of equipment
Trang 5Introduction & Background
Project objectives and outputs expected are as follows:
Objective 1 To establish a forest pest and disease database and reference collection
Output 1.1 Operational specimen-based forest pest and disease database
Output 1.2 Identify key pests and diseases for each of the main plantation species grown in
Vietnam; reference material of these pests and diseases assembled
Objective 2 To provide training on forest health surveillance, damage assessment, pest risk analysis,
collection, preservation, identification and curation and to increase awareness and understanding of forest health surveillance among stakeholders
Output 2.1 Surveillance training program for staff from regional research centres
Output 2.2 Monitor awareness, knowledge, attitudes and practices of key stakeholder groups
towards forest health surveillance in Vietnam
Output 2.3 Extension material produced detailing symptoms and management options for key
pests and diseases
Objective 3 To establish and equip a pilot network of observation centres based on FSIV regional centres
supplemented by provincial Departments of Crop Protection
Output 3.1 Network of suitably equipped surveillance centres established at 3 regional centres
throughout Vietnam
Output 3.2 Ongoing Forest Health Surveillance and Static trapping Programs initiated in each
regional centre
Output 3.3 Forest Health Guide developed from existing data and data collected during training
Objective 4 To create linkages between Forestry, Agriculture and Quarantine agencies within Vietnam
and with regional and international organisations
Output 4.1 Joint training in surveillance and diagnostics for FSIV and MARD
Output 4.2 Information routinely exchanged between MARD and FSIV
Objective 5 Manage and report on the project
The approach and methodology to achieve these objectives and outputs includes:
• Developing and deploying a Forest Health Surveillance database, incorporating existing material from FSIV collections and records and incorporation of new FHS records
• Accessing and identifying relevant material in existing insect collections in Vietnam
• Providing practical training in forest health surveillance skills in Australia and Vietnam supported
by training materials
• Preparing extension material and Forest Health Guide for FSIV staff and tree growers
Trang 6Progress to Date
1 Implementation Highlights
General
• Preliminary database design completed and plans prepared for deployment
• Plans for baseline survey, assessment of collections, and procurement of equipment completed
Objective 1
Output 1.1 Operational specimen-based forest pest and disease database
• Database development and planning workshop held
• Database field form prepared
• Documentation to accompany field forms currently being prepared
• Plans made for travel to Vietnam to deploy database, provide initial training, and assess
collections
Output 1.2 Identify key pests and diseases for each of the main plantation species grown in Vietnam
• Preliminary pest list collated from available resources
Objective 2
Output 2.2 Monitor awareness, knowledge, attitudes and practices of key stakeholder groups towards
forest health surveillance in Vietnam
• Plans for baseline survey and draft questionnaire in place
Objective 3
Output 3.1 Network of suitably equipped surveillance centres established at 3 regional centres throughout
Vietnam
• Equipment purchased or ordered for provision to regional centres It is anticipated that items will
be delivered progressively to Vietnam commencing in October 2008
Refer to the attached Progress Report Logframe for further details
2 Smallholder Benefits
The stakeholder survey was developed with consideration for assessing the current knowledge and future requirements of smallholders with respect to forestry pest and disease issues
3 Capacity Building
Principal capacity-building activities will commence during the visit to Vietnam in October and with the workshop in Australia in February 2009 Preparations for both activities are underway
4 Publicity
No major significant publicity has occurred during the past 6 months
Delays in the signing of the contract between DAFF and Queensland DPI&F caused delays in initiation of some project activities
Trang 7Ms Wendy Lee, Office of the Chief Plant Protection Officer (OCPPO), DAFF has assumed project-officer responsibilities for the project in Canberra, in support of Dr Naumann
Communication between project staff in Australia and Vietnam has been good Canberra- and Brisbane-based staff have held several teleconferences and one face-to-face meeting (31 July 2008) Brisbane- and Hanoi-based staff work together by email; exchanges have facilitated planning for the database, base-line survey and travel to Vietnam
Report on Cross-Cutting Issues
There have been no major (negative) environmental issues associated with the Project to date
2 Gender and Social Issues
There has been no opportunity to assess gender or social impacts in the project to date
Implementation & Sustainability Issues
1 Issues and Constraints
• To date, there have been no major issues or constraints affecting the overall planned objectives and outputs Minor problems have arisen following delays in signing of contract between DAFF and DPI&F, causing some delay in preparation of travel documents and equipment procurement
Nothing to report at this stage
3 Sustainability
Nothing to report at this stage
Next Critical Steps
Next critical steps in the project are:
• Fine tuning database, installing the database on FSIV computers and providing training in data-entry and the production of reports
• Accessing and identifying specimens from FSIV, MARD and NIPP insect collection is Hanoi
• Preparing materials and activities for training workshop in Australia
Conclusion
At this early stage the project is progressing well overall, with most planned activities either complete or well-advanced The visit to Hanoi in October will be critical to the project with the deployment of the database and inclusion of existing records After this visit the extent and value of existing collections will
be better understood
Statutory Declaration
The CARD contract is a lump sum outputs based contract CARD does not require institutions to submit receipts (although they need to be retained by institutions for accounting and taxation purposes) CARD
Trang 8does need to be assured that the inputs detailed in the Contract Schedules have been delivered The statutory declaration below is to be used to provide this assurance
Trang 9Project Progress Against Proposed Objectives, Outputs, Activities And Inputs
Project Title: Protecting productivity, incomes and trade through improved health surveillance of Vietnam’s plantations
Vietnamese Implementing Institution: Forest Protection Research Division, Forest Science Institute of Vietnam:
Narrative Information
Required
Performance Measures
Assumptions Information Required
Objective 1 To establish a forest
pest and disease
database and
reference collection
Database developed and being used by project participants; voucher specimens routinely added
to collection and collection maintained
Training gives participants confidence to use and maintain database and reference collection
Project objective still relevant
No need to modify logframe
Output 1.1 Operational
specimen-based
forest pest and
disease database
Forest pest and disease database developed, tested and being used
operationally by FSIV participants
Specimens can be identified reliably
Output still relevant and achievable.
forest health database
for Vietnam:
development and
planning/training
workshop
Database suitable for forest health surveillance data developed
Planning/training meeting takes place
Compatibility can be achieved between forest health surveillance database and National Phytosanitary Database
• Database development and planning workshop held in Brisbane on 31 July
2008, attended by Ian Naumann, Simon Lawson, Judy King, Manon Griffiths and Suzanne Brangwin (UniQuest Pty Ltd) Decision to base database on existing QDPI&F Forest Health Surveillance database, modifying fields to suit Vietnamese situation
• Database field form prepared and forwarded to FSIV staff in Vietnam for confirmation of suitability to Vietnamese situation Following modification as required, field forms
to be translated into Vietnamese for distribution to field stations
• Documentation to accompany field forms currently being prepared
examination and
validation of existing
forestry collections in
Vietnam
Existing collections examined and validated by QDPI&F and other international experts
Existing collections are sufficiently representative of pests and diseases to provide reasonable basis for planning diagnostic training
Plans for travel to Vietnam to deploy database, provide initial training, and assess collections
• Airfares for Judy King and Manon Griffiths booked for
18-27 October 2008
• Internal DPI&F travel forms prepared and submitted
records into forest
health database
Additional taxonomic, spatial and temporal data added to database
Surveillance undertaken by staff
of regional centres
Not addressed during current reporting period
Output 1.2 Identify key pests
and diseases for each
of the main
plantation species
grown in Vietnam;
reference material of
these pests and
diseases assembled
Target list of key pests and diseases developed for future training workshops and production of extension material
Reference collections established
Pest and diseases are tractable for diagnostic training given facilities in Vietnam
Output still relevant and achievable.
Trang 10Activity 1.2.1 Identify key pests
and diseases based on
narrative data from
field staff data and
existing records
List includes organisms to account for most known damage and outbreaks
Narrative data from field staff can be collated
Preliminary pest list collated from available resources including:
• ACIAR project Acacia and Eucalypt pest lists
• MARD forestry pest lists
• GBIV database records
collections of key
pests and diseases at
FSIV, Hanoi
Reference collections meet modern curatorial standards
Appropriate facilities (e.g space and climate control) available for storage
of pest and disease specimens
Not addressed during current reporting period
Objective 2 To provide training
on forest health
surveillance, damage
assessment, pest risk
analysis, collection,
preservation,
identification and
curation, and to
increase awareness
and understanding of
forest health
surveillance among
stakeholders
Vietnamese participants trained in surveillance techniques and identification of key pests and disease and awareness and understanding of benefits of surveillance enhanced among stakeholders
Turnover and movement of staff prevents acquisition and utilisation of required skills
Comprehensive pest lists may not be achievable within the time frame of the project
Project objective still relevant
No need to modify logframe
Output 2.1 Surveillance training
program for staff
from regional
research centres
Training workshops in Years 1 (Australia) & 2 (Vietnam) delivered for total of 70 Vietnamese participants
Appropriate participants selected for training
Output still relevant and achievable
Workshop 1
(Australia)
Representatives of FSIV, Hanoi and two regional centres participate in training workshop covering key pests and diseases (in Australia)
Training in Australia
is relevant to Vietnamese forest systems
Training workshop dates confirmed for 16-26 February 2009
Preliminary workshop program prepared
Output 2.2 Monitor awareness,
knowledge, attitudes
and practices of key
stakeholder groups
towards forest health
surveillance in
Vietnam
Enhanced awareness and knowledge, more appropriate responses from key stakeholders
Survey results are not confounded by desire among stakeholders
to please Survey during final year of project reflects durable changes in attitudes
Output still relevant and achievable
knowledge, attitudes
and practices among
key stakeholders
Responses from all major stakeholder groups
Key stakeholders participate in survey
Plans for baseline survey and draft questionnaire in place
• Questionnaires for Tree growers and FSIV regional staff prepared and forwarded to Vietnam for translation
• Correspondence with Vietnamese project leader in preparation for distribution of surveys to regional centres and tree growers
Objective 3 To establish and
equip a pilot network
of observation
centres based on
FSIV regional centres
supplemented by
provincial
Departments of Crop
Protection.
Pilot observation centre network established &
equipped appropriately according to regional needs.
Regional centres have resources to undertake on-going surveillance
Project objective still relevant
No need to modify logframe
Output 3.1 Network of suitably
equipped surveillance
centres established at
Pilot regional surveillance network operational
Output still relevant and achievable.